F5W61608 USPFO Warehouse Ohio Army National Guard Rev. 0 Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final
SUMMARY (SCOPE OF WORK) 011000 – 1
SECTION 011000 – SUMMARY (SCOPE OF WORK)
PART 1 - GENERAL
1.1 SUMMARY - (SCOPE OF WORK)
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Type of the Contract.
3. Work under other contracts.
4. Use of premises.
5. Work restrictions.
6. Specification formats and conventions.
B. Related Sections include the following:
1. Section 010000 “General Requirements”.
2. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Government's facilities.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Identification: Ohio Army National Guard, USPFO Warehouse.
1. Project Location: Columbus, Ohio.
B. Building Owner: Ohio Army National Guard.
C. Property Owner: Ohio Army National Guard
1.3 WORK DESCRIPTION
A. Summary Scope of Work
The project includes complete construction to the extent indicated on the Drawings and in the Specifications of a facility that provides training for the Army National Guard with 69,880 sq. ft. total, excluding 514 sq. ft. programmed for the Controlled Waste Handling Facility in a detached hazmat container. Project includes mobili-zation, site work, construction, site restoration, systems testing and training, and demobilization and commissioning. Site work generally consists of POV and cus-tomer parking, access aprons, loading dock/ramp access, drives, general storm water control/detention, utilities, sidewalks, and other miscellaneous site features as appropriate to this type of facility.
1.4 TYPE OF CONTRACT
A. Project will be constructed under a single prime contract.
Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final
SUMMARY (SCOPE OF WORK) 011000 – 2
B. Work Not in Contract (N.I.C.) – All items indicated on the Drawings or in the Specifica-tions as N.I.C. will be furnished and installed by the Government.
1.5 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Co-ordinate the Work of this Contract with work performed under separate contracts.
1.6 USE OF PREMISES
A. General: Contractor shall have full use of premises for construction operations, includ-ing use of Project site, during construction period. Contractor's use of premises is lim-ited only by Government's right to perform work or to retain other contractors on por-tions of Project.
B. Use of Site: Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1.7 WORK RESTRICTIONS
A. Workweek shall be Monday through Friday, 6:00 AM through 6:00 PM, except Gov-ernment observed holidays, as follows:
1. New Years Day.
2. Martin Luther King's Birthday.
3. Presidents Day.
4. Memorial Day.
5. Independence Day.
6. Labor Day.
7. Columbus Day.
8. Veterans Day.
9. Thanksgiving Day.
10. Christmas Day.
1.8 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections us-ing the 50-division format and CSI/CSC's "MasterFormat" numbering system.
1. Section Identification: The Specifications use Section numbers and titles to help cross-referencing in the Contract Documents. Sections in the Project Manual are in numeric sequence; however, the sequence is incomplete because all available Section numbers are not used. Consult the table of contents at the beginning of the Project Manual to determine numbers and names of Sections in the Contract Documents.
2. Division 01: Sections in Division 01 govern the execution of the Work of all Sec-tions in the Specifications.
Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final
SUMMARY (SCOPE OF WORK) 011000 – 3
B. Specification Content: The Specifications use certain conventions for the style of lan-guage and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropri-ate. Words implied, but not stated, shall be inferred as the sense requires. Singu-lar words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifica-tions. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
a. The words "shall," "shall be," or "shall comply with," depending on the con-text, are implied where a colon (:) is used within a sentence or phrase.
1.9 GENERAL REQUIREMENTS
A. The General CONTRACTOR shall be thoroughly familiar with the Drawings and Speci-fications to ensure against misunderstanding between trades during entire construction of the Project.
B. Before construction begins, a construction schedule shall be prepared by the CONTRACTOR and reviewed/approved by the CONTRACTING OFFICER.
1.10 MISCELLANEOUS REQUIREMENTS
A. Rough-In: All rough-in for all items of work and materials indicated on the Drawings or in the Specifications, except as may be specifically excluded, shall be furnished and in-stalled, complete, by the CONTRACTOR.
B. Demolition: All demolition work shall proceed with due care and safety for personnel and pedestrians. All operations shall be planned to cause the minimum amount of in-terference with normal routine and functioning of existing facilities.
C. Preservation and Restoration of Property: CONTRACTOR shall be responsible for the preservation of all public and private property on the surface or underground, along and adjacent to the work, and shall conduct their operations in a manner that will en-sure against injury or damage thereto.
D. Where any direct or indirect damage is done to public or private property by or on ac-count of any act, omission, neglect or misconduct in the execution of the work, or be-cause of non-execution thereof, on the part of the CONTRACTOR, such property shall be restored by the CONTRACTOR, at no cost to the GOVERNMENT, to a condition equal to that existing before such damage was done, by repairing, rebuilding or other-wise restoring same in a manner acceptable to the GOVERNMENT.
Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final
SUMMARY (SCOPE OF WORK) 011000 – 4
E. All work performed under this Contract shall proceed with due care and safety for all personnel and pedestrians. All work shall be planned so that the Project can be se-cured against unauthorized entry at the end of each working day.
F. Although every endeavor has been made, on the Drawings and in Specifications to show all new and existing conditions, it will be the CONTRACTOR's responsibility to fully and carefully evaluate drawings and jobsite conditions prior to submitting the bid proposal. It is not the intent of the Contract to pay the CONTRACTOR for work due to minor deviations from Drawings and Specifications.
1.11 SAFETY REQUIREMENTS
A. The CONTRACTOR shall provide and maintain all necessary fences, barricades and other reasonable safeguards required to ensure the safety of all personnel.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .