055213 pipe and tube railings.pdf
PDF 17 KB Posted
- Attached to
- CONSTRUCT CSMS PHASE II Federal contract opportunity
- Solicitation number
- W91364-09-B-0002
About this file
09B000255213 pipe and tube railings.pdf
View the file
Other files for this federal contract opportunity
Show all 50
CONSTRUCT CSMS PHASE II has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
F5W61607 Combined Support Maintenance Shop - Phase II Ohio Army National Guard Rev. 0 Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final
PIPE AND TUBE RAILINGS 055213 - 1
SECTION 055213 - PIPE AND TUBE RAILINGS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Steel pipe and tube railings.
B. See Division 05 Section "Ladders" for steel tube railings associated with metal stairs.
1.2 PERFORMANCE REQUIREMENTS
A. Delegated Design: Design railings, including comprehensive engineering analysis by a qualified professional engineer, using performance requirements and design criteria indicated.
B. Structural Performance: Railings shall withstand the effects of gravity loads and the following loads and stresses within limits and under conditions indicated:
1. Handrails and Top Rails of Guards:
a. Uniform load of 50 lbf/ ft. applied in any direction.
b. Concentrated load of 200 lbf applied in any direction.
c. Uniform and concentrated loads need not be assumed to act concurrently.
2. Infill of Guards:
a. Concentrated load of 50 lbf applied horizontally on an area of 1 sq. ft.
b. Infill load and other loads need not be assumed to act concurrently.
C. Control of Corrosion: Prevent galvanic action and other forms of corrosion by insulating metals and other materials from direct contact with incompatible materials.
1.3 SUBMITTALS
A. Product Data: For the following:
1. Manufacturer's product lines of mechanically connected railings.
2. Railing brackets.
3. Grout, anchoring cement, and paint products.
Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final
PIPE AND TUBE RAILINGS 055213 - 2
B. LEED Submittals:
1. Product Data for Credit MR 4.1 and Credit MR 4.2: Indicating percentages by weight of postconsumer and preconsumer recycled content for products having recycled content. Include statement indicating costs for each product having recycled content.
C. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work.
D. Samples: For each type of exposed finish required.
E. Delegated-Design Submittal: For installed products indicated to comply with performance requirements and design criteria, including analysis data signed and sealed by the qualified professional engineer responsible for their preparation.
F. Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified testing agency, according to ASTM E 894 and ASTM E 935.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
1. Steel Pipe and Tube Railings:
a. Pisor Industries, Inc.
b. Wagner, R & B, Inc.; a division of the Wagner Companies.
c. Approved equal.
2.2 METALS, GENERAL
A. Brackets, Flanges, and Anchors: Cast or formed metal of same type of material and finish as supported rails unless otherwise indicated.
2.3 STEEL AND IRON
A. Recycled Content of Steel Products: Provide products with average recycled content of steel products so postconsumer recycled content plus one-half of preconsumer recycled content is not less than 25 percent.
B. Tubing: ASTM A 500 (cold formed) or ASTM A 513.
Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final
PIPE AND TUBE RAILINGS 055213 - 3
C. Pipe: ASTM A 53/A 53M, Type F or Type S, Grade A, Standard Weight (Schedule 40), unless another grade and weight are required by structural loads.
1. Provide galvanized finish for exterior installations and where indicated.
D. Plates, Shapes, and Bars: ASTM A 36/A 36M.
E. Cast Iron: Either gray iron, ASTM A 48/A 48M, or malleable iron, ASTM A 47/A 47M, unless otherwise indicated.
2.4 MISCELLANEOUS MATERIALS
A. Fasteners: Provide the following:
1. Hot-Dip Galvanized Railings: Type 304 stainless-steel or hot-dip zinc-coated steel fasteners complying with ASTM A 153/A 153M or ASTM F 2329 for zinc coating.
B. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy welded.
C. Etching Cleaner for Galvanized Metal: Complying with MPI#25.
D. Galvanizing Repair Paint: High-zinc-dust-content paint complying with SSPC- Paint 20 and compatible with paints specified to be used over it.
E. Shop Primer for Galvanized Steel: Zinc-dust, zinc-oxide primer formulated for priming zinc-coated steel and for compatibility with finish paint systems indicated, and complying with SSPC-Paint 5.
F. Bituminous Paint: Cold-applied asphalt emulsion complying with ASTM D 1187.
G. Nonshrink, Nonmetallic Grout: Factory-packaged, nonstaining, noncorrosive, nongaseous grout complying with ASTM C 1107. Provide grout specifically recommended by manufacturer for interior and exterior applications.
2.5 FABRICATION
A. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch unless otherwise indicated. Remove sharp or rough areas on exposed surfaces.
B. Form work true to line and level with accurate angles and surfaces.
Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final
PIPE AND TUBE RAILINGS 055213 - 4
C. Welded Connections: Cope components at connections to provide close fit, or use fittings designed for this purpose. Weld all around at connections, including at fittings.
1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.
2. Obtain fusion without undercut or overlap.
3. Remove flux immediately.
4. At exposed connections, finish exposed surfaces smooth and blended so no roughness shows after finishing and welded surface matches contours of adjoining surfaces.
D. Nonwelded Connections: Connect members with concealed mechanical fasteners and fittings. Fabricate members and fittings to produce flush, smooth, rigid, hairline joints.
E. Form changes in direction by bending .
F. Bend members in jigs to produce uniform curvature without buckling or otherwise deforming exposed surfaces.
G. Close exposed ends of railing members with prefabricated end fittings.
H. Provide wall returns at ends of wall-mounted handrails unless otherwise indicated.
I. Brackets, Flanges, Fittings, and Anchors: Provide wall brackets, flanges, miscellaneous fittings, and anchors to interconnect railing members to other work unless otherwise indicated.
1. At brackets and fittings fastened to plaster or gypsum board partitions, provide crush-resistant fillers to transfer loads through wall finishes.
2.6 STEEL AND IRON FINISHES
A. Galvanized Railings:
1. Hot-dip galvanize exterior steel and iron railings, including hardware, after fabrication.
2. Comply with ASTM A 123/A 123M for hot-dip galvanized railings.
3. Comply with ASTM A 153/A 153M for hot-dip galvanized hardware.
B. Preparing Galvanized Railings for Shop Priming: After galvanizing, thoroughly clean railings of grease, dirt, oil, flux, and other foreign matter, and treat with etching cleaner.
C. Primer Application: Apply shop primer to prepared surfaces of railings unless otherwise indicated. Comply with requirements in SSPC-PA 1, "Paint Application
Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final
PIPE AND TUBE RAILINGS 055213 - 5
Specification No. 1: Shop, Field, and Maintenance Painting of Steel," for shop painting.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Set railings accurately in location, alignment, and elevation; measured from established lines and levels and free of rack.
1. Do not weld, cut, or abrade surfaces of railing components that have been coated or finished after fabrication and that are intended for field connection by mechanical or other means without further cutting or fitting.
2. Set posts plumb within a tolerance of 1/16 inch in 3 feet.
3. Align rails so variations from level for horizontal members and variations from parallel with rake of steps and ramps for sloping members do not exceed 1/4 inch in 12 feet.
B. Anchor posts in concrete by inserting into formed or core-drilled holes and grouting annular space.
C. Anchor railing ends at walls with round flanges anchored to wall construction.
D. Attach railings to wall with wall brackets, except where end flanges are used. Use type of bracket with flange tapped for concealed anchorage to threaded hanger bolt.
E. Secure wall brackets and railing end flanges to building construction as follows:
1. For concrete and solid masonry anchorage, use drilled-in expansion shields and hanger or lag bolts.
2. For hollow masonry anchorage, use toggle bolts.
3. For steel-framed partitions, use hanger or lag bolts set into fire-retardant-treated wood backing between studs. Coordinate with stud installation to locate backing members.
3.2 ADJUSTING AND CLEANING
A. Touchup Painting: Immediately after erection, clean field welds, bolted connections, and abraded areas of shop paint, and paint exposed areas with the same material as used for shop painting to comply with SSPC-PA 1 for touching up shop-painted surfaces.
Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final
PIPE AND TUBE RAILINGS 055213 - 6
B. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair galvanizing to comply with ASTM A 780.
END OF SECTION 055213