271100 communications equipment room fittings.pdf

PDF 24 KB Posted

Attached to
CONSTRUCT CSMS PHASE II
Solicitation number
W91364-09-B-0002
Issued by

About this file

271100 communications equipment room fittings.pdf

View the file

Other files

File Type Posted
Bid Abstract 09-B-0002.pdf PDF
09-B-0002 Amendment 4.pdf PDF
ADDENDUM NO 02 CSMS PH II Narrative SENT.pdf PDF
ADDENDUM NO 03 CSMS PH II Narrative.pdf PDF
09-B-0002 Amendment 2.pdf PDF
CSMS PH II Addendum.pdf PDF
Bid Questions CSMS phase II JACOBS RESPONSES JFK.doc DOC document
e1w13300.PDF PDF
L502.pdf PDF
CSMS268 Layout1 —
CSM-A721W .pdf PDF
CSM-G000W-VOL2.pdf PDF
CSMP404W.pdf PDF
CSMM312aW.pdf PDF
CSM-A102W .pdf PDF
C100.pdf PDF
CSM-I101W .pdf PDF
CSM-A421W .pdf PDF
C301.pdf PDF
CSMS218W Layout1 —
CSMP402W.pdf PDF
CSMM312cW.pdf PDF
C604.pdf PDF
CSM-A701W .pdf PDF
CSMP602W.pdf PDF
CSMF401W.pdf PDF
CSM-A810W .pdf PDF
CSM-A322W .pdf PDF
CSMF317W.pdf PDF
CSM-A323W .pdf PDF
C402.pdf PDF
CSM-G116W .pdf PDF
E-301.pdf PDF
CSM-A251W .pdf PDF
CSM-G126W .pdf PDF
E-418.pdf PDF
CSMS219W Layout1 —
E-706.pdf PDF
CSMS306W Layout1 —
CSM-A518W .pdf PDF
E-104.pdf PDF
CSMM005W.pdf PDF
CSMS303W Layout1 —
CSMM314aW.pdf PDF
E-105.pdf PDF
CSMM204W.pdf PDF
CSMM314cW.pdf PDF
CSMP311W.pdf PDF
CSM-A712W .pdf PDF
CSM-A822W .pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F5W61607 Combined Support Maintenance Shop - Phase II Ohio Army National Guard Rev. 0 Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

COMMUNICATIONS EQUIPMENT ROOM FITTINGS 271100 - 1

SECTION 271100 - COMMUNICATIONS EQUIPMENT ROOM FITTINGS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Telecommunications mounting elements.

2. Backboards.

3. Telecommunications equipment racks and cabinets.

4. Telecommunications service entrance pathways.

5. Grounding.

B. Related Sections:

1. Division 27 Section "Communications Backbone Cabling" for voice and data cabling associated with system panels and devices.

2. Division 27 Section "Communications Horizontal Cabling" for voice and data cabling associated with system panels and devices.

1.3 DEFINITIONS

A. Basket Cable Tray: A fabricated structure consisting of wire mesh bottom and side rails.

B. BICSI: Building Industry Consulting Service International.

C. Channel Cable Tray: A fabricated structure consisting of a one-piece, ventilated-bottom or solid-bottom channel not exceeding 6 inches in width.

D. Ladder Cable Tray: A fabricated structure consisting of two longitudinal side rails connected by individual transverse members (rungs).

E. LAN: Local area network.

F. RCDD: Registered Communications Distribution Designer.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

COMMUNICATIONS EQUIPMENT ROOM FITTINGS 271100 - 2

G. Solid-Bottom or Nonventilated Cable Tray: A fabricated structure consisting of a bottom without ventilation openings within integral or separate longitudinal side rails.

H. Trough or Ventilated Cable Tray: A fabricated structure consisting of integral or separate longitudinal rails and a bottom having openings sufficient for the passage of air and using 75 percent or less of the plan area of the surface to support cables.

1.4 PERFORMANCE REQUIREMENTS

A. Seismic Performance: Floor-mounted cabinets and cable pathways shall withstand the effects of earthquake motions determined according to SEI/ASCE 7.

1. The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces specified."

1.5 SUBMITTALS

A. Product Data: For each type of product indicated. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes for equipment racks and cabinets. Include rated capacities, operating characteristics, electrical characteristics, and furnished specialties and accessories.

B. Shop Drawings: For communications equipment room fittings. Include plans, elevations, sections, details, and attachments to other work.

1. Detail equipment assemblies and indicate dimensions, weights, loads, required clearances, method of field assembly, components, and location and size of each field connection.

2. Equipment Racks and Cabinets: Include workspace requirements and access for cable connections.

3. Grounding: Indicate location of grounding bus bar and its mounting detail showing standoff insulators and wall mounting brackets.

C. Qualification Data: For Installer, qualified layout technician, installation supervisor, and field inspector.

D. Seismic Qualification Certificates: For floor-mounted cabinets, accessories, and components, from manufacturer.

1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation.

2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions. Base certification on the maximum number of components capable of being mounted in each rack type. Identify components on which certification is based.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

COMMUNICATIONS EQUIPMENT ROOM FITTINGS 271100 - 3

3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: Cabling Installer must have personnel certified by BICSI on staff.

1. Layout Responsibility: Preparation of Shop Drawings shall be under the direct supervision of RCDD.

2. Installation Supervision: Installation shall be under the direct supervision of Level 2 Installer, who shall be present at all times when Work of this Section is performed at Project site.

3. Field Inspector: Currently registered by BICSI as RCDD to perform the on-site inspection.

B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

C. Telecommunications Pathways and Spaces: Comply with TIA/EIA-569-B.

D. Grounding: Comply with ANSI-J-STD-607-A.

1.7 PROJECT CONDITIONS

A. Environmental Limitations: Do not deliver or install equipment frames and cable trays until spaces are enclosed and weathertight, wet work in spaces is complete and dry, and work above ceilings is complete.

1.8 COORDINATION

A. Coordinate layout and installation of communications equipment with Owner's telecommunications and LAN equipment and service suppliers. Coordinate service entrance arrangement with local exchange carrier.

1. Meet jointly with Ohio Army National Guard IT Personnel, telecommunications and LAN equipment suppliers, local exchange carrier representatives, and Owner to exchange information and agree on details of equipment arrangements and installation interfaces.

2. Record agreements reached in meetings and distribute them to other participants.

3. Adjust arrangements and locations of distribution frames, cross-connects, and patch panels in equipment rooms to accommodate and optimize arrangement and space requirements of telephone switch and LAN equipment.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

COMMUNICATIONS EQUIPMENT ROOM FITTINGS 271100 - 4

4. Adjust arrangements and locations of equipment with distribution frames, cross-connects, and patch panels of cabling systems of other communications, electronic safety and security, and related systems that share space in the equipment room.

B. Coordinate location of power raceways and receptacles with locations of communications equipment requiring electrical power to operate.

PART 2 - PRODUCTS

2.1 PATHWAYS

A. General Requirements: Comply with TIA/EIA-569-B.

B. Cable Support: NRTL labeled. Cable support brackets shall be designed to prevent degradation of cable performance and pinch points that could damage cable. Cable tie slots fasten cable ties to brackets.

1. Comply with NFPA 70 and UL 2043 for fire-resistant and low-smoke-producing characteristics.

2. Support brackets with cable tie slots for fastening cable ties to brackets.

3. Lacing bars, spools, J-hooks, and D-rings.

4. Straps and other devices.

C. Cable Trays:

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Cablofil Inc.

b. Cooper B-Line, Inc.

c. Cope - Tyco/Allied Tube & Conduit.

d. GS Metals Corp.

2. Cable Tray Materials: Metal, suitable for indoors and protected against corrosion by electroplated zinc galvanizing, complying with ASTM B 633, Type 1, not less than 0.000472 inch thick.

a. Basket Cable Trays: 8 inches wide and 2 inches deep. Wire mesh spacing shall not exceed 2 by 4 inches.

D. Conduit and Boxes: Comply with requirements in Division 26 Section "Raceway and Boxes for Electrical Systems." Flexible metal conduit shall not be used.

1. Outlet boxes shall be no smaller than 4 inches wide, 4 inches high, and 2-1/2 inches deep.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

COMMUNICATIONS EQUIPMENT ROOM FITTINGS 271100 - 5

2.2 BACKBOARDS

A. Backboards: Plywood, fire-retardant treated, 3/4 by 48 by 96 inches. Comply with requirements for plywood backing panels specified in Division 06 Section "Rough Carpentry."

2.3 EQUIPMENT CABINETS AND RACKS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following

1. APC.

2. Cooper B-Line, Inc.

3. Ortronics, Inc.

4. Siemon Co. (The).

B. General Frame Requirements:

1. Distribution Frames: Freestanding and wall-mounting, modular-steel units designed for telecommunications terminal support and coordinated with dimensions of units to be supported.

2. Module Dimension: Width compatible with EIA 310 standard, 19-inch panel mounting.

3. Finish: Manufacturer's standard, baked-polyester powder coat.

C. Floor-Mounted Racks: Modular-type, steel construction.

1. Vertical and horizontal cable management channels, top and bottom cable troughs, grounding lug, and a power strip.

2. Baked-polyester powder coat finish.

D. Modular Freestanding Cabinets:

1. Removable and lockable side panels.

2. Hinged and lockable front and rear doors.

3. Adjustable feet for leveling.

4. Screened ventilation openings in the roof and rear door.

5. Cable access provisions in the roof and base.

6. Grounding bus bar.

7. Rack-mounted, 550-cfm fan with filter.

8. Power strip.

9. Baked-polyester powder coat finish.

10. All cabinets keyed alike.

E. Modular Wall Cabinets:

1. Wall mounting.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

COMMUNICATIONS EQUIPMENT ROOM FITTINGS 271100 - 6

2. Steel construction.

3. Treated to resist corrosion.

4. Lockable front doors.

5. Louvered side panels.

6. Cable access provisions top and bottom.

7. Grounding lug.

8. Rack-mounted, 250-cfm fan.

9. Power strip.

10. All cabinets keyed alike.

F. Cable Management for Equipment Frames:

1. Metal, with integral wire retaining fingers.

2. Baked-polyester powder coat finish.

3. Vertical cable management panels shall have front and rear channels, with covers.

4. Provide horizontal crossover cable manager at the top of each relay rack, with a minimum height of two rack units each.

2.4 POWER STRIPS

A. Power Strips: Comply with UL 1363.

1. Rack mounting.

2. Six, 20-A, 120-V ac, NEMA WD 6, Configuration 5-20R receptacles.

3. LED indicator lights for power and protection status.

4. LED indicator lights for reverse polarity and open outlet ground.

5. Circuit Breaker and Thermal Fusing: When protection is lost, circuit opens and cannot be reset.

6. Circuit Breaker and Thermal Fusing: Unit continues to supply power if protection is lost.

7. Cord connected with 15-foot line cord.

8. Rocker-type on-off switch, illuminated when in on position.

9. Peak Single-Impulse Surge Current Rating: 33 kA per phase.

10. Protection modes shall be line to neutral, line to ground, and neutral to ground.

UL 1449 clamping voltage for all 3 modes shall be not more than 330 V.

2.5 GROUNDING

A. Comply with requirements in Division 26 Section "Grounding and Bonding for Electrical Systems." for grounding conductors and connectors.

B. Telecommunications Main Bus Bar:

1. Connectors: Mechanical type, cast silicon bronze, solderless compression-type wire terminals, and long-barrel, two-bolt connection to ground bus bar.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

COMMUNICATIONS EQUIPMENT ROOM FITTINGS 271100 - 7

2. Ground Bus Bar: Copper, minimum 1/4 inch thick by 4 inches wide with 9/32-inch holes spaced 1-1/8 inches apart.

3. Stand-Off Insulators: Comply with UL 891 for use in switchboards, 600 V.

Lexan or PVC, impulse tested at 5000 V.

C. Comply with ANSI-J-STD-607-A.

2.6 LABELING

A. Comply with TIA/EIA-606-A and UL 969 for a system of labeling materials, including label stocks, laminating adhesives, and inks used by label printers.

PART 3 - EXECUTION

3.1 ENTRANCE FACILITIES

A. Contact telecommunications service provider and arrange for installation of demarcation point, protected entrance terminals, and a housing when so directed by service provider.

B. Install underground pathways complying with recommendations in TIA/EIA-569-B, "Entrance Facilities" Article.

3.2 Install underground entrance pathway complying with Division 26 Section "Raceway and Boxes for Electrical Systems "INSTALLATION

A. Comply with NECA 1.

B. Comply with BICSI TDMM for layout and installation of communications equipment rooms.

C. Cable Trays: Comply with NEMA VE 2 and TIA/EIA-569-A-7.

D. Bundle, lace, and train conductors and cables to terminal points without exceeding manufacturer's limitations on bending radii. Install lacing bars and distribution spools.

3.3 FIRESTOPPING

A. Comply with requirements in Division 07 Section "Penetration Firestopping."Comply with TIA/EIA-569-B, Annex A, "Firestopping."

B. Comply with BICSI TDMM, "Firestopping Systems" Article.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

COMMUNICATIONS EQUIPMENT ROOM FITTINGS 271100 - 8

3.4 GROUNDING

A. Install grounding according to BICSI TDMM, "Grounding, Bonding, and Electrical Protection" Chapter.

B. Comply with ANSI-J-STD-607-A.

C. Locate grounding bus bar to minimize the length of bonding conductors. Fasten to wall allowing at least 2-inch clearance behind the grounding bus bar. Connect grounding bus bar with a minimum No. 3/0 grounding electrode conductor from grounding bus bar to suitable electrical building ground.

D. Bond metallic equipment to the grounding bus bar, using No. 6 AWG equipment grounding conductor.

1. Bond the shield of shielded cable to the grounding bus bar in communications rooms and spaces.

3.5 IDENTIFICATION

A. Identify system components, wiring, and cabling complying with TIA/EIA-606-A.

Comply with requirements in Division 26 Section "Identification for Electrical Systems." Comply with requirements in Division 09 Section "Interior Painting" for painting backboards. For fire-resistant plywood, do not paint over manufacturer's label.

B. See Division 27 Section "Communications Horizontal Cabling" for additional identification requirements. See Evaluations for discussion of TIA/EIA standard as it applies to this Section. Paint and label colors for equipment identification shall comply with TIA/EIA-606-A for Class 2 level of administration.

C. Labels shall be preprinted or computer-printed type.

END OF SECTION 271100