015000 temporary facilities and controls.pdf

PDF 33 KB Posted

Attached to
CONSTRUCT CSMS PHASE II Federal contract opportunity
Solicitation number
W91364-09-B-0002
Issued by
Department of the Army Ohio Army National Guard

About this file

09B000215000 temporary facilities and controls.pdf

View the file

Other files for this federal contract opportunity

Other files attached to CONSTRUCT CSMS PHASE II, newest first.
File Type Posted
CSMM315aW.pdf PDF
CSMS271 Layout1 —
E-602.pdf PDF
CSM-Q503W.pdf PDF
CSM-A423W .pdf PDF
CSMM315cW.pdf PDF
CSM-A723W .pdf PDF
CSMS265 Layout1 —
CSM-A519W .pdf PDF
CSMM319bW.pdf PDF
CSMM318bW.pdf PDF
CSM-A807W .pdf PDF
CSM-A100W .pdf PDF
CSM-Q504W.pdf PDF
E-501.pdf PDF
CSMF314W.pdf PDF
CSM-A200W .pdf PDF
CSM-A303W .pdf PDF
CSM-A410W .pdf PDF
C201.pdf PDF
CSMM407W.pdf PDF
E-802.pdf PDF
CSM-A817W .pdf PDF
CSMM409W.pdf PDF
CSMS507W Layout1 —
L501.pdf PDF
CSMFA601W.pdf PDF
C500.pdf PDF
CSMM317aW.pdf PDF
L101.pdf PDF
CSM-A212bW .pdf PDF
CSMS266 Layout1 —
CSM-A411W .pdf PDF
CSM-A403W .pdf PDF
CSMS212W Layout1 —
CSM-A267W .pdf PDF
CSMM317cW.pdf PDF
220529 hangers and supports for plumbing piping and equipment.pdf PDF
412213.19 jib cranes.pdf PDF
013300d submittal register.pdf PDF
133423 fabricated structure.pdf PDF
017839 project record documents.pdf PDF
224500 emergency plumbing fixtures.pdf PDF
260523 control-voltage electrical power cables.pdf PDF
055000 metal fabrications.pdf PDF
271100 communications equipment room fittings.pdf PDF
221123 domestic water pumps.pdf PDF
019313 operation and maintenance manuals.pdf PDF
230523 general-duty valves for hvac piping.pdf PDF
085124 steel acoustical windows.pdf PDF
Show all 50

CONSTRUCT CSMS PHASE II has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F5W61607 Combined Support Maintenance Shop - Phase II Ohio Army National Guard Rev. 0 Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TEMPORARY FACILITIES AND CONTROLS 015000 - 1

SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.

B. Related Sections:

1. Division 01 Section "Summary" for work restrictions and limitations on utility interruptions.

2. Division 31 Section "Dewatering" for disposal of ground water at Project site.

3. Division 32 Section "Concrete Paving" for construction and maintenance of cement concrete pavement for temporary roads and paved areas.

1.3 USE CHARGES

A. General: Cost or use charges for temporary facilities shall be included in the Con-tract Sum. Allow other entities to use temporary services and facilities without cost, including, but not limited to, Government's representatives, occupants of Project, testing agencies, and others necessary to complete the Work.

B. Contractor shall pay for utilities. Contractor shall sign utility services contract and provide contractor’s billing information.

1. Install an electric meter for construction trailer(s).

2. Trailer water use shall be metered. Contractor may elect not to install meter, and water usage will be estimated by the Government.

3. Trailer sewer service will be estimated at the same usage as water.

4. Contractor shall obtain approved hydrant permit.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TEMPORARY FACILITIES AND CONTROLS 015000 - 2

1.4 INFORMATIONAL SUBMITTALS

A. Site Plan: Show temporary facilities, utility hookups, staging areas, and parking areas for construction personnel.

B. LEED Submittals: Refer to Section 018113 “Sustainable Design Requirements: for additional LEED submittal requirements. Requirements are listed in Attachment A to Section 018113, LEED analysis, under column titled “Documentation and Submittal Reference.” Contractor shall provide LEED submittals corresponding to each LEED Credit claimed and provide documentation per Section 018113, paragraph titled LEED Documentation Submittals.

C. Erosion- and Sedimentation-Control Plan: Show compliance with requirements of EPA Construction General Permit or authorities having jurisdiction, whichever is more stringent.

D. Moisture-Protection Plan: Describe procedures and controls for protecting materials and construction from water absorption and damage, including delivery, handling, and storage provisions for materials subject to water absorption or water damage, discarding water-damaged materials, protocols for mitigating water intrusion into completed Work, and replacing water damaged Work.

1. Indicate sequencing of work that requires water, such as plastering, and describe plans for dealing with water from these operations. Show procedures for verifying that wet construction has dried sufficiently to permit installation of finish materials.

E. Dust-Control and HVAC-Control Plan: Submit coordination drawing and narrative that indicates the dust-control and HVAC-control measures proposed for use, proposed locations, and proposed time frame for their operation. Identify further options if proposed measures are later determined to be inadequate. Include the following:

1. Locations of dust-control partitions at each phase of the work.

2. HVAC system isolation schematic drawing.

3. Location of proposed air filtration system discharge.

4. Other dust-control measures.

5. Waste management plan.

1.5 QUALITY ASSURANCE

A. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TEMPORARY FACILITIES AND CONTROLS 015000 - 3

C. Accessible Temporary Egress: Comply with applicable provisions in the U.S.

Architectural & Transportation Barriers Compliance Board's ADA-ABA Accessibility Guidelines and ICC/ANSI A117.1.

1.6 PROJECT CONDITIONS

A. Temporary Use of Permanent Facilities: Engage installer of each permanent service to assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Portable Chain-Link Fencing: Minimum 2-inch (50-mm), 9-gage, galvanized steel, chain-link fabric fencing; minimum 6 feet (1.8 m) high with galvanized steel pipe posts; minimum 2-3/8-inch- (60-mm-) OD line posts and 2-7/8-inch- (73-mm-) OD corner and pull posts, with 1-5/8-inch- (42-mm-) OD top and bottom rails. Provide concrete bases for supporting posts.

B. Lumber and Plywood: Comply with requirements in Section 061000 "Rough Car-pentry."

C. Gypsum Board: Minimum 1/2 inch (12.7 mm) thick by 48 inches (1219 mm) wide by maximum available lengths; regular-type panels with tapered edges. Comply with

ASTM C 36/C 36M.

D. Dust Control Adhesive-Surface Walk-off Mats: Provide mats minimum 36 by 60 inches.

E. Insulation: Unfaced mineral-fiber blanket, manufactured from glass, slag wool, or rock wool; with maximum flame-spread and smoke-developed indexes of 25 and 50, respectively.

2.2 TEMPORARY FACILITIES

A. Field Offices, General: Prefabricated or mobile units with serviceable finishes, temperature controls, and foundations adequate for normal loading.

1. Provide separate trailer for Owner.

B. Common-Use Field Office: Of sufficient size to accommodate needs of Owner, Architect, and construction personnel office activities and to accommodate project

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TEMPORARY FACILITIES AND CONTROLS 015000 - 4

meetings specified in other Division 01 Sections. Keep office clean and orderly.

Furnish and equip offices as follows:

1. Furniture required for Project-site documents including file cabinets, plan tables, plan racks, and bookcases.

2. Conference room of sufficient size to accommodate meetings of 12 individuals.

Provide electrical power service and 120-V ac duplex receptacles, with not less than 1 receptacle on each wall. Furnish room with conference table, chairs, and 4-foot- square tack and marker boards.

3. Drinking water and private toilet.

4. Coffee machine and supplies.

5. Heating and cooling equipment necessary to maintain a uniform indoor temperature of 68 to 72 deg F.

6. Lighting fixtures capable of maintaining average illumination of 20 fc at desk height.

C. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to accommodate materials and equipment for construction operations.

1. Store combustible materials apart from building.

2.3 EQUIPMENT

A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.

B. HVAC Equipment: Unless Owner authorizes use of permanent HVAC system, provide vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space thermostatic control.

1. Use of gasoline-burning space heaters, open-flame heaters, or salamander-type heating units is prohibited.

2. Heating Units: Listed and labeled for type of fuel being consumed, by a testing agency acceptable to Contracting Officer, and marked for intended use.

3. Permanent HVAC System: If Government authorizes use of permanent HVAC system for temporary use during construction, provide filter with MERV of 8 at each return air grille in system and remove at end of construction.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TEMPORARY FACILITIES AND CONTROLS 015000 - 5

B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

3.2 TEMPORARY UTILITY INSTALLATION

A. General: Install temporary service or connect to existing service.

1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

B. Sewers and Drainage: Provide temporary utilities to remove effluent lawfully.

1. Connect temporary sewers to municipal system as directed by authorities having jurisdiction.

C. Water Service: Install water service and distribution piping in sizes and pressures adequate for construction.

D. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.

E. Heating: Provide temporary heating required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of low temperatures or high humidity. Select equipment that will not have a harmful effect on completed installations or elements being installed.

F. Isolation of Work Areas in Occupied Facilities: Prevent dust, fumes, and odors from entering occupied areas.

1. Prior to commencing work, isolate the HVAC system in area where work is to be performed in accordance with approved coordination drawings.

a. Disconnect supply and return ductwork in work area from HVAC systems servicing occupied areas.

2. Maintain dust partitions during the Work. Use vacuum collection attachments on dust-producing equipment. Isolate limited work within occupied areas using portable dust containment devices.

3. Perform daily construction cleanup and final cleanup using approved, HEPA-filter-equipped vacuum equipment.

G. Ventilation and Humidity Control: Provide temporary ventilation required by construction activities for curing or drying of completed installations or for protecting installed construction from adverse effects of high humidity. Select equipment that

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TEMPORARY FACILITIES AND CONTROLS 015000 - 6

will not have a harmful effect on completed installations or elements being installed.

Coordinate ventilation requirements to produce ambient condition required and minimize energy consumption.

1. Provide dehumidification systems when required to reduce substrate moisture levels to level required to allow installation or application of finishes.

H. Electric Power Service: Provide electric power service and distribution system of sufficient size, capacity, and power characteristics required for construction operations.

1. Install electric power service underground or above, unless otherwise indicated.

I. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.

1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.

2. Install lighting for Project identification sign.

J. Telephone Service: Provide temporary telephone service in common-use facilities for use by all construction personnel. Install two telephone line(s) for each field of-fice.

1. Provide additional telephone lines for the following:

a. Provide a dedicated telephone line for each facsimile machine and com-puter in each field office.

2. At each telephone, post a list of important telephone numbers.

a. Police and fire departments.

b. Ambulance service.

c. Contractor's home office.

d. Architect's office.

e. Engineers' offices.

f. Contracting Officer's office.

g. Principal subcontractors' field and home offices.

3. Provide superintendent with cellular telephone or portable two-way radio for use when away from field office.

K. Electronic Communication Service: Provide temporary electronic communication service, including electronic mail, in common-use facilities.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TEMPORARY FACILITIES AND CONTROLS 015000 - 7

1. Provide DSL in primary field office. If DSL service is not available, provide a separate communications line for standard "dial-up" connection/service in Gov-ernment's temporary construction trailer.

3.3 SUPPORT FACILITIES INSTALLATION

A. General: Comply with the following:

1. Provide construction for temporary offices, shops, and sheds located within construction area or within 30 feet of building lines that is noncombustible according to ASTM E 136. Comply with NFPA 241.

2. Maintain support facilities until Contracting Officer schedules Final Acceptance inspection. Remove before Final Acceptance. Personnel remaining after Final Acceptance will be permitted to use permanent facilities, under conditions acceptable to Owner.

B. Temporary Roads and Paved Areas: Construct and maintain temporary roads and paved areas adequate for construction operations. Locate temporary roads and paved areas within construction limits indicated on Drawings.

1. Provide dust-control treatment that is nonpolluting and nontracking. Reapply treatment as required to minimize dust.

C. Traffic Controls: Comply with requirements of authorities having jurisdiction.

1. Protect existing site improvements to remain including curbs, pavement, and utilities.

2. Maintain access for fire-fighting equipment and access to fire hydrants.

D. Parking: Provide temporary parking areas for construction personnel.

E. Dewatering Facilities and Drains: Comply with requirements of authorities having jurisdiction. Maintain Project site, excavations, and construction free of water.

1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining properties nor endanger permanent Work or temporary facilities.

2. Remove snow and ice as required to minimize accumulations.

F. Project Identification and Temporary Signs: Provide Project identification. Install signs where indicated to inform public and individuals seeking entrance to Project.

Unauthorized signs are not permitted.

1. Provide temporary, directional signs for construction personnel and visitors.

a. Maintain and touchup signs so they are legible at all times.

2. Maintain and touchup signs so they are legible at all times.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TEMPORARY FACILITIES AND CONTROLS 015000 - 8

G. Waste Disposal Facilities: Comply with requirements specified in Section 017419 "Construction Waste Management and Disposal."

H. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel.

1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities.

I. Temporary Stairs: Until permanent stairs are available, provide temporary stairs where ladders are not adequate.

J. Temporary Use of Permanent Stairs: Use of new stairs for construction traffic will be permitted, provided stairs are protected and finishes restored to new condition at time of Final Acceptance.

3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

B. Temporary Erosion and Sedimentation Control: Provide measures to prevent soil erosion and discharge of soil-bearing water runoff and airborne dust to adjacent properties and walkways, according to requirements of authorities having jurisdic-tion.

1. Inspect, repair, and maintain erosion- and sedimentation-control measures during construction until permanent vegetation has been established.

C. Stormwater Control: Comply with requirements of authorities having jurisdiction.

Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater from heavy rains.

D. Tree and Plant Protection: Install temporary fencing located as indicated or outside the drip line of trees to protect vegetation from damage from construction operations.

Protect tree root systems from damage, flooding, and erosion.

E. Pest Control: Engage pest-control service to recommend practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at Final Acceptance. Obtain extended warranty for Owner.

Perform control operations lawfully, using environmentally safe materials.

F. Site Enclosure Fence: Before construction operations begin, furnish and install site enclosure fence in a manner that will prevent people and animals from easily enter-ing site except by entrance gates.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TEMPORARY FACILITIES AND CONTROLS 015000 - 9

1. Extent of Fence: As required to enclose entire Project site or portion deter-mined sufficient to accommodate construction operations.

2. Maintain security by limiting number of keys and restricting distribution to authorized personnel. Provide Contracting Officer with one set of keys.

G. Security Enclosure and Lockup: Install temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security. Lock entrances at end of each work day.

H. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.

I. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses.

Comply with NFPA 241.

1. Prohibit smoking in construction areas.

2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction.

3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information.

4. Provide temporary standpipes and hoses for fire protection. Hang hoses with a warning sign stating that hoses are for fire-protection purposes only and are not to be removed. Match hose size with outlet size and equip with suitable nozzles.

3.5 MOISTURE AND MOLD CONTROL

A. Contractor's Moisture-Protection Plan: Avoid trapping water in finished work.

Document visible signs of mold that may appear during construction.

B. Exposed Construction Phase: Before installation of weather barriers, when materials are subject to wetting and exposure and to airborne mold spores, protect as follows:

1. Protect porous materials from water damage.

2. Protect stored and installed material from flowing or standing water.

3. Keep porous and organic materials from coming into prolonged contact with concrete.

4. Remove standing water from decks.

5. Keep deck openings covered or dammed.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TEMPORARY FACILITIES AND CONTROLS 015000 - 10

C. Partially Enclosed Construction Phase: After installation of weather barriers but before full enclosure and conditioning of building, when installed materials are still subject to infiltration of moisture and ambient mold spores, protect as follows:

1. Do not load or install drywall or other porous materials or components, or items with high organic content, into partially enclosed building.

2. Keep interior spaces reasonably clean and protected from water damage.

3. Periodically collect and remove waste containing cellulose or other organic matter.

4. Discard or replace water-damaged material.

5. Do not install material that is wet.

6. Discard, replace or clean stored or installed material that begins to grow mold.

7. Perform work in a sequence that allows any wet materials adequate time to dry before enclosing the material in drywall or other interior finishes.

D. Controlled Construction Phase of Construction: After completing and sealing of the building enclosure but prior to the full operation of permanent HVAC systems, maintain as follows:

1. Control moisture and humidity inside building by maintaining effective dry-in conditions.

2. Use permanent HVAC system to control humidity.

3. Comply with manufacturer's written instructions for temperature, relative humidity, and exposure to water limits.

3.6 OPERATION, TERMINATION, AND REMOVAL

A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.

B. Maintenance: Maintain facilities in good operating condition until removal.

1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.

C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Final Acceptance.

D. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Final Acceptance. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

Defense Supply Center Columbus, Ohio 30 January 2009 Bid Final

TEMPORARY FACILITIES AND CONTROLS 015000 - 11

1. Materials and facilities that constitute temporary facilities are property of Contractor. Owner reserves right to take possession of Project identification signs.

2. Remove temporary roads and paved areas not intended for or acceptable for integration into permanent construction. Where area is intended for landscape development, remove soil and aggregate fill that do not comply with requirements for fill or subsoil. Remove materials contaminated with road oil, asphalt and other petrochemical compounds, and other substances that might impair growth of plant materials or lawns. Repair or replace street paving, curbs, and sidewalks at temporary entrances, as required by authorities having jurisdiction.

3. Before Final Acceptance, repair, renovate, and clean permanent facilities used during construction period. Comply with final cleaning requirements specified in Section 017700 "Closeout Procedures."

END OF SECTION 015000