SF30_Amend_0003.pdf

PDF 21 KB Posted

Attached to
Amend 0003 Federal contract opportunity
Solicitation number
W912P815B0046
Issued by
Department of the Army Corps of Engineers Engineering District New Orleans

About this file

Amendment 0003 SF30

View the file

Other files for this federal contract opportunity

Other files attached to Amend 0003, newest first.
File Type Posted
Drawing_for_MA-1_(_11-12-04)_New_Foundation_Part8.pdf PDF
Batch__2_Questions-Replies_W912P8-15-B-0046_(Amend0003).pdf PDF
Drawing_for_MA-1_(_11-12-04)_New_Foundation_Part9.pdf PDF
Drawing_for_MA-1_(_11-12-04)_New_Foundation_Part5.pdf PDF
Drawing_for_MA-1_(_11-12-04)_New_Foundation_Part10.pdf PDF
Drawing_for_MA-1_(_11-12-04)_New_Foundation_Part2.pdf PDF
SF30_Amend_0002Corrected.pdf PDF
QASP_Performance_Work_Statement__replacement.pdf PDF
Drawings_LAFCO_441-25_Welding_Sch_ _Details.pdf PDF
Drawings_LAFCO_441-16B_A_C_Electrical_System.pdf PDF
Drawings_LAFCO_441-12B_Fixed_CO2_Sys.pdf PDF
Drawings_LAFCO_441-3_Scantlings_and_Inboard_Profile.pdf PDF
Drawings_Launch_Edge_Water__914-433-009_Rigging_ _Tackle_Assy.pdf PDF
Drawings_LAFCO_441-23_Bumper_Details.pdf PDF
Drawings_LAFCO_441-19_Fuel_Tank.pdf PDF
Drawings_Launch_Edge_Water__914-433-005_Gen_Notes_and_BOM.pdf PDF
Drawings_11-04-01_opt.pdf PDF
Drawings_Launch_Edge_Water_914-433-000_General_Arrangement.pdf PDF
Drawings_Launch_Edge_Water__914-433-011_Davit_Arm_Installation _Winch_and_Misc_Details.pdf PDF
Drawings_Launch_Edge_Water__914-433-003_Support_Frame_Weldment.pdf PDF
Avondale_Drawings_combined_Part12.pdf PDF
Avondale_Drawings_combined_Part2.pdf PDF
Avondale_Drawings_combined_Part54.pdf PDF
Avondale_Drawings_combined_Part43.pdf PDF
Avondale_Drawings_combined_Part37.pdf PDF
Avondale_Drawings_combined_Part63.pdf PDF
Avondale_Drawings_combined_Part59.pdf PDF
Avondale_Drawings_combined_Part69.pdf PDF
Avondale_Drawings_combined_Part35.pdf PDF
Avondale_Drawings_combined_Part9.pdf PDF
Avondale_Drawings_combined_Part38.pdf PDF
Avondale_Drawings_combined_Part62.pdf PDF
Avondale_Drawings_combined_Part53.pdf PDF
Avondale_Drawings_combined_Part64.pdf PDF
Avondale_Drawings_combined_Part52.pdf PDF
Avondale_Drawings_combined_Part70.pdf PDF
Avondale_Drawings_combined_Part49.pdf PDF
Avondale_Drawings_combined_Part4.pdf PDF
Avondale_Drawings_combined_Part58.pdf PDF
Avondale_Drawings_combined_Part17.pdf PDF
Misc_Drawings_Part9.pdf PDF
Misc_Drawings_Part2.pdf PDF
Misc_Drawings_Part1.pdf PDF
Misc_Drawings_Part7.pdf PDF
Misc_Drawings_Part6.pdf PDF
Dredge_Technology_Drawings_Part3.pdf PDF
Dredge_Technology_Drawings_Part5.pdf PDF
Dredge_Technology_Drawings_Part8.pdf PDF
Section_J_Attachment_List_.pdf PDF
W912P8-15-B-0046.pdf PDF
Show all 50

Amend 0003 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The above numbered solicitation for the Dredge Wheeler Dry Dock, Berthing and Repair is hereby amended as follow s:

See the continuation pages of this document for all details.

Bid due date and time of 24 September 2015 at 2p.m. local time (CST) remains unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Sep-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P8-15-B-0046

X 9B. DATED (SEE ITEM 11)

12-Aug-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

18-Sep-2015

CODE

USACE, CONTRACTING DIVISION

ATTN: CEMVN-CT, ROOM 172

7400 LEAKE AVE.

NEW ORLEANS LA 70118-3651

W912P8 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P8-15-B-0046

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

(End of Summary of Changes)

The following items are applicable to this modification:

AMENDMENT 0003

The above numbered solicitation for the Dredge Wheeler Dry Dock, Berthing and Repair is hereby amended (0003) as follows:

- Adds Clarification verbiage for “Launch Vessel” work under LW-1.11, "PORT &

STARBOARD STRUT BEARINGS AND PROPELLERS REPLACEMENT":

2nd paragraph: first (1st) sentence should read "The Contractor shall disconnect the port and starboard couplings and measure the alignment between the engines and shafts at the couplings prior to dry-docking." Right now the spec only says "couplings".

3rd paragraph: first (1st) sentence should read "After removal of the port and starboard strut bearings, the Contractor shall check the alignment of the strut barrels, stern tubes, and engines with music wire after hull and bulkhead plating renewal (if any), structural framing renewal (if any), and main engine installation is complete." Right now the spec only says "...

port and strut bearings...”

- Adds: Technical Information titled: (ALFA LAVAL) Plate Heat Exchanger AX30-HBM downloadable via FBO labeled attachment.

- Adds: Clarification Drawings: #11-12-04 for the new foundation called out for in item #MA-1 downloadable via FBO labeled attachment..

- Adds batch #2 replies to questions submitted by 2p.m. local time (CST), 18 September 2015 as established deadline for all questions.

- Adds reply to question submitted regarding government vessel security requirements for accessing and working on the Dredge Wheeler during the dry dock and repair period.

Question: While reviewing the latest amendment to the Dredge Wheeler solicitation, we see a new requirement, starting on page 5, for MVN Security -- Background Checks for Building and Non-Building Access. (1) Will shipyard personnel, including our subcontractors, now be required to have background checks to board or work on the vessel?

Does the Corp consider the vessel a building? (2) A facility? (3) We are trying to fully understand the impacts of this newly added requirement; perhaps some background on why this requirement was added would be useful.

Reply:

1. All employees must have a current local background check to do work on the Dredge Wheeler if they do not possess a Federal TWIC Card. If they possess a TWIC, they have already been vetted at meet the background check requirements.

W912P8-15-B-0046

2. The vessel is considered a facility.

3. Why: This new requirement is to comply with the new Presidential Directive for Installation/facility access and the vetting of contractors prior to entering an instillation/facility.

- Adds: CAUTION TO BIDDERS: In delivery of hand-carried bids, bidders are cautioned to allow sufficient time for delays which may be encountered as a result of frequent trains which are subject to block all access roads to place of bid opening for various lengths of time. Such delays DO NOT permit acceptance or consideration of late bids.

- Adds Bid Bond Form (SF24-98)