Corrected_Revised_Bid_Schedule_to_include_Launch_01Sept2015.pdf

PDF 53 KB Posted

Attached to
Amend 0003 Federal contract opportunity
Solicitation number
W912P815B0046
Issued by
Department of the Army Corps of Engineers Engineering District New Orleans

About this file

Corrected revised bid schedule replaces previous posted revised bid schedule due missing bid schedule items 0018 description.

View the file

Other files for this federal contract opportunity

Other files attached to Amend 0003, newest first.
File Type Posted
Drawing_for_MA-1_(_11-12-04)_New_Foundation_Part8.pdf PDF
Batch__2_Questions-Replies_W912P8-15-B-0046_(Amend0003).pdf PDF
Drawing_for_MA-1_(_11-12-04)_New_Foundation_Part9.pdf PDF
Drawing_for_MA-1_(_11-12-04)_New_Foundation_Part3.pdf PDF
SF30_Amend_0002Corrected.pdf PDF
QASP_Performance_Work_Statement__replacement.pdf PDF
Drawings_LAFCO_441-25_Welding_Sch_ _Details.pdf PDF
Drawings_LAFCO_441-16B_A_C_Electrical_System.pdf PDF
Drawings_LAFCO_441-12B_Fixed_CO2_Sys.pdf PDF
Drawings_LAFCO_441-3_Scantlings_and_Inboard_Profile.pdf PDF
Drawings_Launch_Edge_Water__914-433-009_Rigging_ _Tackle_Assy.pdf PDF
Drawings_LAFCO_441-23_Bumper_Details.pdf PDF
Drawings_LAFCO_441-19_Fuel_Tank.pdf PDF
Drawings_Launch_Edge_Water__914-433-005_Gen_Notes_and_BOM.pdf PDF
Drawings_LAFCO_441-18_Shafting_Propeller.pdf PDF
Drawings_LAFCO_441-12_Fuel_Oil_ _Bilge_Sys.pdf PDF
SF30_Amend_0002.pdf PDF
Avondale_Drawings_combined_Part12.pdf PDF
Avondale_Drawings_combined_Part2.pdf PDF
Avondale_Drawings_combined_Part54.pdf PDF
Avondale_Drawings_combined_Part43.pdf PDF
Avondale_Drawings_combined_Part37.pdf PDF
Avondale_Drawings_combined_Part63.pdf PDF
Avondale_Drawings_combined_Part59.pdf PDF
Avondale_Drawings_combined_Part69.pdf PDF
Avondale_Drawings_combined_Part35.pdf PDF
Avondale_Drawings_combined_Part9.pdf PDF
Avondale_Drawings_combined_Part38.pdf PDF
Avondale_Drawings_combined_Part62.pdf PDF
Avondale_Drawings_combined_Part53.pdf PDF
Avondale_Drawings_combined_Part64.pdf PDF
Avondale_Drawings_combined_Part52.pdf PDF
Avondale_Drawings_combined_Part67.pdf PDF
Avondale_Drawings_combined_Part1.pdf PDF
Avondale_Drawings_combined_Part41.pdf PDF
Avondale_Drawings_combined_Part14.pdf PDF
Avondale_Drawings_combined_Part46.pdf PDF
Avondale_Drawings_combined_Part26.pdf PDF
Misc_Drawings_Part9.pdf PDF
Misc_Drawings_Part2.pdf PDF
Misc_Drawings_Part1.pdf PDF
Misc_Drawings_Part7.pdf PDF
Misc_Drawings_Part6.pdf PDF
Misc_Drawings_Part8.pdf PDF
Dredge_Technology_Drawings_Part3.pdf PDF
Dredge_Technology_Drawings_Part5.pdf PDF
Dredge_Technology_Drawings_Part6.pdf PDF
Dredge_Technology_Drawings_Part1.pdf PDF
Dredge_Technology_Drawings_Part9.pdf PDF
Dredge_Technology_Drawings_Part10.pdf PDF
Show all 50

Amend 0003 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B-1 reference and any product or commodity that will satisfy solicitation or contract

NOTE 6: See solicitation Clause 52.228-16 "Performance and Payment Bonds -

NOTE 7: Central Contract Registration is a one time registration that must be

SECTION B

SUPPLIES OR SERVICES AND PRICES/COSTS

to insert descriptive words or abbreviations such as "no charge" or "N.C."

NOTE 1: The bidder is required to bid on all line items. Failure to submit a bid on all such line

NOTE 2: Prospective bidders are encouraged to examine the vessel prior to bid opening.

NOTE 4: Payments for items identified as (Optional) will be paid in accordance items shall result in a non-responsive bid, requiring rejection thereof. In event that a bidder is willing to waive costs associated with an individual line item, he is required with the provisions located in SECTION H, at paragraph H-2, "Optional Item."

EXAMPLE

NOTE 3: All requirements in the schedule under the ITEM and Description/Specs./Work Statement."

0001 DD-1 Berthage, Drydocking and Services manufacturer's specifications or information sheets delineating those like characteristics.

before submitting a bid will not be considered cause for claim against the Government.

NOTE 5: The use of any particular product or commodity name is only given as a point of

Other than Construction" in Section I.

Contract Line Item 0001.

ITEM Spec. DESCRIPTION accomplished through the website at www.ccr.dlsc.dla.mil.

The citation "0001 DD-1" gives the necessary information for proper bid preparation for

Payment shall be calculated by multiplying the bid Optional (U/P) by the actual Quantity (Qty.) used - (U/P x QTY).

performance requirements may be offered. It is further requested that offeror submit accomplished prior to award of a Department of Defense contract. Registration may be

The date for examining the vessel is scheduled by appointment. All arrangements shall be made with Mr. Hung V. Quach, (504) 862-1150 prior to the scheduled date. Failure to examine the vessel

B-2

Item Description Qty. U/I Unit Price Amount

0001 Berthage, Drydocking, and Services 1 job

0002 Sea Chests and Gratings 1 job

0003 Sea Chests Strainers 1 job

0004 Sea Chests Vent Pipes 1 job

0005 Sea Valves 1 job

0006 Anchors and Anchor Chains 1 job

0007 Hopper Doors 1 job

0008 (Optional) Hopper Door Top Insert Plates Renew 10 ea

0009 (Optional) Hopper Door Side Plates Renew 10 ea

0010 (Optional) Hopper Door Fwd & Aft Plates Renew 6 ea

0011 (Optional) Hopper Door (3/4") Hinge Plate Bushing 30 ea

0012 (Optional) Hopper Door (1-3/4") Hinge Plate Bushing 30 ea

0013 (Optional) Hopper Door (3/4") Hinge Plate Replacement 20 ea

0014 (Optional) Bearing Pot Replacement 10 ea

0015 (Optional) Bearing Pot Bushings 40 ea

0016 (Optional) Hopper Door Pad Eye Bushings 14 ea

0017 (Optional) Top Bushing on Lower Push-Pull Rods w/Eye 14 ea

0018 (Optional) Top Bushing on lower Push-Pull Rods w/Fork 28 ea

0019 (Optional) Bottom Bushing on Push-Pull Rods 28 ea

0020 Replacement of Hopper Door Seals 1 job

0021 (Optional) Upper Rod Lower Guide Support Repl. 20 ea

0022 (Optional) Upper Rod Lower Guide Block Repair 28 ea

0023 (Optional) Upper Rod Upper Guide Block Repair 20 ea

0024 (Optional) Upper Rod New Sleeve Installation 7 ea

0025 Zinc Anodes 1 job

0026 Hopper Bay Inspection 1 job

0027 (Optional) Hopper Bay Plating, Athwartship, Plate A 7 ea

0028 (Optional) Hopper Bay Plating, Athwartship, Plate B 7 ea

0029 (Optional) Hopper Bay Plating, Athwartship, Plate C 7 ea

0030 (Optional) Hopper Bay Plating, Athwartship, Plate D 14 ea

0031 (Optional) Hopper Bay Plating, Longitudinal, Plate A 10 ea

0032 (Optional) Hopper Bay Plating, Longitudinal, Plate B 7 ea

0033 (Optional) Longitudinal Reinforced Plate in Void 7 ea

0034 (Optional) Hopper Bay Sloped Plate Weld Seam Repair 20 ea

0035 (Optional) Wing Voids Interior Weld Seam Repair 20 ea

HH-2.1.3

HH-1

HH-4

HH-2.3

HH-2.1.2

DD-7.12

DD-7.16

DD-7.8

DD-7.7

DD-7.4

HH-2.1.1

DD-7.15

DD-7.14

DD-2

DD-7.3

DD-7.6

DD-7.1

DD-1

Spec.

DD-5

DD-7.2

DD-7.9

DD-3

DD-7

DD-7.5

DD-7.11

DD-7.10

DD-4

DD-6

HH-2.1.4

HH-3

HH-2.2.1

HH-2.3

DD-7.13

DD-8

DD-7.17

HH-2.2.2

B-3

Item Description Qty. U/I Unit Price AmountSpec.

0036 (Optional) Centerwell Bulkhead Weld Seam Repair 20 ea

0037 (Optional) Hopper Weld Seam Repair (Various Locations) 20 ea

0038 (Optional) Large Vertical T-Beam Section 2 ea

0039 (Optional) Medium Vertical T-Beam Section 2 ea

0040 (Optional) Small Vert. T-Beam Section (Above Stringer) 6 ea

0041 (Optional) Small Vert. T-Beam Section (Below Stringer) 6 ea

0042 (Optional) Stringer Plate Section 6 ea

0043 Replacement of Vertical Beams - Aft Center Bulkhead 1 job

0044 (Optional) Ultrasonic Thickness Measurements 10000 ea

0045 Cover For Stacks 1 job

0046 (Optional) Steel Plate 5/16 inch to 1/2 inch 2000 lb

0047 (Optional) Steel Plate 9/16 inch to 1 inch 8000 lb

0048 HH-10.3 (Optional) Bulhead Plating 5/8 inch Cor-Ten 7500 lb

0049 (Optional) Bulkhead Plating 3/4 inch Cor-Ten 7500 lb

0050 (Optional) Steel Pipe, Galv 6-inch 100 lf

0051 (Optional) Steel Pipe, Galv 8-inch 100 lf

0052 (Optional) Steel Pipe, Galv, 10-inch 50 lf

0053 (Optional) S.S. Hanger for 6-inch Pipe 20 ea

0054 (Optional) S.S. Hanger for 8-inch Pipe 20 ea

0055 (Optional) S.S. Hanger for 10-inch Pipe 20 ea

0056 (Optional) Services of Machinist (outside) 2500 hr

0057 (Optional) Machining 1000 hr

0058 (Optional) Mild Steel Welding 1000 hr

0059 (Optional) Low Hydrogen Welding 5000 hr

0060 HH-13.3 (Optional) Stainless Steel Welding 200 hr

0061 (Optional) Inspection of Welds 500 hr

0062 Ballast Tanks, Voids, and CofferDams 1 job

0063 Dirty Lube Oil, Oily Bilge & Sludge Tanks 1 job

0064 Fuel Oil Tanks 1 job

0065 Fuel Oil Vent Containments (Clean, Steel Repair) 1 job

0066 No. 2 Port Void - Deck Plate Replacement 1 job

0067 Protection, Cleaning, and Surface Preparation 1 job

0068 Painting 1 job

0069 No. 2 DB Center Tank Surface Preparation & Painting 1 job

0070 Steel Plate in AMR, Mid Level, Starboard Side 1 job

HH-5

HH-13.2

HH-10.7

HH-7.6

HH-7.1

HH-10.8

HH-10.5

HH-10.6

HH-10.11

HH-18

HH-13.4

HH-14

HH-8

HH-7.2

HH-10.9

HH-9

HH-10.4

HH-12

HH-10.1

HH-11

HH-21

HH-10.2

HH-6

HH-22

HH-10.7

HH-16

HH-19

HH-7.5

HH-7.3

HH-7.4

HH-13.1

HH-20

HH-17

HH-15

B-4

0071 Stanchions under Helodeck and Helo Nets 1 job

0072 Port Holes Replacement 1 job

0073 Propeller Hydraulic System Inspection 1 job

0074 Hydraulic Power Unit and Hub Oil System Maintenance 1 job

0075 Port & Starboard Servo Box Inspection 1 job

0076 (Optional) Tailshaft and Hub Replacement 1 job

0077 Port & Stbd Strut and Stern Tube Bearing Inspection 1 job

0078 (Optional) Port Stern Tube Gland Seal Maintenance 1 job

0079 (Optional) Starboard Stern Tube Gland Seal Maintenance 1 job

0080 Bow Thruster Inspection & Maintenance 1 job

0081 Rudder Stock & Pintle Pin Clearances (Port & Starboard) 1 job

0082 (Optional) Port Pintle Pin Bushing Replacement 1 job

0083 Sluice Valve Inspection 1 job

0084 (Optional) Sluice Valve, 18-Inch Diameter 5 ea

0085 (Optional) Sluice Valve, 24-Inch Diameter 2 ea

0086 (Optional) Sluice Valve, 26-Inch Diameter 2 ea

0087 (Optional) Sluice Valve, 30-inch Diameter 3 ea

0088 (Optional) Sluice Valve, 32-inch Diameter 2 ea

0089 (Optional) Sluice Valve, 43-inch Diameter 1 ea

0090 (Optional) Collection Valve Gate Repair 3 job

0091 Collection Valve Flushing Lines and Body Cleaning 1 job

0092 Clean Jetting Pipe & Rebuild Jetting Pumps 1 job

0093 Weld Seam Repair on Collection Pipes in Voids (P & S) 1 job

0094 (Optional) Port Overside Trunnion Hull Flange 1 job

0095 (Optional) Starboard Overside Trunnion Hull Flange 1 job

0096 Center Dragarm Gimbal Bushing Replacement 1 job

0097 Center Dragarm, Upper Frame Repair 1 job

0098 (Port & Starboard) Lander Pipe Replacement 1 job

0099 (Port & Starboard) Inboard Pump Shaft Sleeve Repl. 1 job

0100 Starboard Overside Davits Shafts 1 job

0101 Overside Carriage (Port & Starboard) 1 job

0102 Swell Comp & Shock Absorder Cylinders Repair 1 job

0103 Starboard Plate Cooler Maintenance and Repair 1 job

0104 Drain, Dispose, Refill, and Treat Fresh Water System 1 job

0105 Clean And Paint Two Fresh Water Expansion Tanks 1 job

MD-12

MD-11

MD-8

MA-1

MA-2

MP-3.1

MP-4.2

MD-1.2.5

MD-1.2.3

MP-2.2

MP-2.3

MD-2

MD-1.2.1

MD-1.3

MA-3

MD-6

MD-10

MP-2.1

MP-1.1

MD-7

MP-1.2

MD-3

MP-1.4

HH-23

HH-24

MP-1.3

MD-1.2.4

MD-4

MD-5

MD-9

MP-4.1

MD-1.1

MD-1.2.6

MD-1.4

MD-1.2.2

B-5

0106 Bilge-SW Pipe Replacement (Pump Rm, Starboard side) 1 job

0107 Forward Fire Pump Piping Replacement (Pump Room) 1 job

0108 Seawater Piping & Valves Replacement (Pump Room) 1 job

0109 Seawater Pumps Rebuild (Port & Starboard) 1 job

0110 Port Forward Fresh Water Pump Rebuild & Valves Repl. 1 job

0111 Tate Temco Valve Manifolds 1 job

0112 Potable Water System 1 job

0113 Port & Starboard Lifeboats Davits & Winches Repair 1 job

0114 Vent And Sounding Pipes Replacement 1 job

0115 Relocate Sewage Vacuum Pump Unit in AMR 1 job

0116 Replace Starboard Stern Tube Vent Pipe (1-1/2") 1 job

0117 Install Gate Valves On Bilge & Ballast Piping (Eng Rm.) 1 job

0118 Relocate One 5 inch Gate Valve (Engine Room) 1 job

0119 (Optional) Bilge & Ballast Pipes (2") 100 ft

0120 (Optional) Bilge & Ballast Pipes (3") 100 ft

0121 (Optional) Bilge & Ballast Pipes (4") 100 ft

0122 (Optional) Bilge & Ballast Pipes (5") 100 ft

0123 (Optional) Bilge & Ballast Pipes (6") 100 ft

0124 EE-1 Dragarm Monitoring System Installation 1 job

0125 TR-2 Dock Trials 1 job

0126 LW-1.6 "For Launch" Berthage, Drydocking, and Services 1 job

0127 LW-1.7 Overboard Discharges And Shell Connections 1 job

0128 LW-1.8

Fuel Oil Tank Cleaning & Main Engines and Generator Set Removal. 1 job

0129 LW-1.9 Lifting Hooks and Stern Bit Pin 1 job

0130 LW-1.10 Generator Inspection, Overhaul & Testing 1 job

0131 LW-1.11

Port & Starboard Strut Bearings & Propellers Replacement 1 job

0132 LW-1.12 Sea Chests & Raw Water Valves Maintenance 1 job

0133 LW-1.13 Engine Room Cleaning 1 job

0134 LW-1.14.1 Overhead Air Conditioning Unit Replacement 1 job

0135 LW-1.14.2 Wall Mounted Air Conditioning Units Maintenance 1 job

0136 LW-1.15.1 Cleaning and Coating 1 job

0137 LW-1.16 Anodes 1 job

0138 LW-1.17 Port & Starboard Main Engines & Marine Gears Overhaul 1 job

0139 LW-1.18 Port & Starboard Main Engines Alignment 1 job

0140 LW-1.19

Port & Starboard Heat Exchanger Boil Out & Modifications 1 job

MA-5

MA-6

MA-17.4

MA-10

MA-12

MA-14

MA-4

MA-7

MA-16

MA-17.5

MA-15

MA-13

MA-11

MA-17.2

MA-17.3

MA-17.1

MA-9

MA-8

B-6

0141 LW-1.20 Port & Starboard Main Engines Fuel Filter Separators 1 job

0142 LW-1.21 Port & Starboard Main Engines Miscellaneous Equipment 1 job

0143 LW-1.22 Dock & Sea Trials 1 job

0144 LW-1.23 Spare Part List 1 job

0145 Growth Rate $ /hr This labor hourly rate shall be used in pricing all contract changes in accordance with the clause of

Section H-2A entitled "COMPOSITE LABOR HOUR RATE FOR

CONTRACT CHANGES."

NOTE: The contractor only needs to fill in the hourly rate in the Optional column in his bid.

Percent Mark-Up (%) % The percent mark-up applies only to materials, parts, and sub-contract service in growth work only.

NOTE: The contractor only needs to fill in the percent Mark-Up in the Optional column in his bid.

Grand Bid Total:

END OF SECTION B

B-7

B-8

B-9

B-10

B-11

B-12

Sheet1

File details come from the government source that posted it. Updated .