IFB No. W912P5-17-R-0002 Amendment No. 0001
Station Service Upgrade Wolf Creek Powerhouse
Russell County, Kentucky
I. CHANGES TO TECHNICAL SPECIFICATIONS
A. Section 01 11 10 SUMMARY OF WORK
1. Remove Section 01 11 10 in its entirety (4 pages), and replace with revised Section
01 11 10 (5 pages).
B. Section 01 22 00 PRICE AND PAYMENT PROCEDURES
1. Remove Section 01 22 00 in its entirety (8 pages), and replace with revised Section
01 22 00 (7 pages).
C. Section 01 95 00 FORMS AND ATTACHMENTS
1. Remove Section 01 95 00 in its entirety (2 pages), and replace with revised Section
01 95 00 (2 pages).
2. Remove the Submittal Register in its entirety (18 pages) from the back of Section
01 95 00, and replace with revised Submittal Register (17 pages).
3. Add Asbestos Survey (8 pages) to the back of Section 01 95 00.
D. Section 02 82 13 ASBESTOS ABATEMENT
1. Remove Section 02 82 13 in its entirety (14 pages) without replacement.
E. Section 26 00 00.00 26 GENERAL ELECTRICAL WORK AND EQUIPMENT
1. Remove Section 26 00 00.00 26 in its entirety (26 pages), and replace with revised
Section 26 00 00.00 26 (26 pages).
F. Section 26 08 01.00 26 SYSTEMS TESTING AND COMMISSIONING
1. Remove Section 26 08 01.00 26 page 2, and replace with revised Section
26 08 01.00 26 page 2.
G. Section 26 12 16.10 26 DRY-TYPE TRANSFORMERS
1. Remove Section 26 12 16.10 26 page 3, and replace with revised Section
26 12 16.10 26 page 3.
H. Section 26 13 13.00 26 METAL CLAD SWITCHGEAR
1. Remove Section 26 13 13.00 26 pages 4 and 15, and replace with revised Section
26 13 13.00 26 pages 4 and 15.
I. Section 26 24 19.00 26 SYSTEMS TESTING AND COMMISSIONING
1. Remove Section 26 24 19.00 26 page 3, and replace with revised Section
26 24 19.00 26 page 3.
--- END OF AMENDMENT NO. 0001 TECHNICAL CHANGES---
| IFB No. W912P5-17-R-0002 |
| Amendment No. 0001 |
| Station Service Upgrade |
| Russell County, Kentucky |
| I. CHANGES TO TECHNICAL SPECIFICATIONS |
| A. Section 01 11 10 SUMMARY OF WORK |
| 1. Remove Section 01 11 10 in its entirety (4 pages), and replace with revised Section 01 11 10 (5 pages). |
| B. Section 01 22 00 PRICE AND PAYMENT PROCEDURES |
| 1. Remove Section 01 22 00 in its entirety (8 pages), and replace with revised Section 01 22 00 (7 pages). |
| C. Section 01 95 00 FORMS AND ATTACHMENTS |
| 1. Remove Section 01 95 00 in its entirety (2 pages), and replace with revised Section 01 95 00 (2 pages). |
| 2. Remove the Submittal Register in its entirety (18 pages) from the back of Section 01 95 00, and replace with revised Submittal Register (17 pages). |
| 3. Add Asbestos Survey (8 pages) to the back of Section 01 95 00. |
| D. Section 02 82 13 ASBESTOS ABATEMENT |
| 1. Remove Section 02 82 13 in its entirety (14 pages) without replacement. |
| E. Section 26 00 00.00 26 GENERAL ELECTRICAL WORK AND EQUIPMENT |
| 1. Remove Section 26 00 00.00 26 in its entirety (26 pages), and replace with revised Section 26 00 00.00 26 (26 pages). |
| F. Section 26 08 01.00 26 SYSTEMS TESTING AND COMMISSIONING |
| 1. Remove Section 26 08 01.00 26 page 2, and replace with revised Section 26 08 01.00 26 page 2. |
| G. Section 26 12 16.10 26 DRY-TYPE TRANSFORMERS |
| 1. Remove Section 26 12 16.10 26 page 3, and replace with revised Section 26 12 16.10 26 page 3. |
| H. Section 26 13 13.00 26 METAL CLAD SWITCHGEAR |
| 1. Remove Section 26 13 13.00 26 pages 4 and 15, and replace with revised Section 26 13 13.00 26 pages 4 and 15. |
| I. Section 26 24 19.00 26 SYSTEMS TESTING AND COMMISSIONING |
| 1. Remove Section 26 24 19.00 26 page 3, and replace with revised Section 26 24 19.00 26 page 3. |
File details come from the government source that posted it.