Ky_Lock_SDU_-_Site_Visit_Presentation.pdf

PDF 4 MB Posted

Attached to
Kentucky Lock Site, Demolitions, and Utilities Construction
Solicitation number
W912P517B0015
Issued by

About this file

Site Visit Presentation

View the file

Other files

File Type Posted
OF1419_Construction-signed.pdf PDF
Amendment_0005.pdf PDF
W912P517B00150004.pdf PDF
W912P517B00150003.pdf PDF
W912P5-17-B-0015_TSpecs_050523pg3-_AMD_003.pdf PDF
W912P5-17-B-0015_TSpecs_051200pg6_-_AMD_003.pdf PDF
Amend_0002_Errata_Sheet.pdf PDF
W912P517B00150002.pdf PDF
W912P5-17-B-0015_Plans_-_AMD_002.pdf PDF
W912P5-17-B-0015_TSpecs_-_AMD_002.pdf PDF
KYLK_As-Built_Folio_1_Part15.pdf PDF
KYLK_As-Built_Folio_1_Part8.pdf PDF
KYLK_As-Built_Folio_1_Part10.pdf PDF
KYLK_As-Built_Folio_1_Part1.pdf PDF
KYLK_As-Built_Folio_2_Part3.pdf PDF
KYLK_As-Built_Folio_2_Part11.pdf PDF
KYLK_As-Built_Folio_1_Part4.pdf PDF
KYLK_As-Built_Folio_1_Part11.pdf PDF
KYLK_As-Built_Folio_1_Part9.pdf PDF
KYLK_As-Built_Folio_2_Part5.pdf PDF
KYLK_As-Built_Folio_2_Part7.pdf PDF
KYLK_As-Built_Folio_1_Part13.pdf PDF
KYLK_As-Built_Folio_2_Part9.pdf PDF
KYLK_As-Built_Folio_1_Part14.pdf PDF
KYLK_As-Built_Folio_1_Part3.pdf PDF
KYLK_As-Built_Folio_1_Part2.pdf PDF
KYLK_As-Built_Folio_2_Part4.pdf PDF
KYLK_As-Built_Folio_2_Part6.pdf PDF
KYLK_As-Built_Folio_2_Part10.pdf PDF
KYLK_As-Built_Folio_1_Part12.pdf PDF
KYLK_As-Built_Folio_2_Part2.pdf PDF
KYLK_As-Built_Folio_2_Part8.pdf PDF
KYLK_As-Built_Folio_1_Part6.pdf PDF
KYLK_As-Built_Folio_2_Part1.pdf PDF
KYLK_As-Built_Folio_1_Part7.pdf PDF
KYLK_As-Built_Folio_1_Part16.pdf PDF
KYLK_As-Built_Folio_1_Part5.pdf PDF
P&L_Railroad_Bridge_Reference_Folio.pdf PDF
Site_Visit_Roster.pdf PDF
W912P517B00150001.pdf PDF
Mechanical_Reference_Folio.pdf PDF
Powerhouse_Access_Bridge_Reference_Folio.pdf PDF
US_62^641_Highway_Bridge_Reference_Folio.pdf PDF
Combined_Abutments_Reference_Folio.pdf PDF
SDU_-_QA_spreadsheet_-_Amend_1_v3.pdf PDF
Electrical_Reference_Folio.pdf PDF
W912P517B0015.pdf PDF
FN_Site_Visit_Form-KY_Lock.pdf PDF
W912P517B0015_Bid_Schedule.xlsx XLSX spreadsheet
W912P5-17-B-0015_TSpecs.pdf PDF
Show 40 more

Latest 50 of 52 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

.59

“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”

Kentucky Lock Addition Nashville District

KENTUCKY LOCK ADDITION

SITE, DEMOLITION & UTILITY

RELOCATIONS

CONTRACTOR SITE VISIT

File Name

December 19, 2017

.59

New Hwy and RR Bridges

New Transmission

Towers

Upstream

Cofferdam

Upstream

Lock Monoliths

Kentucky Lock Addition

Completed Features

.59

New Hwy and RR Bridges

New Transmission

Towers

Upstream

Cofferdam

Upstream

Lock Monoliths

Completed and Ongoing

Construction

Ongoing Downstream Cofferdam

Downstream Lock Excavation

Award: September 2018

SITE, DEMOLITION AND UTILITY RELOCATIONS

Scope of Work:

1. Mechanical/Electrical Utility Relocations

2. Potable Water and Sewer Line Relocations

3. New Sewer Lift Station

4. New Land Wall Cat-walk System

5. Land Wall Pipe Support Replacement

6. New Lock Utility Bridges

7. Demolition and Modifications to Existing Lock Operations

Building

PROJECT OVERVIEW

DOWNSTREAM PLAN VIEW

DOWNSTREAM PIPING SECTION - RIVERWALL

Relocated conduit for:

- gate spray

- compressed air

- service water

Relocate

- Potable water

- Sewer line

DOWNSTREAM CONDUIT SECTION - RIVERWALL

Relocate 13.8 KV Feeders and Controls Conduit

Cut Slot in Roof of Manhole 9, Relocate Comm/Power/Control

Conduit

DOWNSTREAM CONDUIT SECTION - LANDWALL

Oil Storage Room

Demolition

Concrete Stairs

Demolition

DOWNSTREAM CONDUIT SECTION - LANDWALL

Relocated conduit for:

- Communication

- Power

- Controls

Support for new conduit

TYPICAL BRIDGE SECTION

Relocated conduit for:

- Communication

- Power

- Controls

New Conduit Rack

New Pipe Rack

UPSTREAM PLAN VIEW

New Utility Bridges across existing Lock

New Sewage Lift Station New Utility Pipe Supports

UPSTREAM PLAN VIEW

Existing Portions of Operations Building to be Removed

Basement Utility Work:

- Piping relocation

- Demo/removal of lift station

Potable Waterline Connection to Operations Building

CONSTRUCTION LIMITS

Upstream Laydown Yard

(Shared with DS Cofferdam

Contractor)

Construction Limits

Disposal Area

(Shared with DS Cofferdam Contractor)

Downstream Cofferdam

Construction Limits

Construction Constraints and Issues:

1. Timing of Temporary Hazardous Material Storage

– Demolition of existing oil-storage building

– Construction of new Haz-Mat storage

2. Potable Waterline Relocation

Construction Coordination:

1. Existing Lock Operations Personnel

– Active lock navigation

– Coordinate work thru COR and Lockmaster

2. Coordination with TVA – Tennessee Valley Authority

3. AT&T accommodation for relocation of their lines near the end of construction

Site Visit Sequence:

Start – Location of new Temporary Haz-Mat Storage Facility

End – Near sewer manhole connections

EXPECTED CONTENT OF AMENDMENT

- Option expiration date from 16 March 2018 to 1 July

2018.

- Period of performance from 300 to 308 calendar days.

- Provisions for Lock Operations building water line if

Option is not exercised.

SITE WALK-THRU

File Name