About this file

Solicitation Exhibit E4

View the file

Other files

File Type Posted
QuestionsAnswers-14May2010.pdf PDF
QuestionsAnswers-5May2010.pdf PDF
FTIGInstallationDesignGuide.pdf PDF
QuestionsAnswers-4May2010.pdf PDF
QuestionsAnswers-3May2010.pdf PDF
QuestionsAnswers-29Apr2010.pdf PDF
QuestionsAnswers-27Apr2010.pdf PDF
QuestionsAnswers-2-22Apr2010.pdf PDF
QuestionsAnswers-22Apr2010.pdf PDF
21April2010SecondarySiteVisitAttendees.pdf PDF
QuestionsAnswers-21Apr2010.pdf PDF
QuestionsAnswers-19Apr2010.pdf PDF
QuestionsAnswers-16Apr2010.pdf PDF
Amended Exhibit F.doc DOC document
Amended Exhibit G.doc DOC document
QuestionsAnswers-3-9Apr2010.pdf PDF
QuestionsAnswers-2-9Apr2010.pdf PDF
QuestionsAnswers9Apr2010.pdf PDF
Exhibit F.doc DOC document
Exhibit G.doc DOC document
Exhibit E4-1.doc DOC document
Exhibit D.doc DOC document
Exhibit B.doc DOC document
Exhibit E.doc DOC document
Exhibit C.doc DOC document
Exhibit E-1.doc DOC document
Exhibit E2.doc DOC document
Exhibit A.doc DOC document
Exhibit E2-1.doc DOC document
7April2010ConferenceAttendees.pdf PDF
Pre-Proposal Conference.pdf PDF
QuestionsAnswers2Apr2010.pdf PDF
QuestionsAnswers31Mar2010.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IDIQ MATOC

RFP W912KC-10-R-0001

EXHIBIT E4 PROTOTYPICAL PROJECT FOUR

NOTICE OF PROPOSED PROJECT, PROPOSAL FORM

Date: 30 March 2010 PROJECT TITLE AND NO.: Area-13 Barracks Renovations PROJECT DESCRIPTION: Remodeling of wooden barracks facilities originally constructed in 1941. All facilities will be upgraded to enhance living conditions for soldiers and bring these facilities up to standard for energy efficiency and code compliance. Bldg. 13-128, 13-129, 13-140 & 13-141.

MAGNITUDE OF PROJECT: $500,000 - $1,000,000

PERFORMANCE PERIOD: 300 Days, after receipt of Notice to Proceed

SITE VISIT: A site visit will be conducted in conjunction with the MATOC pre-proposal meeting. See Section 00100 of the solicitation for details.

PERFORMANCE & PAYMENT BONDS: In accordance with FAR 28.102-1 and Contract Clause 52.228-15, Contractors are reminded that any amount awarded over $30,000 shall require Payment Bonds, and awards exceeding $100,000 shall require both Payment and Performance Bonds. All bonds are due no later than 10 days after award.

LIQUIDATED DAMAGES: (X) YES or ( ) NO- reference Contract Clause 52.211-12. Fill-in amout is “a one time fee of $200.00 for legal services, plus $421.12 per day”

CONSTRUCTION: (X) YES or ( ) NO- reference Contract Clause 52.246-21, Warranty of Construction, is applicable to this task order.

WAGE DETERMINATION: Currently, General Decision Number PA100008, dated March 12, 2010, is applicable to this task order. However, the current prevailing Wage Determination will be incorporated at time of award.

PROJECT SAFETY: In accordance with FAR 52.236-13, Accident Prevention, construction contractors are required to use the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1. To view this manual click here http://www.usace.army.mil/inet/usace-docs/eng-manuals/em385-1-1/toc.htm PROPOSAL DUE DATE: All offers are due with proposal for MATOC basic contract. Failure to provide a price will make offer noncompliant, eliminated from the competition and offeror ineligible for a basic contract award. Basis for award is in the RFP.

Item

Number

Description

Lump Sum Amount

All work complete IAW specifications and drawings for Bldg. 13-128, 13-129, 13-140 and 13-141

Option 0001 Addition of Bldg. 13-142

SIGNATURE:

COMPANY NAME

Name and title of person authorized to sign

Offer Date