IDIQ MATOC
RFP W912KC-10-R-0001
EXHIBIT E PROTOTYPICAL PROJECT ONE
NOTICE OF PROPOSED PROJECT, PROPOSAL FORM
Date: 30 March 2010 PROJECT TITLE AND NO.: FTIG Paving Project; Prototypical One PROJECT DESCRIPTION: Fort Indiantown Gap Bituminous Concrete Paving Project for Bldg. 8-57 & 9-100, and Logan Road. This project is to provide bituminous paved parking at three different locations (Bldg 8-57, 9-100 and Logan Road). At Bldg. 8-57 there is an existing gravel parking area which is to be extended and paved along with the a gravel driveway which connects to Service Road. At Bldg. 9-100 there is an existing gravel parking lot parallel to Signal Street which is to be paved. The present driveway connecting it to Signal Street is to be removed and reconstructed at the north end of the parking lot. On Logan Road, the existing gravel parking lot is to be extended and paved; the existing gravel shoulder on the east side of Logan Road is to be paved; and Logan Road itself will be resurfaced from Clement Avenue northerly for a distance of approximately 225 feet.
MAGNITUDE OF PROJECT: $250,000-$500,000
PERFORMANCE PERIOD: 90 Days, after receipt of Notice to Proceed
SITE VISIT: A site visit will be conducted in conjunction with the MATOC pre-proposal meeting. See Section 00100 of the solicitation for details.
PERFORMANCE & PAYMENT BONDS: In accordance with FAR 28.102-1 and Contract Clause 52.228-15, Contractors are reminded that any amount awarded over $30,000 shall require Payment Bonds, and awards exceeding $100,000 shall require both Payment and Performance Bonds. All bonds are due no later than 10 days after award.
LIQUIDATED DAMAGES: ( ) YES or (X) NO- reference Contract Clause 52.211-12.
CONSTRUCTION: (X) YES or ( ) NO- reference Contract Clause 52.246-21, Warranty of Construction, is applicable to this task order.
WAGE DETERMINATION: Currently, General Decision Number PA100014 dated March 12, 2010 is applicable to this task order. However, the current prevailing Wage Determination will be incorporated at time of award.
PROJECT SAFETY: In accordance with FAR 52.236-13, Accident Prevention, construction contractors are required to use the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1. To view this manual click here http://www.usace.army.mil/inet/usace-docs/eng-manuals/em385-1-1/toc.htm PROPOSAL DUE DATE: All offers are due with proposal for MATOC basic contract. Failure to provide a price will make offer noncompliant, eliminated from the competition and offeror ineligible for a basic contract award. Basis for award is in the RFP.
Item
Number
Description
Lump Sum Amount
BLDG. 8-57
BLDG. 9-100
LOGAN ROAD
TOTAL
SIGNATURE:
COMPANY NAME
Name and title of person authorized to sign
Offer Date