RFI-001_Water_main_loops.docx

DOCX document 11 KB Posted

Attached to
Add Water Main Loops
Solicitation number
W912JB-18-R-9003
Issued by

About this file

Request For Information and answer.

View the file

Other files

File Type Posted
Evaluation_Factor_Amendment-0002.docx DOCX document
W912JB-18-R-9003-0002.pdf PDF
Amendment_to_instructions_to_offerors_section.docx DOCX document
W912JB-18-R-9003-0001.pdf PDF
RFI-002_Water_Main_Loops.pdf PDF
Wage_Determination_MI42.pdf PDF
Water_Main_Loops_Site_Visit_Minutes.docx DOCX document
Water_main_loops_site_visit_sign_in_sheet.docx DOCX document
RFI_001.docx DOCX document
AF66_-_TDVG142913_Replace_Water_main_loops.pdf PDF
Alpena_Base_Access_requirements.pdf PDF
B-3_Replace_Water_Main_Loops-_Drawings.pdf PDF
W912JB-18-R-9003.pdf PDF
B3_Specifications_-_Copy.doc DOC document
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912JB-18-R-9003

ADD WATER MAIN LOOPS

RFI-001

Question: What are the security measures required for when a portion of the fence is removed to install the water main on sheet C-300?

Answer: C/300 and C/302 show details removing and restoring fence. In both areas fence fabric will need to be temporarily secured at the end of each work day. Security Forces will increase evening patrols