Amendment_to_instructions_to_offerors_section.docx

DOCX document 13 KB Posted

Attached to
Add Water Main Loops Federal contract opportunity
Solicitation number
W912JB-18-R-9003
Issued by
Department of the Army Michigan Army National Guard

About this file

Changes to evaluation factors

View the file

Other files for this federal contract opportunity

Other files attached to Add Water Main Loops, newest first.
File Type Posted
W912JB-18-R-9003-0002.pdf PDF
Evaluation_Factor_Amendment-0002.docx DOCX document
W912JB-18-R-9003-0001.pdf PDF
RFI-002_Water_Main_Loops.pdf PDF
Wage_Determination_MI42.pdf PDF
RFI-001_Water_main_loops.docx DOCX document
Water_main_loops_site_visit_sign_in_sheet.docx DOCX document
Water_Main_Loops_Site_Visit_Minutes.docx DOCX document
RFI_001.docx DOCX document
Alpena_Base_Access_requirements.pdf PDF
B-3_Replace_Water_Main_Loops-_Drawings.pdf PDF
W912JB-18-R-9003.pdf PDF
B3_Specifications_-_Copy.doc DOC document
AF66_-_TDVG142913_Replace_Water_main_loops.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912JB-18-R-9003-0001

Amendment to Instructions to offerors section

The following revision is being made to the instructions to offerors section:

5.3 Provide a construction schedule with a period of performance (POP) not to exceed 60 days after NTP, with all “Fast Tracking” areas clearly identified if proposed. The schedule shall be task oriented, capturing all Statement of Work (SOW) requirements and indicate dates by which milestones are to be achieved. The offeror shall use either the GANNT chart or an equivalent critical path scheduling approach and the schedules shall be graphically represented. The offeror shall also submit a brief written rationale (not to exceed 2 pages, typed with no smaller than 10pt font) explaining how the schedule will be achieved.

Evaluation Factors The Best Value offer will be determined on the basis of the lowest priced proposal meeting the acceptability standards for non-priced evaluation factors.

Non-Priced Evaluation Factors listed below were evaluated on an acceptable /unacceptable basis:

• Technical

• Past Performance

TECHNICAL

The Technical Evaluation consists of one factor: Construction Schedule.

Provide a construction schedule with a period of performance (POP) not to exceed 60 days after NTP, with all “Fast-Tracking” areas clearly identified if proposed. The schedule shall be task oriented, capturing all Statement of Work (SOW) requirements and indicate dates by which milestones are to be achieved. The offeror shall use a either the GANTT chart or an equivalent critical path scheduling approach and the schedules shall be graphically represented. The offeror shall also submit a brief written rationale (not to exceed 2 pages, typed with no smaller than 10pt font) explaining how the schedule will be achieved.

Acceptability will be based on the offeror’s demonstration of execution of the construction schedule Outlining completion within the desired POP. The schedule shall capture all SOW requirements, execution timelines, And critical path items. The written rationale shall describe coordination of work activities, phasing if applicable, And demonstrate an overview of how the project will be completed on time.