Questions_and_Answers_Set_8.doc

DOC document 23 KB Posted

Attached to
Concrete Pads for Emergency Operations Tower
Solicitation number
W912GY19R0005
Issued by

View the file

Other files

File Type Posted
W192GY19R00050001.pdf PDF
Site_Visit_Sign_In_Sheet.pdf PDF
Questions_Set_7_Clarification_to_Question_1.doc DOC document
Questions_and_Answers_Set_7.doc DOC document
Questions_and_Answers_Set_6.doc DOC document
Questions_&_Answers_Set_5.doc DOC document
Concrete_Pad_Location.jpg JPG image
Questions_and_Answers_Set_4.doc DOC document
Question_and_Answer_Set_3.doc DOC document
Questions_and_Answers_Set_2.doc DOC document
Questions_and_Answers_Set_1.doc DOC document
Visitor_Request_form1246R_Mar-2017.pdf PDF
W912GY19R0005_-_CONCRETE_PADS_FOR_FIRE_TOWER.pdf PDF
EOTT_Grading_Plan_and_Location_Drawing.pdf PDF
BOLLARD_DETAIL.pdf PDF
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers Set 8

Item No. 0001 describes the scope of work and looks to be the only item that requires pricing.

Items No. A001, A002 & A003 state that these items are not separately priced and to not provide a price. Am I understanding that these items should be priced into Item No. 0001 or not priced at all?

ANSWER: The only line item that requires pricing is line item 0001. Line Items A001-A003 are contractor deliverables based on the performance work statement and are not separately priced. All costs associated with the project should be priced in line item 0001.