Amendment 0001
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912ER-17-R-0011
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
W912ER-17-R-0011-0001
Please refer to the SF-30 Block 14 Continuation Page
1. CONTRACT ID CODE PAGE OF PAGES
1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 25-May-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ER-17-R-0011
X 9B. DATED (SEE ITEM 11)
18-Apr-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
25-May-2017
CODE
W912ER DISTRICT (TAM), USACE
MIDDLE EAST DISTRICT (CETAM-CT)
PO BOX 2250
WINCHESTER VA 22604-1450
W912ER 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ER-17-R-0011 Amendment 0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
CONTINUATION PAGE
MIDDLE EAST DISTRICT
U.S. ARMY CORPS OF ENGINEERS
P.O. BOX 2250 WINCHESTER, VIRGINIA 22604-
1450 Amendment 0001
SUBJECT: Amendment 0001 to W912ER-17-R-0011, PV VII, Package C, Cairo West Air Base, Egypt
1. Specifications: Revised sections are replaced in their entirety. Revisions to the specification pages are shown on the pages in the following manner: New text is underlined and deleted text is shown using strikeout. The amendment number appears in the bottom margin on all pages of the revised sections.
The following have been revised/added:
Project Table of Contents - Replaced in its entirety Section 01 33 00
Submittal Register 7 41 63 – Added – pages 17 thru 19 of 80 8 11 16 – Deleted 08 34 59 – Deleted 22 31 00 – Revised – page 43 of 80 28 10 05 – Deleted 32 01 16.17 – Deleted 32 01 17.62 – Deleted 33 11 00 – Revised – page 69 of 80
Section 01 45 35
Attachment added in its entirety
Section 05 50 13 Paragraph 2.11 – page 12
Section 07 41 63 - Added in its entirety
Section 08 11 16 – Deleted in its entirety
Section 08 34 59 – Deleted in its entirety
Section 22 31 00
Paragraph 1.2 – page 5 Paragraph 3.4 – page 12
W912ER-17-R-0011 Amendment 0001
Section 26 56 20.00 10 Paragraph 2.1 – pages 6 and 7 Paragraph 2.4.2.6 – page 8 Paragraph 2.4.7 – page 10 Paragraph 2.4.8 – page 10 Paragraph 2.4.9 – page 10 Paragraph 2.4.11 – page 10 Paragraph 2.5 – page 10 Paragraph 2.6 – pages 10 and 11 Paragraph 3.9 – page 14 Paragraph 3.10 – page 14 Paragraph 3.11 – page 14 Paragraph 3.13.2 – page 15 Paragraph 3.14 – page 15 Paragraph 3.15 – page 15
Section 28 10 05 – Deleted in its entirety
Section 32 01 16.17 – Deleted in its entirety
Section 32 01 17.62 – Deleted in its entirety
Section 33 11 00
Section Title Revised – page 1 Paragraph 1.1 – page 4 Paragraph 1.2 – page 8 Paragraph 2.7 – pages 13 and 14 Paragraph 3.2.7 – page 19 Paragraph 3.2.8 – page 19
2. Drawings. Revisions to the following drawings are identified by a triangle placed on the drawing near each revision and a "cloud" drawn around both the triangle and change.
GI001 Index of Drawings GI003 Index of Drawings
SITE DESIGN: CD268, CG268A, CP268, XE003, XE004, XE172, XE188, XE189,
XE190, XE205, XE206, XE251, XE601, XE602, XT154, XT155, XT608 and ST007
FACILITY “LLL” SITE DESIGN: C102 and CG102
FACILITY “MSF” SITE DESIGN: C101
FACILITY H – SQUADRON OPERATIONS: AE401 and MH601
STANDARD DETAILS: New Sheet SC104 and ST052
3. Volume 1 Solicitation Instructions, Section 00 21 00: Language regarding design and evaluation of design has been removed.
4. The proposal due date has been extended to 4:00 PM (EST) on June 9, 2017.
5. All other terms and conditions remain unchanged.
File details come from the government source that posted it. Updated .