CDC_Cost_Documents_5_Apr_17.pdf
PDF 15 KB Posted
- Attached to
- Construction - Peace Vector (PV) VII Package C in Cairo, Egypt Federal contract opportunity
- Solicitation number
- W912ER-17-R-0011
About this file
Cost Breakdown Sheet and Proposal Schedule
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP: W912ER-17-R-0011 P2# 402784
PROJECT:
LOCATION: Cairo Egypt
ITEM NO. DESCRIPTION QTY UNIT TOTAL ($)
Base Bid Items
Mobilization and Demobilization for PV VII Pkg C in accordance with the Contract Documents
1 JOB
Provide Office Supplies and Support in accordance with the Contract Documents
1 NTE
$50,000
Construct New Munitions Storage Compound in accordance with the Contract Documents
1 JOB
Construct Vehicle Maintenance Facility in accordance with the Contract Documents
1 JOB
Construct Squadron Operations Building in accordance with the Contract Documents
1 JOB
Construct Additional Sewage Connections and Increase Waste Water Treatment Plant in accordance with the Contract Documents
1 JOB
Renovate Wash Rack in accordance with the Contract Documents
1 JOB
Option Items
Option 1
Mobilization and Demobilization for Miscellaneous Improvements in accordance with the Contract Documents
1 JOB
Construct Miscellaneous Improvements in accordance with the Contract Documents
1 JOB
Option 2
Mobilization and Demobilization for Access Roads at W & Z Cluster in accordance with the Contract Documents
1 JOB
Construct Access Road at W & Z Cluster in accordance with the Contract Documents
1 JOB
Option 3
Mobilization and Demobilization for Sunshade (LLL) and Personnel Support Building (CC) located at W cluster accordance with the Contract Documents
1 JOB
Construct Sunshade (LLL) and Personnel Support Building (CC) located at W cluster accordance with the Contract Documents
1 JOB
Option 4
Total Option 1 Bid Price
PROPOSAL SCHEDULE
PV VII Pkg C
TOTAL Base Bid Item(s) Price (ITEMS 0001-0007)
Total Option 2 Bid Price
Total Option 3 Bid Price
RFP: W912ER-17-R-0011 P2# 402784
PROJECT:
LOCATION: Cairo Egypt
ITEM NO. DESCRIPTION QTY UNIT TOTAL ($)
PROPOSAL SCHEDULE
PV VII Pkg C
Mobilization and Demobilization for Sunshade (LLL) and Personnel Support Building (CC) located at U cluster accordance with the Contract Documents
1 JOB
Construct Sunshade (LLL) and Personnel Support Building (CC) located at U cluster accordance with the Contract Documents
1 JOB
Option 5
Mobilization and Demobilization for Sunshade (LLL) and located at Z cluster accordance with the Contract Documents
1 JOB
Construct Sunshade (LLL) located at Z cluster accordance with the Contract Documents
1 JOB
Option 6
Mobilization and Demobilization for Airfield Lighting Vault in accordance with the Contract Documents
1 JOB
Construct Airfield Lighting Vault in accordance with the Contract Documents
1 JOB
Option 7
Mobilization and Demobilization for Telecommunication Duct Bank System in accordance with the Contract Documents
1 JOB
Construct Telecommunication Duct Bank in accordance with the Contract Documents
1 JOB
Option 8
Provide Spare Parts in accordance with the Contract Documents
1 NTE
$250,000
Total Option 8 Bid Price $250,000 Option 9
Provide Operations and Maintenance in accordance with the Contract Documents 1 Year
Total Option 9 Bid Price
TOTAL BASE AND OPTION(S) PRICE (ITEMS 0001-0023)
TOTAL OPTION(S) PRICE (ITEMS 0008-0023)
TOTAL Base Bid Item(s) Price (ITEMS 0001-0007)
Total Option 4 Bid Price
Total Option 5 Bid Price
Total Option 6 Bid Price
Total Option 7 Bid Price
RFP: W912ER-17-R-0011 P2#: 402784
PROJECT: PV VII Pkg C Cost Breakdown Sheet
PROPOSER: _____________________________
LOCATION: Cairo Egypt DATE: _____________________________
ITEM DESCRIPTION
DIRECT LABOR
COST
DIRECT
EQUIPMENT COST
DIRECT MATERIALS COST
SUB
CONTRACTOR
COST
TOTAL
DIRECT COST
INDIRECT JOOH
COST
INDIRECT HOOH
COST
PROFIT
BOND COST
TOTAL
PROPOSED PRICE
Mobilization and Demobilization for PV VII Pkg C in accordance with the Contract Documents
Provide Office Supplies and Support in accordance with the Contract Documents
$50,000
Construct New Munitions Storage Compound in accordance with the Contract Documents
0003AA Sitework, fence, Roadwork 0003BB 3 Munitions Storage Facilities 0003CC Munitions Assembly
Construct Vehicle Maintenance Facility in accordance with the Contract Documents
Construct Squadron Operations Building in accordance with the Contract Documents
Construct Additional Sewage Connections and Increase Waste Water Treatment Plant in accordance with the Contract Documents
Renovate Wash Rack in accordance with the Contract Documents
TOTAL Base Bid Item(s) Price (ITEMS 0001-0007)
Option 1
Mobilization and Demobilization for Miscellaneous Improvements in accordance with the Contract Documents
Construct Miscellaneous Improvements in accordance with the Contract Documents
Total Option 1 Bid Price
Option 2
Mobilization and Demobilization for Access Roads at W & Z Cluster in accordance with the Contract Documents
Construct Access Road at W & Z Cluster in accordance with the Contract Documents
Total Option 2 Bid Price
Base Bid
Options
RFP: W912ER-17-R-0011 P2#: 402784
PROJECT: PV VII Pkg C Cost Breakdown Sheet
PROPOSER: _____________________________
LOCATION: Cairo Egypt DATE: _____________________________
ITEM DESCRIPTION
DIRECT LABOR
COST
DIRECT
EQUIPMENT COST
DIRECT MATERIALS COST
SUB
CONTRACTOR
COST
TOTAL
DIRECT COST
INDIRECT JOOH
COST
INDIRECT HOOH
COST
PROFIT
BOND COST
TOTAL
PROPOSED PRICE
Option 3
Mobilization and Demobilization for Sunshade (LLL) and Personnel Support Building (CC) located at W cluster accordance with the Contract Documents
Construct Sunshade (LLL) and Personnel Support Building (CC) located at W cluster accordance with the Contract Documents
Total Option 3 Bid Price
Option 4
Mobilization and Demobilization for Sunshade (LLL) and Personnel Support Building (CC) located at U cluster accordance with the Contract Documents
Construct Sunshade (LLL) and Personnel Support Building (CC) located at U cluster accordance with the Contract Documents
Total Option 4 Bid Price
Option 5
Mobilization and Demobilization for Sunshade (LLL) and located at Z cluster accordance with the Contract Documents
Construct Sunshade (LLL) located at Z cluster accordance with the Contract Documents
Total Option 5 Bid Price
Option 6
Mobilization and Demobilization for Airfield Lighting Vault in accordance with the Contract Documents
Construct Airfield Lighting Vault in accordance with the Contract Documents
Total Option 6 Bid Price
Option 7
Mobilization and Demobilization for Telecommunication Duct Bank System in accordance with the Contract Documents
Construct Telecommunication Duct Bank in accordance with the Contract Documents
Total Option 7 Bid Price
Option 8
Provide Spare Parts in accordance with the Contract Documents $250,000.00
Total Option 8 Bid Price $250,000.00
Option 9
Provide Operations and Maintenance in accordance with the Contract Documents
Total Option 9 Bid Price
TOTAL OPTION(S) PRICE (ITEMS 0008-0023)
TOTAL BASE AND OPTION(S) PRICE (ITEMS 0001-0023)