Special_Instructions_Schedule.pdf
PDF 219 KB Posted
- Attached to
- Construction - Peace Vector (PV) VII Package C in Cairo, Egypt Federal contract opportunity
- Solicitation number
- W912ER-17-R-0011
About this file
Special Instructions_Schedule
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
SCHEDULE OF SPECIAL INSPECTIONS
Reference UFGS 01 45 35 for all requirements not noted as part of this schedule.
INSPECTION DEFINITIONS:
PERFORM: Perform these tasks for each weld, fastener or bolted connection, and noted verification.
OBSERVE: Observe these items randomly during the course of each work day to insure that applicable requirements are being met. Operations need not be delayed pending these inspections at contractor’s risk.
DOCUMENT: Document, with a report, that the work has been performed in accordance with the contract documents. This is in addition to any other reports required in the Special Inspections guide specification.
CONTINUOUS: Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
A. STRUCTURAL ‐ STEEL – WELDING SECTION
THIS SECTION APPLICABLE IF BOX IS CHECKED: ☐
STEEL INSPECTION PRIOR TO WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.2.1, AISC 360‐10: Table C‐N5.4‐1
TASK INSPECTION TYPE1 DESCRIPTION
1. Verify that the welding procedures specification (WPS) is available
PERFORM
2. Verify manufacturer certifications for welding consumables are available
PERFORM
3. Verify material identification PERFORM Type and grade.
4. Welder Identification System
PERFORM The fabricator or erector, as applicable, shall maintain a system by which a welder who has welded a joint or member can be identified. Stamps, if used, shall be the low‐stress type.
5. Fit‐up of groove welds (including joint geometry)
OBSERVE Joint preparation Dimensions (alignment, root opening, root face, bevel) Cleanliness (condition of steel surfaces) Tacking (tack weld quality and location) Backing type and fit (if applicable)
6. Configuration and finish of access holes
OBSERVE
7. Fit‐up of fillet welds OBSERVE Dimensions (alignment, gaps at root) Cleanliness (condition of steel surfaces) Tacking (tack weld quality and location)
STEEL INSPECTION DURING WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.2.1, AISC 360‐10: Table C‐N5.4‐2
TASK INSPECTION TYPE DESCRIPTION
8. Use of qualified welders PERFORM Welding by welders, welding operators, and tack welders who are qualified in conformance with requirements.
9. Control and handling of welding consumables
OBSERVE Packaging Electrode atmospheric exposure control
10. No welding over cracked tack welds
OBSERVE
11. Environmental conditions OBSERVE Wind speed within limits Precipitation and temperature
12. Welding Procedures Specification followed
OBSERVE Settings on welding equipment Travel speed Selected welding materials Shielding gas type/flow rate Preheat applied Interpass temperature maintained (min./max.)
Proper position (F, V, H, OH) Intermix of filler metals avoided
13. Welding techniques OBSERVE Interpass and final cleaning Each pass within profile limitations Each pass meets quality requirements
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need not be delayed pending these inspections at contractor’s risk.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
A. STRUCTURAL ‐ STEEL – WELDING SECTION (CONTINUED)
STEEL INSPECTION AFTER WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 2015 1705.2.1, AISC 360‐10: Table C‐N5.4‐3
TASK INSPECTION TYPE 1 DESCRIPTION
14. Welds cleaned OBSERVE
15. Size, length, and location of all welds
PERFORM Size, length, and location of all welds conform to the requirements of the detail drawings.
16. Welds meet visual acceptance criteria
PERFORM AND
DOCUMENT
Crack prohibition Weld/base‐metal fusion Crater cross section Weld profiles Weld size Undercut Porosity
17. Arc strikes PERFORM
18. k‐area PERFORM When welding of doubler plates, continuity plates or stiffeners has been performed in the k‐area, visually inspect the web k‐area for cracks.
19. Backing removed, weld tabs removed and finished, and fillet welds added where required
PERFORM
20. Repair activities PERFORM AND
DOCUMENT
21. Document acceptance or rejection of welded joint or member
PERFORM
END SECTION
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
B. STRUCTURAL ‐ STEEL – BOLTING SECTION
STEEL INSPECTION TASKS PRIOR TO BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.2.1, AISC 360‐10: Table C‐N5.6‐1
TASK INSPECTION TYPE 1 DESCRIPTION
1. Manufacture’s certifications available for fastener materials
PERFORM
2. Fasteners marked in accordance with ASTM requirements
OBSERVE
3. Proper fasteners selected for joint detail (grade, type, bolt length if threads are to be excluded from shear plane)
OBSERVE
4. Proper bolting procedure selected for joint detail
OBSERVE
5. Connecting elements, including appropriate faying surface condition and hole preparation, if specified, meet applicable requirements
OBSERVE
6. Proper storage provided for bolts, nuts, washers, and other fastener components
OBSERVE
STEEL INSPECTION TASKS DURING BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.2.1, AISC 360‐10: Table C‐N5.6‐2
TASK INSPECTION TYPE 1 DESCRIPTION
7. Fastener assemblies of suitable condition, placed in all holes and washers (if required) are positioned as required
OBSERVE
8. Joint brought to the snug‐tight condition prior to pretensioning operation
OBSERVE
9. Fastener component not turned by the wrench prevented from rotating
OBSERVE
10. Bolts are pretensioned in accordance with RCSC Specification, progressing systematically from the most rigid point toward the free edges
OBSERVE
STEEL INSPECTION TASKS AFTER BOLTING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.2.1, AISC 360‐10: Table C‐N5.6‐3
TASK INSPECTION TYPE 1 DESCRIPTION
11. Document acceptance or rejection of all bolted connections
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
C. STRUCTURAL ‐ STEEL ‐ NON DESTRUCTIVE TESTING SECTION
NONDESTRUCTIVE TESTING OF WELDED JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.2.1, AISC 360‐10: Section N5.5
TASK INSPECTION TYPE 1 DESCRIPTION
1. Use of qualified nondestructive testing personnel
PERFORM Visual weld inspection and nondestructive testing (NDT) shall be conducted by personnel qualified in accordance with AWS D1.8 clause 7.2
2. CJP groove welds OBSERVE Dye penetrant testing (DT) and ultrasonic testing (UT) shall be performed on 20% of CJP groove welds for materials greater than 5/16” (8mm) thick. Testing rate must be increased to 100% if greater than 5% of welds tested have unacceptable defects.
3. Welded joints subject to fatigue
OBSERVE Dye penetrant testing (DT) and Ultrasonic testing (UT) shall be performed on 100% of welded joints identified on contract drawings as being subject to fatigue.
4. Weld tab removal sites OBSERVE At the end of welds where weld tabs have been removed, magnetic particle testing shall be performed on the same beam‐to‐column joints receiving UT
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
D. STRUCTURAL ‐ STEEL – AISC 341 REQUIREMENTS (SEISMIC PROVISIONS) SECTION
NONDESTRUCTIVE TESTING OF WELDED JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.2.1, AISC 341‐10: Section J6.2
TASK INSPECTION TYPE 1 DESCRIPTION
5. CJP groove welds OBSERVE Dye penetrant testing (DT) and ultrasonic testing (UT) shall be performed on 100% of CJP groove welds for materials greater than 5/16” thick (8mm).
6. Beam cope and access hole.
OBSERVE At welded splices and connections, thermally cut surfaces of beam copes and access holes shall be tested using magnetic particle testing (MT) or dye penetrant testing (DT), when the flange thickness exceeds 1 1/2 in. for rolled shapes, or when the web thickness exceeds 1 1/2 in. for built‐up shapes.
7. K‐area NDT (AISC 341)
PERFORM Where welding of doubler plates, continuity plates or stiffeners has been performed in the k‐area, the web shall be tested for cracks using magnetic particle testing (MT). The MT inspection area shall include the k‐area base metal within 3‐inches of the weld. The MT shall be performed no sooner than 48 hours following completion of the welding.
8. Placement of reinforcing or contouring fillet welds
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
E. STRUCTURAL ‐ STEEL ‐ COMPOSITE CONSTRUCTION 1
COMPOSITE CONSTRUCTION PRIOR TO PLACING CONCRETE – VERIFY THE FOLLOWING ARE IN COMPLIANCE IBC 1705.2.1, AISC 360‐10: Table N6.1, AISC 341‐10: Table J9‐1
TASK INSPECTION TYPE 2 DESCRIPTION
1. Placement and installation of steel headed stud anchors
PERFORM
2. Material identification of reinforcing steel (Type/Grade)
OBSERVE
3. Determination of carbon equivalent for reinforcing steel other than ASTM A706
OBSERVE
4. Proper reinforcing steel size, spacing, clearances, support, and orientation
OBSERVE
5. Reinforcing steel has been tied and supported as required
OBSERVE
F. STRUCTURAL ‐ STEEL ‐ OTHER INSPECTIONS
OTHER STEEL INSPECTIONS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.2.1, AISC 341‐10: Tables J8‐1 & J10‐1
TASK INSPECTION TYPE 2 DESCRIPTION
1. Anchor rods and other embedments supporting structural steel
PERFORM Verify the diameter, grade, type, and length of the anchor rod or embedded item, and the extent or depth of embedment prior to placement of concrete.
2. Fabricated steel or erected steel frame
OBSERVE Verify compliance with the details shown on the construction documents, such as braces, stiffeners, member locations and proper application of joint details at each connection.
3. Reduced beam sections (RBS) where/if occurs
DOCUMENT Contour and finish Dimensional tolerances
4. Protected zones DOCUMENT No holes or unapproved attachments made by fabricator or erector
5. H‐piles where/if occurs DOCUMENT No holes or unapproved attachments made by the responsible contractor
1 See Concrete Construction Section for all concrete related inspection of composite steel construction.
2 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
G. STRUCTURAL ‐ COLD‐FORMED METAL DECK ‐ PLACEMENT SECTION
METAL DECK INSPECTION PRIOR TO DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC‐2011, Appendix 1, Table 1.1
TASK INSPECTION TYPE 1 DESCRIPTION
1. Verify compliance of materials (deck and all deck accessories) with construction documents, including profiles, material properties, and base metal thickness
PERFORM
2. Document acceptance or rejection of deck and deck accessories
DOCUMENT
METAL DECK INSPECTION DURING DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC‐2011, Appendix 1, Table 1.2
TASK INSPECTION TYPE 1 DESCRIPTION
3. Verify compliance of deck and all deck accessories installation with construction documents
PERFORM
4. Verify deck materials are represented by the mill certifications that comply with the construction documents
PERFORM
5. Document acceptance or rejection of installation of deck and deck accessories
DOCUMENT
METAL DECK INSPECTION AFTER DECK PLACEMENT – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC‐2011, Appendix 1, Table 1.3
TASK INSPECTION TYPE 1 DESCRIPTION
6. Welding procedure specification (WPS) available
PERFORM
7. Manufactures certifications for welding consumables available
OBSERVE
8. Material identification (type/grade)
OBSERVE
9. Check welding equipment OBSERVE
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
H. STRUCTURAL ‐ COLD‐FORMED METAL DECK – WELDING SECTION
METAL DECK INSPECTION DURING WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
SDI QA/QC‐2011, Appendix 1, Table 1.4
TASK INSPECTION TYPE 1 DESCRIPTION
1. Use of qualified welders OBSERVE
2. Control and handling of welding consumables
OBSERVE
3. Environmental conditions (wind speed, moisture, temperature)
OBSERVE
4. WPS followed OBSERVE
METAL DECK INSPECTION AFTER WELDING – VERIFY THE FOLLOWING ARE IN COMPLIANCE
SDI QA/QC‐2011, Appendix 1, Table 1.5
TASK INSPECTION TYPE 1 DESCRIPTION
5. Verify size and location of welds, including support, sidelap, and perimeter welds.
PERFORM
6. Welds meet visual acceptance criteria
PERFORM
7. Verify repair activities PERFORM
8. Document acceptance or rejection of welds
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
I. STRUCTURAL ‐ COLD‐FORMED METAL DECK – FASTENING SECTION
METAL DECK INSPECTION BEFORE MECHANICAL FASTENING – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC‐2011, Appendix 1, Table 1.6
TASK INSPECTION TYPE 1 DESCRIPTION
1. Manufacturer installation instructions available for mechanical fasteners
OBSERVE
2. Proper tools available for fastener installation
OBSERVE
METAL DECK INSPECTION DURING MECHANICAL FASTENING – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC‐2011, Appendix 1, Table 1.7
TASK INSPECTION TYPE 1 DESCRIPTION
3. Fasteners are positioned as required
OBSERVE
4. Fasteners are installed in accordance with manufacturer's instructions
OBSERVE
METAL DECK INSPECTION AFTER MECHANICAL FASTENING – VERIFY THE FOLLOWING ARE IN COMPLIANCE SDI QA/QC‐2011, Appendix 1, Table 1.8
TASK INSPECTION TYPE 1 DESCRIPTION
5. Check spacing, type, and installation of support fasteners
PERFORM
6. Check spacing, type, and installation of sidelap fasteners
PERFORM
7. Check spacing, type, and installation of perimeter fasteners
PERFORM
8. Verify repair activities PERFORM
9. Document acceptance or rejection of mechanical fasteners
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
J. STRUCTURAL ‐ LIGHT GAUGE STEEL FRAMING AND/OR LIGHT GAUGE TRUSSES SECTION
LIGHT GAUGE STEEL CONSTRUCTION AND CONNECTIONS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.2.2, 1705.11.2, 1705.11.3, UFC 4 023 03
TASK INSPECTION TYPE1 DESCRIPTION
1. Trusses spanning 60‐ feet or greater where/if applies
PERFORM Verify that temporary and permanent truss restraint/bracing is installed in accordance with approved truss submittal package.
2. Welded connections (seismic and/or wind resisting system)
OBSERVE Visually inspect all welds composing part of the main wind or seismic force resisting system, including shearwalls, braces, collectors (drag struts), and hold‐downs.
3. Connections (seismic and/or wind resisting system)
OBSERVE Visually inspect all screw attachment, bolting, anchoring and other fastening of components within the main wind or seismic force resisting system, including roof deck, roof framing, exterior wall covering, wall to roof/floor connections, braces, collectors (drag struts) and hold‐downs.
4. Cold‐formed steel (progressive collapse resisting system where/if applies)
OBSERVE Verify proper welding operations, screw attachment, bolting, anchoring and other fastening of components within the progressive collapse resisting system, including horizontal tie force elements, vertical tie force elements and bridging elements (UFC 4 023 03).
K. STRUCTURAL ‐ OPEN‐WEB STEEL JOISTS SECTION
OPEN‐WEB STEEL JOISTS AND JOIST GIRDERS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC TABLE 1705.2.3
TASK INSPECTION TYPE 1 DESCRIPTION
1. Installation of open‐ web steel joists and joist girders
OBSERVE End connections – welded or bolted Bridging – horizontal and diagonal
1 PERFORM: Perform these tasks for each weld, fastener or bolted connection, and required verification.
OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
L. STRUCTURAL ‐ CONCRETE CONSTRUCTION SECTION
THIS SECTION APPLICABLE IF BOX IS CHECKED: ☒
CONCRETE CONSTRUCTION, INCLUDING COMPOSITE DECK – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC TABLE 1705.3 (ACI 318 REFERENCES NOTED IN IBC TABLE)
TASK INSPECTION TYPE 1 DESCRIPTION
1. Inspect reinforcement, including prestressing tendons, and verify placement.
OBSERVE Verify prior to placing concrete that reinforcing is of specified type, grade and size; that it is free of oil, dirt and unacceptable rust; that it is located and spaced properly; that hooks, bends, ties, stirrups and supplemental reinforcement are placed correctly;
that lap lengths, stagger and offsets are provided;
and that all mechanical connections are installed per the manufacturer’s instructions and/or evaluation report.
2. Reinforcing bar welding OBSERVE Verify weldability of reinforcing bars other than
ASTM A 706
Inspect single‐pass fillet welds, maximum 5/16” in accordance with AWS D1.4
3. All other welding CONTINUOUS Visually inspect all welds in accordance with AWS D1.4
4. Cast in place anchors and post installed drilled anchors (downward inclined)
OBSERVE Verify prior to placing concrete that cast in place anchors and post installed drilled anchors have proper embedment, spacing and edge distance.
5. Post‐installed adhesive anchors in horizontal or upward inclined orientations
CONTINUOUS AND
DOCUMENT
Inspect as required per approved ICC‐ES report Verify that installer is certified for installation of horizontal and overhead installation applications Inspect proof loading as required by the contract documents
6. Verify use of required mix design OBSERVE Verify that all mixes used comply with the approved construction documents
7. Prior to concrete placement, fabricate specimens for strength tests, perform slump and air content tests, and determine the temperature of the concrete
CONTINUOUS At the time fresh concrete is sampled to fabricate specimens for strength test verify these tests are performed by qualified technicians.
8. Inspect concrete and/or shotcrete placement for proper application techniques
CONTINUOUS Verify proper application techniques are used during concrete conveyance and depositing avoids segregation or contamination. Verify that concrete is properly consolidated.
9. Verify maintenance of specified curing temperature and technique
OBSERVE Inspect curing, cold weather protection, and hot weather protection procedures.
10. Pre‐stressed concrete CONTINUOUS Verify application of prestressing forces and grouting of bonded prestressing tendons.
CONTINUED ON FOLLOWING PAGE
1 OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
CONTINUOUS: Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
K. STRUCTURAL ‐ CONCRETE CONSTRUCTION (CONTINUED)
CONCRETE CONSTRUCTION, INCLUDING COMPOSITE DECK – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC TABLE 1705.3 (ACI 318 REFERENCES NOTED IN IBC TABLE)
TASK INSPECTION TYPE 1 DESCRIPTION
11. Inspect erection of precast concrete members
OBSERVE
12. Verify in‐situ concrete strength, prior to stressing of tendons in post‐tensioned concrete and prior to removal of shores and forms from beams and structural slabs.
OBSERVE
13. Inspect formwork for shape, location and dimensions of the concrete member being formed.
1 OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
DOCUMENT: Document in a report that the work has been performed as required. This is in addition to all other required reports.
CONTINUOUS: Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
M. STRUCTURAL ‐ MASONRY CONSTRUCTION SECTION (ALL RISK CATEGORIES)
MASONRY CONSTRUCTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE AT START OF CONSTRUCTION
IBC 1705.4 (ACI 530‐13 TABLE 3.1.2 & 3.1.3)
TASK INSPECTION TYPE 1 DESCRIPTION
1. Compliance with approved submittals prior to start OBSERVE
2. Proportions of site‐mixed mortar. OBSERVE
3. Grade and type of reinforcement, anchor bolts, and prestressing tendons and anchorages
OBSERVE
4. Prestressing technique OBSERVE
5. Properties of thin bed mortar for AAC masonry OBSERVE
MASONRY CONSTRUCTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE PRIOR TO GROUTING
IBC 1705.4 (ACI 530‐13 TABLE 3.1.2 & 3.1.3)
TASK INSPECTION TYPE 1 DESCRIPTION
6. Grout space OBSERVE
7. Proportions of site‐prepared grout and prestressing grout for bonded tendons
OBSERVE
8. Proportions of site‐mixed grout and prestressing grout for bonded tendons
OBSERVE
9. Placement of masonry units and mortar joints OBSERVE
10. Welding of reinforcement CONTINUOUS
MASONRY CONSTRUCTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE DURING CONSTRUCTION
IBC 1705.4 (ACI 530‐13 TABLE 3.1.2 & 3.1.3)
TASK INSPECTION TYPE 1 DESCRIPTION
11. Size and location of structural elements is in compliance
OBSERVE
12. Preparation, construction, and protection of masonry during cold weather (temperature below 40oF (4.4oc) or hot weather (temp above 90oF (32.2oC))
OBSERVE
13. Application and measurement of prestressing force CONTINUOUS
14. Placement of grout and prestressing grout for bonded tendons
CONTINUOUS
15. Placement of AAC masonry units and construction of thin bed mortar joints
CONTINUOUS Continuous for first 5000 square feet only (465 square meters).
16. Observe preparation of grout specimens, mortar specimens, and/or prisms
OBSERVE
17. Type, size and placement of reinforcement, connectors, anchor bolts and prestressing tendons and anchorages, including details of anchorage of masonry to structural members, frames, or other construction
1 OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
CONTINUOUS: Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
N. STRUCTURAL ‐ WOOD CONSTRUCTION – SPECIALTY ITEMS SECTION
WOOD CONSTRUCTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.5
TASK INSPECTION TYPE 1 DESCRIPTION
1. High‐load diaphragms where applicable
OBSERVE Verify thickness and grade of sheathing, size of framing members at panel edges, nail diameters and length, and the number of fastener lines and that fastener spacing is per approved contract documents.
2. Metal‐plate connected wood trusses spanning 60 feet or greater
OBSERVE Verify that the temporary installation restraint/bracing and the permanent individual truss member restraint/bracing are installed in accordance with the approved truss submittal package
O. STRUCTURAL ‐ WOOD CONSTRUCTION ‐ SEISMIC & WIND SECTION
WOOD CONSTRUCTION SEISMIC AND WIND – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.5
TASK INSPECTION TYPE 1 DESCRIPTION
1. Nailing, bolting, anchoring and other fastening of elements of the main wind/seismic force‐ resisting system
OBSERVE Includes connectors for: shearwall sheathing, roof/floor sheathing, drag struts/collectors, braces, hold downs, roof and floor framing connections to exterior walls.
P. STRUCTURAL – ISOLATION AND ENERGY DISSIPATION SYSTEMS SECTION
ISOLATION AND ENERGY DISSIPATION SYSTEMS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC TABLE 1705.2.3
TASK INSPECTION TYPE 1 DESCRIPTION
1. Fabrication and installation OBSERVE Verify that fabrication and installation of isolator units and energy dissipation devices conform to manufacturer’s recommendations and approved construction documents
1 OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
Q. GEOTECHNICAL ‐ SOILS INSPECTION SECTION
SOILS INSPECTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.6
TASK INSPECTION TYPE 1 DESCRIPTION
1. Materials below shallow foundations are adequate to achieve the design bearing capacity.
OBSERVE
2. Excavations are extended to proper depth and have reached proper material
OBSERVE
3. Verify use of proper materials, densities and lift thicknesses during placement and compaction of compacted fill
CONTINUOUS
4. Prior to placement of compacted fill, inspect subgrade and verify that site has been prepared properly.
OBSERVE During fill placement, the special inspector shall verify that proper materials and procedures are used in accordance with the provisions of the approved geotechnical report
R. GEOTECHNICAL ‐ DRIVEN DEEP FOUNDATION ELEMENTS SECTION
DEEP DRIVEN FOUNDATION CONSTRUCTION – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.5
TASK INSPECTION TYPE 1 DESCRIPTION
1. Verify element materials, sizes and lengths comply with requirements
CONTINUOUS
2. Inspect driving operations and maintain complete and accurate records for each element
CONTINUOUS
3. Verify placement locations and plumbness, confirm type and size of hammer, record number of blows per foot of penetration, determine required penetrations to achiever design capacity, record tip and butt elevations and document ay damage to foundation element
1 OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
CONTINUOUS: Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
S. GEOTECHNICAL ‐ HELICAL PILE FOUNDATIONS SECTION
HELICAL PILE FOUNDATIONS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.9
TASK INSPECTION TYPE 1 DESCRIPTION
1. Record installation equipment used, pile dimensions, tip elevations, final depth, final installation torque and other pertinent installation data. The approved geotechnical report and the contract documents shall be used to determine compliance
T. GEOTECHNICAL ‐ CAST IN PLACE DEEP FOUNDATION ELEMENTS SECTION
CAST IN PLACE DEEP FOUNDATION ELEMENTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.8
TASK INSPECTION TYPE 1 DESCRIPTION
1. Inspect drilling operations and maintain complete and accurate records for each element.
2. Verify placement locations and plumbness, confirm element diameters, bell diameters (if applicable), lengths, embedment into bedrock (if applicable and adequate end‐bearing strata capacity. Record concrete or grout volumes
1 CONTINUOUS: Constant monitoring of identified tasks by a special inspector over the duration of performance of said tasks.
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
U. FIRE PROTECTION ‐ SPRAYED FIRE‐RESISTANT MATERIALS SECTION
SPRAYED FIRE RESISTANT MATERIALS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.14
TASK INSPECTION TYPE 1 DESCRIPTION
1. Surface condition OBSERVE
Prior to application confirm that surface has been prepared per the approved fire‐resistance design and manufacturer’s instructions.
2. Application OBSERVE Prior to application confirm that the substrate meets the minimum ambient temperature per the approved fire‐ resistance design and manufacturer’s instructions.
3. Material thickness OBSERVE Verify that the thickness of the SFRM to structural elements is not less than the thickness require by the fire‐resistant design in more that 10 percent of the measurement, but in no case less than minimum allowable thickness required by 1705.14.
4. Material density OBSERVE Verify that the thickness of the SFRM to structural elements is not less than the thickness require by the fire‐resistant design in more than 10 percent of the measurement, but in no case less than minimum allowable thickness required by IBC 1705.14.5
5. Bond strength OBSERVE Verify cohesive/adhesive bond strength of the cured SFRM applied to the structural element is not less than 150psf and according to IBC 1705.14.6
END SECTION
V. FIRE PROTECTION ‐ MASTIC AND INTUMESCENT COATINGS SECTION
THIS SECTION APPLICABLE IF BOX IS CHECKED: ☐
MASTIC AND INTUMESCENT FIRE‐RESISTANT COATINGS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.15
TASK INSPECTION TYPE 1 DESCRIPTION
1. Surface preparation OBSERVE
Inspections shall be performed in accordance with AWCI 12‐B and the contract documents
W. FIRE PROTECTION – FIRE RESISTANT PENETRATIONS AND JOINTS SECTION
FIRE RESISTANT PENETRATIONS AND JOINTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.17
TASK INSPECTION TYPE 1 DESCRIPTION
1. Inspections of penetration firestop systems conducted in accordance with ASTM E 2174.
2. Inspections of fire‐resistant joint systems conducted in accordance with ASTM E 2393
1 OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
X. FIRE PROTECTION – SMOKE CONTROL SECTION
SMOKE CONTROL – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.17
TASK INSPECTION TYPE 1 DESCRIPTION
1. Verify device locations and perform leakage testing
Perform during erection of ductwork and prior to concealment
2. Pressure difference testing, flow measurements and detection and control verification
Perform prior to occupancy and after sufficient completion
1 OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
Y. ARCHITECTURAL ‐ EXTERIOR INSULATION AND FINISH SYSTEMS SECTION
EXTERIOR INSULATION AND FINISH SYSTEMS (EIFS) – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.16
TASK INSPECTION TYPE 1 DESCRIPTION
1. Water resistive barrier coating applied over a sheathing substrate.
Verify that water resistive barrier coating complies with ASTM E 2570.
Z. ARCHITECTURAL – ARCHITECTURAL COMPONENTS
ARCHITECTURAL COMPONENTS – VERIFY THE FOLLOWING ARE IN COMPLIANCE
IBC 1705.12.5, 1705.12.7
TASK INSPECTION TYPE 1 DESCRIPTION
1. Erection and fastening of exterior cladding and interior and exterior veneer.
Verify appropriate materials, fasteners and attachment at commencement of work and at completion. Inspector Note: Inspection not required if height is less than 30 feet or weight is less than 5psf
2. Interior and exterior non‐ load bearing walls
OBSERVE Verify appropriate materials, fasteners and attachment at commencement of work and at completion. Inspector Note: Inspection not required if height is less than 30 feet. Also, Interior non‐load bearing walls need not be inspected if weighing less than 15psf
3. Access floors OBSERVE Verify that anchorage complies with approved construction documents. Inspection of post‐installed anchors shall comply with approved ICC‐ES report
4. Storage racks OBSERVE Verify that anchorage complies with approved construction documents. Inspection of post‐installed anchors shall comply with approved ICC‐ES report.
Inspector Note: Not required for racks less than 8 feet in height
1 OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
SCHEDULE OF SPECIAL INSPECTIONS (UFGS 01 45 35) REVISED FOR IBC 2015 ON 9/30/16
AA. PLUMBING/MECHANICAL/ELECTRICAL DESIGNATED SEISMIC SYSTEMS SECTION
PLUMBING, MECHANICAL AND ELECTRICAL ‐ DESIGNATED SEISMIC SYSTEMS
IBC 1705.12.4
TASK INSPECTION TYPE 1 DESCRIPTION
1. Designated Seismic Systems equipment verification
Verify model number and serial number are in conformance with project specific seismic qualification (PSSQ)
Verify Tag ID is correct and installed per specifications
2. Designated Seismic Systems equipment Mounting
OBSERVE Verify that Anchor Base Bolting is installed per PSSQ
Verify that Equipment Bracing is Installed per PSSQ
Verify that Bracing Attachments are installed per PSSQ
3. Designated Seismic Systems utility Conduit/Piping
OBSERVE Verify that Conduit/Piping is connected to the equipment per PSSQ (flex or rigid)
Verify that Conduit/Piping is seismically supported independently of equipment and in accordance with PSSQ support requirements
4. Designated Seismic Systems clearance OBSERVE Adjacent Equipment – Verify that there is adequate gap to eliminate possibility of pounding
Conduit/Piping ‐ Verify that there is adequate gap to eliminate possibility of pounding
1 OBSERVE: Observe these items on a random sampling basis daily to insure that applicable requirements are met. Operations need
File details come from the government source that posted it. Updated .