Attachment 6 - TE 7.5.3 - Fort Gordon Turn Over Memos

View the file

Other files for this federal contract opportunity

Other files attached to FORT GORDON BASE OPERATIONS AND MAINTENANCE SUPPORT SERVICES REQUEST FOR PROPOSAL - SOLICITATION, newest first.
File Type Posted
W91249-18-R-0001-0004.docx DOCX document
Attachment_16_-_Revised_Questions_&_Responses_to_Solicitation_&_Amendment_0001_0002__and_0003.pdf PDF
W91249-18-R-0001-0003.pdf PDF
Attachment_16_-_Revised_Questions_&_Responses_to_Solicitation_&_Amendment_0001.pdf PDF
Attachment_10_-_Pricing_and_Labor_Matrix_Worksheet_(Revision_1).xlsx XLSX spreadsheet
Technical_Exhibit_7.5.9.8.1__Dumpster_Locations_List.docx DOCX document
Attachment_16_-_Questions_&_Responses_to_Solicitation_&_Amendment_0001.pdf PDF
Amendment_W91249-18-R-0001-0001.pdf PDF
Attachment_10_-_Pricing_and_Labor_Matrix_Worksheet.xlsx XLSX spreadsheet
Technical_Exhibit_7.3.3__PWO_Workload.docx DOCX document
Technical_Exhibit_7.5.9.1__Central_Energy_Plant_No__1_Bldg_25910_Installed_Equipment.docx DOCX document
Technical_Exhibit_7.3.1__DMO_Workload.docx DOCX document
Technical_Exhibit_7.5.7.8_Fort_Gordon_Cemeteries.doc DOC document
Technical_Exhibit_7.5.9.7_Fuel_Oil_Tanks_At_Dual_Fired_Facilities.doc DOC document
Technical_Exhibit_7.5.6.12_Emergency_Generators.docx DOCX document
Technical_Exhibit_7.3.4__RPMA_Supply_Operations_Estimated_Workload.docx DOCX document
Technical_Exhibit_7.5.6.7_Lifts_and_Cranes_Inventory.docx DOCX document
Technical_Exhibit_7.3.2__OWO_Workload.docx DOCX document
Technical_Exhibit_7.3.7_Estimated_Furniture_Management_Workload.docx DOCX document
Technical_Exhibit_7.5.4.2_Water_Monitoring_Wells_Requiring_Sampling_and_Analysis.docx DOCX document
Technical_Exhibit_7.5.7.1_Ft._Gordon_Grounds_Mowing_Map.docx DOCX document
Attachments_4_-_6_-_DRAFT_Technical_Exhibits_7.3_7.4_7.5.docx DOCX document
Technical_Exhibit_7.5.6.18_Public_Works_Look_Ahead_Report_Template.doc DOC document
Attachment_10_-_Pricing_and_Labor_Matrix_Worksheet.xlsx XLSX spreadsheet
Technical_Exhibit_7.5.7.9_Pruning_Standards.docx DOCX document
Technical_Exhibit_7.5.8.1_Recreation_and_Athletic_Fields.docx DOCX document
Technical_Exhibit_7.5.8.4_Special_Events_Taskings.doc DOC document
Technical_Exhibit_7.5.5.1._Pest_Control_Amplifying_Information.docx DOCX document
Technical_Exhibit_7.4.2_Government_Furnsihed_Equipment.docx DOCX document
Technical_Exhibit_7.5.7.7.1_Estimated_IDIQ_Qunatities.docx DOCX document
Attachment_9_-_Davis_Bacon_Act_(DBA)_Wage_determination_GA165.pdf PDF
Technical_Exhibit_7.5.6.6_Range_Hood_Cleaning_Services.docx DOCX document
Technical_Exhibit_7.5.7.5_Range_Mowing_Map.docx DOCX document
Technical_Exhibit_7.5.9.2__Central_Energy_Plant_No._1_Building_25910_Buildings_Served.docx DOCX document
Technical_Exhibit_7.5.7.7_Flower_Beds.doc DOC document
Attachment_11_-_Sample_Past_Performance_Cover_Letter.docx DOCX document
Technical_Exhibit_7.5.4.3_Underground_Storage_Tanks.docx DOCX document
Technical_Exhibit_7.4.5__Government_Furnished_Vehicles.docx DOCX document
Technical_Exhibit_7.4.3__Fort_Gordon_Facility_Listing_(Excluding_Privatized_Facilities).docx DOCX document
Technical_Exhibit_7.5.8.5_Lakes_and_Ponds.docx DOCX document
Technical_Exhibit_7.5.6.2_Electrical_Lines_of_Demarcation.doc DOC document
Attachment_8_-_Service_Contract_Act_(SCA)_Wage_Determation_2015-4465_Rev5.pdf PDF
Technical_Exhibit_7.5.9.8_Dumpster_Container_Cleaning_List.docx DOCX document
Technical_Exhibit_7.5.6.3__Natural_Gas_Lines_of_Demarcation.doc DOC document
Technical_Exhibit_7.5.9.3a__Plant_No._1_Operation_CEP_CHW_and_High_Temperature_Water_(HTW).doc DOC document
Technical_Exhibit_7.4.7_Energy_Conservation_Measures.docx DOCX document
W91249-18-R-0001.pdf PDF
Technical_Exhibit_7.4.1__Contractor_Personnel_Minimum_Qualifications.docx DOCX document
Technical_Exhibit_7.5.7.6_Semi-Improved_Grounds_Maintenance_Areas_Frequency_Schedule.docx DOCX document
Technical_Exhibit_7.5.6.20_Pest_Control_Services_Look_Ahead_Report_Template.doc DOC document
Show all 50

FORT GORDON BASE OPERATIONS AND MAINTENANCE SUPPORT SERVICES REQUEST FOR PROPOSAL - SOLICITATION has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Exhibit 7.5.3 Fort Gordon Turn Over Memos

MEM-001

CESAS-CD-GOC

MEMORANDUM FOR: Director of Public Works (IMSE-GOR-PWF), Fort Gordon, GA 30905 ATTN: DPW O&M Division

SUBJECT: Contract {CONTRACT_NO} {DELV_ORDER_NO}, {CONTRACT_TITLE}, Real Property transfer for Building {ASK_LINEOFTEXT Enter Building Number} DPW Work Order #: DExxxxx-xP

Attached are copies of the following documents/materials relating to the subject project, supplied in the quantities indicated:

1.Operation & Maintenance Manuals (one hardcopy/ three CDs, or per contract)Initial or N/A
□ Fire Alarm____________
□ Sprinkler____________
□ Mechanical____________
□ Plumbing____________
□ Electrical____________
2.Training Videos (two CDs or per contract) and Sign-in sheets (one hardcopy)
□ Fire Alarm____________
□ Sprinkler____________
□ Mechanical____________
□ Plumbing____________
□ Electrical____________

3. Operational Certificates & Reports (one hardcopy/ no deficiencies)

□ Test/Balance (TAB) Report____________
□ Commissioning Report____________
□ Onyx (one CD)____________
□ NFPA 13 System Acceptance____________
□ NFPA 72 System Acceptance (three hardcopies)____________
□ UFC 3-600-01 Design Analysis and Sealed Red-Line(CD)____________
4.Submittals/ Shop Drawings (one CD and/ or hardcopy)____________
5.Installed Equipment List (one CD with Excel file and hardcopy)____________
6.Warranty Management Plan/ Extended Warranties (one CD & one hardcopy)____________
7.O&M Component Keys (XLS Spread Sheet)____________
8.Spare Parts (Transfer Property List & Signed Acknowledgement of Receipt)____________
Sincerely,

{SIGNATURE_NAME}

{SIGNATURE_TITLE}

Encl (as specified above)

{LETTER_NO}

Pat Arthur
Receipt AcknowledgedDivison Chief__________________________________
Name / TitleSignatureDate

MEM-002

CESAS-CD-GOC

ATTN: DPW Engineering Division

SUBJECT: Contract {CONTRACT_NO} {DELV_ORDER_NO}, {CONTRACT_TITLE}, Real Property transfer for Building {ASK_LINEOFTEXT Enter Building Number}Error! Reference source not found.

DPW Work Order #: DExxxxx-xP

Attached are copies of the following documents/materials relating to the subject project, supplied in the quantities indicated:

Initial or N/A
1.Warranty
□ Warranty Management Plan (one CD and one hardcopy)____________
□ Certificates (extended warranties) (originals)____________
□ Installed Equipment List (one CD and/ or hardcopy)____________
2.Drawings
□ Redline Drawings (one hardcopy)____________
□ Final As-Builts (one CD and hardcopy)____________

3. As-Built Specifications (one CD ) ____________

4. BIM Model (CD only) ____________

5. GIS Documentation (CD only) ____________

6. LEED Documentation (one CD and/ or hardcopy) ____________

7. Shop Drawings (CD only) ____________

Sincerely, Encl (as specified above)

{LETTER_NO}

Receipt AcknowledgedEng. Div. Chief__________________________________
Name / TitleSignatureDate

ATTN: DPW Environmental Division

SUBJECT: Contract {CONTRACT_NO} {DELV_ORDER_NO}, {CONTRACT_TITLE}, Real Property transfer for Building {ASK_LINEOFTEXT Enter Building Number}

Attached are copies of the following documents relating to the subject project, supplied in the quantities indicated:

NPDES & LID Stormwater Documentation, Initial or N/A (Site one acre or more, provide NPDES documentation; Site less than one acre, provide LID documents.)

· NPDES/ LDA daily, weekly, monthly inspection reports____________
· Turbidity Monitoring Results____________
· Final Approved and Red-lined SWPPP Drawings____________
· Notice of Termination (NOT)____________
· Final Approved Erosion Control Plan and Red-lined Erosion Control Drawings____________

Hazardous Waste Documentation

· Asbestos Shipment Records____________
· Asbestos/ Lead Paint Remediation Documents & Certificates____________

Pesticide/ Termiticide Application Record and Applicator Certification ____________

Construction Waste Dump/Haul Tickets (verification of 50% diversion) ____________

LEED Documentation ____________

Spill Control and Countermeasure Plan requirement.

· Aboveground Storage tank (AST) design, specifications, operation and maintenance manuals, spill plan addition / modification. ____________

· Generator design, specifications, o/m manual, fuel type, compliant fuel storage documentation and spill control design specifications. ____________

· UST installation design, specifications, certifications, testing results. ____________

· UST removals provide content sampling analysis, certification of tank destruction, manifest of disposal of contents, IDW disposal documentation and manifests. Confirmatory soil sampling of surrounding soil, old spill contamination of no spill contamination. ____________

GIS Documentation electronic – complete and legible file. ____________ Compliant with current approved version of SDSFIE; Compliant with Army Quality Assurance Plan (QAP) for that data layer, if available; Projected into WGS84 UTM 17N or NAD83 Georgia State Plane East coordinate system.

NEPA mitigation specified in documentation and attached memorandum ____________

Sincerely, {SIGNATURE_NAME}

Encl (as specified above)

{LETTER_NO}

DPW Environmental Division Chief _____________________________________________
Date

MEM-004

CESAS-CD-GOC

ATTN: DPW Real Property Accountable Officer

SUBJECT: Contract {CONTRACT_NO} {DELV_ORDER_NO}, {CONTRACT_TITLE}, Real Property transfer for Building {ASK_LINEOFTEXT Enter Building Number} DPW Work Order #: DExxxxx-xP

Attached are copies of the following documents/materials relating to the subject project:

Initial or N/A

1. For each Capitalized Improvement DD Form 1354 ____________

2. Lifecycle Event Transaction Information; as applicable Acquisition Event - Work Authorization (one required for each event)

o DA Form 4283 (OMA)____________
o DA Form 1391 (MILCON, or OMA > $5M)____________

3. Contract front page, pertinent statement of work describing, Task Orders/Delivery Orders

o DD Form 1155 (ALL Task Orders)____________
o SF Form 1442 (MILCON)____________

4. Photographs (before and after construction) ____________

5. Construction Data

o Length, width, depth L x W x D____________
o Number of floors____________
o Exterior material: Steel, Metal, Brick, Stucco, Block, Wood, etc.____________
o Customer ID: DE (DPW), DL (DOL), etc.____________
6. 11” X 17” Floor Plan____________
7. Facility Keys & Keying Schedule/ Plan (per DPW Key.xls)____________
8. LEED Scorecard (signed as required per contract)____________

NOTE: This is the last Turn-Over Document to be signed and formally transfers project to DPW.

Sincerely, Encl (as specified above)

{LETTER_NO}

Receipt Acknowledged__________________________________
Name / TitleSignatureDate