The resultant contract w ill be an Indefinite Delivery Indefinite Quantity (IDIQ) Multiple Aw ard Task Order Contract (MATOC) for Construction
A. This acquisition is restricted to 100% HUB Zone. Business concerns..
B. The assisgned NAICS Code is 236220, "Commercial and Institutional Building Construction" w ith a small business size standard of $39.5 million.
C. The MATOC is to based on a general Statement of Work (SOW) further defined in individual Task Orders.
D. The number of contracts that may be aw arded as a result of this solicitation shall not exceed Eight (8).
E. The estimated program value for all task orders to be placed over the four (4) year ordering period of the resulting contract w ill be $7.2 million.the program ceiling is $7.2 million.
F. The estimated Magnitude of the Seed Project is betw een $2,000 - $25,000.
G. The minimum dollar value of each task order is $2,000.00.
H. The maximum dollar value of each task order is $25,000.
I. Blocks 11, 12 (See Section H.5 and 13B apply to individual Task Orders
FRANK A. FOGG 910-907-5104
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
07-Jul-2022
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________30 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________52.211.10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________ copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
MICC CENTER - FORT BRAGG
MICC - FORT BRAGG
2175 REILLY ROAD STOP A
FORT BRAGG NC 28310-5000
W91247
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
(hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W9124722R0064 46
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W9124722R0064
Section A - Solicitation/Contract Form
SOLICITATION/CONTRACT FORM
NOTE:
1. The guaranteed minimum for this requirement is $2,000.00 and is applicable ONLY to the first year of the five year ordering period. A task order will be separately issued to each awardee under this requirement to satisfy this guaranteed minimum. There is no guaranteed minimum applicable to any task orders issued during the lifetime of the contract. The total program ceiling for the DPW minor construction Sustainment, Restoration and Modernization (SRM) program at Fort Bragg contracts is $7,200,000.00.
2. The Government is under no obligation to issue any task orders against contracts resulting from this solicitation in excess of the guaranteed minimum. In addition, task orders SHALL NOT be issued for work that exceeds statutory limitation for new construction.
3. The Minor Construction MATOC program assigned General Construction (NACIS: 236220) and comprises of three (3) individual sub -groups: Electrical (NAICS: 238210), HVAC/Plumbing (NAICS: 238220),and All Other Specialty Trade Contractors. (NAICS: 238990)
4. The Contract Line Item Number (CLIN) structure shall be established individually at the Task Order (TO) level.
The Pricing of TOs shall be pursuant to the instructions and limitations provided at Section H, Special Contract Requirements, the MA IDIQ Cap Rates, and instructions at the individual task order level. Offerors binding MA IDIQ CAP RATES (submitted in accordance with section L) shall be included into the table provided at Attachment
6 – MA IDIQ CAP RATES.
Note that bonds shall be reimbursed at cost, no profit, G&A or overhead allowed once proof of payment is furnished.
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Each Minor Construction MATOC
FFP
The contractor shall provide (as specified in each Task Order (TO) under the resulting contract) all labor, equipment, materials and supervision necessary to perform a broad range of construction, repair, maintenance services on real property at Fort Bragg, Simmons and Pope Field, North Carolina to include Camp MacKall, NC. Work shall be performed in accordance with the terms and conditions of the resulting contract, Statement of Work, and Specifications and Drawings as required in any resulting individual TO issued. All work shall be in accordance with local, state, and federal codes. Estimated Program Value is $7.2 million with a Program Ceiling of $7.2 million.Ordering Period: 12-August-2022 through 01-Oct-2026 FOB: Destination
PSC CD: Z1QA
NET AMT
Section C - Descriptions and Specifications
DESCRIPTIONS AND SPECIFICATION
SECTION C
DESCRIPTION AND SPECIFICATIONS
MATOC IDIQ STATEMENT OF WORK
GENERAL PROVISIONS FOR TASK ORDERS
C.1. DESCRIPTION OF WORK: This Multiple Award Task Order Contract (MATOC) will be used to execute a broad range of maintenance, repair, and minor construction projects at Fort Bragg (including Camp Mackall and other Fort Bragg maintained areas) in North Carolina. During the contract span, the Government will identify Tasks required to complete each project. The Contracting Officer (KO) will issue Request for Task Order Proposals (RTOP) to the awarded Contractor(s) to compete for projects.
C.2. MINIMUM QUALIFICATIONS
2.1. PROJECT MANAGEMENT: Contractor shall provide qualified key personnel to manage and execute Task Orders (TO) awarded under this contract. The work management staff shall have project design, quality control, safety, construction, and financial management capability,at a minimum the contractor staff a separate Quality Control Mananger and Superintendent to support field operations for each task order. The contractors superintendent may also serve as the site Safety and Health Officer(SSHO) provided minimum SSHO qualifications are met in accordance with paragraph C.27
2.2. LICENSURE AND CERTIFICATION
2.2.1 CONTRACTOR AND SUBCONTRACTORS:The Contractor shall have a General Construction (GC) license and certification in the contental US and/or its territorys and must abide by State of North Carolina (NC) building codes and all other applicable codes and regulations.The Contractor, or at least one subcontractor retained by the Contractor, shall be licensed and certified in each of the following Specialties: General Construction, Electrical,Plumbing, Heating (HVAC), and All other Sspecialties.
C.3. WORK EXECUTION
3.1. COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK: Contractor shall be required to commence work by an agreed upon date specified in the Task Order Notice to Proceed (NTP) letter.The Construction NTP shall not be issued until the Contractor submits and obtains KO approval of the contractor’s Accident Prevention Plan (APP), Environmental Protection Plan (EPP), and Quality Control Plan (QCP). Within 10 work days after award of the Task Order, the Contractor shall submit these documents to the KO/COR. The Contractor shall complete work not later than the negotiated schedule specified in the TO.
3.2. SUBCONTRACTORS: The prime Contractor shall ensure subcontractors are licensed, certified, competent, and capable of handling all assigned tasks.
3.3. QUALITY CONTROL PLAN (QCP): The QCP shall describe methods for surveillance of the work, including that executed by subcontractors, and in-house Contractor quality control inspectors. The QCP shall be incorporated into and become part of this contract after the plan has been accepted by the KO.
Proposed changes made after KO acceptance shall be submitted in writing through the Contracting Officer Representative (COR) to the KO for review and acceptance prior to implementing any revision. The QCP shall be maintained throughout the life of the Task Order and shall include the Contractor’s procedures to routinely evaluate the effectiveness of the QCP to ensure the Contractor is meeting the performance standards and requirements of the contract. Contractor shall prepare a Quality Control Report (QCR) daily.
The QCR shall be submitted to the COR at least weekly throughout the duration of the TO.
3.4 Nonconformance Report(NCR): When the Contractor's performance is unsatisfactory, a NCR will be issued by the KO. The Contractor shall reply in writing within 5 work days from the date of receipt of the NCR, giving the reasons for the unsatisfactory performance, corrective action taken, and procedures to preclude recurrence.
C.4. RESPONSE REQUIREMENT: The primary goal of this MATOC is the expedient acquisition of facilities requirements, therefore Contractor responsiveness is paramount. Once the KO notifies the Contractor of an existing requirement, the Contractor shall expeditiously prepare the quotes. Upon notification of a routine TO requirement, the Contractor shall respond to the Government within 5 work days as follows: (1) By visiting the proposed work site, accompanied by the KO or COR; or (2) By establishing verbal contact with the KO or COR to further define the scope of the requirement. In the event of an emergency TO requirement, the Contractor’s response time shall be as soon as directed by the KO.
The Contractor or its designated representative who is able to make decisions and obligate the Contractor must be readily available to communicate with KO.
4.4. CONSTRUCTION PRICING. Contractor shall submit detailed construction pricing sufficient to ensure Work Classification types. Detailed unit pricing may be required. This need for this requirement will be established during negotiation of individual TOs.
4.5. CERTIFICATES OF COMPLIANCE AND MATERIAL SUBMITTALS. The Contractor shall submit for approval all certificates of compliance and material submittals required in the technical specifications.
Required submittals shall be submitted for approval not later than 10 days prior to the approval date needed to achieve compliance with the approved project schedule. Approval must be received from the KO or COR before incorporating the materials into the work. The Contractor shall provide a Submittal Register listing all required submittals in the contract to the COR at the time of the first submittal. Submittal forms (ENG Form 4025-R) and a sample Submittal Register (ENG Form 4288-R) will be provided at the Pre- Performance Conferences.
C.6. INSTALLATION DESIGN GUIDE (IDG): All work performed on Fort Bragg shall conform to the requirements and guidelines of the Fort Bragg IDG. The IDG can be accessed at the following web address:
\\155.149.232.124\inetpub\wwwroot\BraggIDG\documents\upload\idg.pdf . The guide provides general and specific guidance in many areas regarding site and facility appearance, material types, finishes (interior and exterior), installation districts (identified by land use and cultural/historic significance), and installation preferences in many important technical areas.Contractors shall also abide y the NEC and all NC Building codes.
C.7. WORK HOURS: Normal duty hours for Fort Bragg and other Army facilities covered by this MATOC are 7:30 A.M. through 4:00 P.M., Monday through Friday. Work on weekends, recognized Federal holidays, or other than normal duty hours must be coordinated with the KO or COR.
C.8. CONTRACTOR’S SUPERINTENDENT: The Contractor shall appoint a full time, qualified superintendent in writing and shall submit the appointment letter with the job superintendent’s name, telephone number and qualifications to the KO and COR 5 days prior to commencement of work on any TO. The superintendent shall have a minimum of four years of superintendence experience, shall have authority to act on behalf of the contractor and shall superintend the project on site daily. In the absence of the superintendent, an alternate superintendent shall be appointed in writing as described above and shall possess the same minimum qualifications.
C.9. CONSTRUCTION SITE MAINTENANCE: Contractor shall store all supplies and equipment on project site so as to preclude theft or damage. Contractor shall maintain each site in a neat and orderly manner. Protection and security for materials and equipment on site is the sole responsibility of the Contractor. The Contractor may be required to install temporary fencing to protect the site, at no cost to the Government.
C.10. WORK AREAS
10.1. The Contractor shall protect and preserve Government property at all times within the work area and adjacent areas that could be affected by the accomplishment of the work specified and indicated. Also, the Contractor shall protect all parties and individuals within or near the work areas who could be endangered by the installation of the work. Protection requirements include protecting the interior of the facility from inclement weather. Any actions necessary to provide adequate protection are solely the Contractor’s responsibility. The contractor shall be required to maintain noise and dust control.
10.2. The Contractor is required to cover equipment that is to remain in place within the area of contract operations and protect it against damage or loss and store equipment that is removed in performance of work where directed or used in work as required by drawings and specifications. Equipment temporarily removed shall be protected and returned equal to its condition prior to starting work at no additional expense to the Government. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the Contractor.
10.3. Contractor shall provide protective barriers for all grass, trees, shrubs, sidewalks, curbs, and gutters within the construction boundary. Furthermore, such items, including grass, outside the construction boundary shall also be protected during delivery of materials and / or moving of equipment. Damages caused by the Contractor to existing grounds, plants, pavements, utilities, work by others, fixtures, or furnishings shall be repaired or replaced by the Contractor, at no cost to the Government. Such repairs or replacements shall be of as good of condition as existed before the damaging, unless such existing work is scheduled for removal or replacement by the work requirements of the contract. This requirement also pertains to grading of site to remove all clods and grade irregularities prior to final inspection and acceptance. The Contractor may be required to install temporary fencing to protect the site, at no cost to the Government.
10.3.1. In some instances, furniture and portable office equipment in the immediate area shall be moved by the Contractor and replaced to original position upon completion of the work. If the work required by the TO will not allow furniture and portable office equipment to be replaced to its original position, the KO will designate new location(s) for the Contractor.
10.3.2. Delivery of materials and equipment shall be made with a minimum of interference to Government operations and personnel.
10.3.3. The work shall, so far as practicable, be done in definite sections or phases and confined to limited areas which shall be completed before work in other sections or phases is begun. The KO has final approval for variations to work areas.
10.3.4. The Contractor shall maintain, on all construction sites with work in progress, approved copies of the following as they apply to the TO: SOW, drawings, contract and contract modifications; excavation, hot work and borrow permits; and Accident Prevention, Quality Control and Environmental Protection Plans.
10.3.4.1 The contractor shall obtain an approved excavation permit from the DPW Operations & Maintenance Division (910-396-0325), with on-site utilities located and/or cleared, prior to beginning excavation. The contractor shall maintain located utility markings throughout the duration of the contract.
The excavation permit is only valid for 60 days and the contractor must obtain a new permit upon expiration of the original permit. The contractor shall hand-locate and use extreme care when working near marked utilities. The contractor is responsible for making emergency notifications (e.g., to the fire department and COR) in the event a utility is struck and the contractor shall be held financially responsible for repairs in the event of negligence.
10.3.4.2. The contractor shall obtain an approved hot work permit (DA Form 5383-R) from the Directorate of Emergency Services (DES) at 910-907-4813 prior to performing any hot work such as brazing, welding, cutting, torching, soldering, etc…. If conditions or locations change or the permit expires, the contractor must obtain a new permit. The contractor must maintain a fire watch and perform other measures (e.g., maintain a fire extinguisher on site) as directed by the DES and will ensure work areas are made safe and secure at the end of operations.
C.11. UTILITY OUTAGES AND ROAD CLOSURES: Utility, road, and railroad outages, detours, and closures will require minimum 10 working days advance written notice and will be subject to KO/COR approval. In the case of road closures, a sketch shall be provided showing the closure location and all necessary signs and barricades. Necessary signage, barricades, flag persons, lights (including temporary traffic control lights), and markings for the safe movement of the public during construction shall be in accordance with the Manual on Uniform Traffic Control Devices (MUTCD), and shall be provided at no additional expense to the Government.
C.12. EARTHWORK REQUIREMENTS:
12.1. SOLID WASTE DISPOSAL AND RECYCLING
The Fort Bragg Lamont Construction and Demolition (C&D) Landfill is closed and will not be accepting any C&D Waste and Asbestos Waste.
The Municipal Solid Waste (MSW) Transfer Station at the Lamont Landfill Facility is closed and will not except MSW at the facility.
All contractors shall use a State Certified C&D Landfill or Sub Title “D” Landfill off Fort Bragg for the disposal of C&D waste, asbestos waste and MSW.
The contractor is responsible to maintain data of all waste disposed (C&D and MSW) and all materials recycled off Fort Bragg. The Department of the Army (DA) and the North Carolina Department of Environmental Quality (NC DEQ) requires monthly and annual reporting of all materials (waste and recyclables) managed by Fort Bragg. The Fort Bragg Environmental Compliance Branch, Solid Waste/Recycling Office is responsible for compiling data into monthly Directorate Reports to be consolidated into reports for the DA and the NC DEQ. A provided form from the Solid Waste/Recycling Office or a contractor form shall be filled out with the type of waste or recycled material, the weight of the waste/material (tons or pounds) and the certified facility the waste or recyclables were delivered. This information is required to be sent to the Fort Bragg Solid Waste/Recycling Office by the second Friday of each month. Email to Jeff Sloop at jeffery.w.sloop.ctr@mail.mil or fax to (910)396-4188, attn: Solid Waste Office.
The Lamont Landfill Facility Recycling Area will accept recyclables items.
1) Concrete, Brick, Block and Asphalt
- Shall be tested and free of asbestos and lead based paint to be recycled
- Shall be no larger than 2’ by 2’ pieces or equivalent
- Shall be minimal amount of dirt in load
- Shall have no rebar protruding out of the concrete
2) Trees, Limbs and Stumps
- Shall be cut to 6 feet or less in length
- If the tree has a large diameter (example 3 ft. Dia.) it shall be cut to lengths of 3 feet or less
- Shall be minimal amount of dirt in load or in stump roots
- Will except ground wood chips
- No trash in load
3) Pallets
- Serviceable and Non-serviceable Pallets
4) Scrap Steel
- No items requiring demilitarized accepted
- No items with liquids in them
5) Scrap Aluminum
- No items requiring demilitarized accepted
- No items with liquids in them
6) Cardboard to be recycled
- A 40 yard Dumpster is available for cardboard
- Also cardboard can be taken to the Fort Bragg Recycling Center at BLDG 3-1240, Butner and Reilly Road
- Shall be clean of trash, plastics, Styrofoam, wood, metal, etc.
Contact your COR or the Solid Waste/Recycling Program at 977-2502, 396-3372 or 432-6412 for additional guidance.
State Law and Fort Bragg regulations requires covering of loads of waste or recyclables to prevent litter.
All waste or recyclable material loads are subject to be inspected of their contents while being present on Fort Bragg.
Note: All Recyclable Materials generated from a construction or demolition job is property of the government unless the contract specifies that the contract can obtain the materials. Items such as HVAC Units (Freon Removed), Air Handlers, Piping, Metals Beams, Motors, Valves, Copper Wire, etc. These types of items shall be transported to the DPW Recycling Center (Butner and Reilly Road) or the Recycling Area at the Lamont Landfill Facility.
12.2. BORROW PERMITS. An Authorization for Use of Borrow Pits permit is required before gaining access to Fort Bragg borrow pits. A copy of the request for authorization to use the borrow pits form will be provided at the Pre-Performance conference. Contractor shall submit request form to DPW Operations and Maintenance Division, Exterior Branch, Building O-3454, Lamont Road, 396-6873/0747 for approval.
Permits are only issued for 60-day increments. Contractor shall fully comply with all the conditions stated on the permit and borrow materials may only be used for the contract identified on the permit. The borrow pit location is shown on the contract drawings.
C.13. GOVERNMENT FURNISHED EQUIPMENT / MATERIALS.
13.1. The Government reserves the right to provide Government-furnished equipment / materials (GFE / GFM) that is on-hand if it can be used by the Contractor to complete a TO. The Government will Hand receipt the GFE/GFM to the Contractor. The Contractor, using its own resources, shall transport all GFE /GFM described on the TO at no additional cost to the Government. The GFE / GFM shall be transported from the Government storage area, or other area specified in the SOW, to the work site indicated by the TO. Contractor shall ensure that COR is kept apprised of any and all movement of
GFE/GFM
13.2. The Contractor assumes the risk and responsibility for the loss or damage to GFE / GFM once the Contractor receives possession of the GFE / GFM.
13.3. The Contractor shall follow the instructions of the KO regarding the disposition of all GFE / GFM not consumed in performance of a TO.
C.14. GOVERNMENT EQUIPMENT ON THE SITE.
14.1. All government equipment and material shall remain the property of the Government unless specifically noted otherwise. Contractor shall relocate all property that the Government retains title to as specified in the TO or per instructions of the KO.
14.2. Contractor is required to protect equipment that is to remain in place within the area of TO operations and protect it against damage and loss, and to store equipment that is removed in performance of work where directed. Equipment temporarily removed shall be protected and returned to its original position prior to completing work at no additional expense to the Government. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the Contractor.
C.15. DISPOSAL OF WASTE:
15.1. Loose debris on trucks leaving the site shall be loaded in a manner that shall prevent dropping of materials on streets and conform to local ordinances / laws. Fasten suitable cover, such as a tarpaulin, over the load before entering surrounding streets. The Contractor shall be responsible for cleaning up any materials that fall from trucks and held liable for any resulting damages. The Contractor is solely responsible for spillage from its vehicles, and such spillage shall be cleaned up immediately. For the duration of this contract and on a daily basis, the Contractor shall remove from all roads and / or streets asphalt, mud, soil, rocks, trash, and debris that result from its construction operations. All roads and / or streets affected shall be cleaned before close of business on the particular day affected.
15.2. Contractor shall submit, upon request, all trip tickets from the off-post landfill facility to show all debris is being land-filled in accordance with all Federal requirements and in an approved location.
15.3. The KO will determine if materials removed from and not reused in the project are salvageable or unsalvageable. Salvageable materials shall be disposed of as directed by the KO When material is designated as unsalvageable, the material from that point shall become the property of the Contractor.
C.16. SALVAGE:
16.1. Title to all materials and equipment to be demolished, except items indicated in the TO as Government salvage, shall be vested to the Contractor upon removal from the post. The Government will not be responsible for the condition, loss or damage to such property after NTP. All unsalvageable material will be disposed of legally off-post.
16.2. Projects which include Government salvage will have such items clearly designated in the TO.
Government salvage materials shall be cleaned, sorted, identified, bundled, boxed, etc. and delivered to the collection location identified in the individual TO.
C.17. APPLICABLE CODES AND REGULATIONS: The latest edition of the following Codes shall be used for all design and construction under this contract. If there is a conflict between these codes or regulations and these contract specifications, the most stringent requirements shall apply at all times. The Contractor shall have a copy of each of these documents available for use during the term of this contract.
Uniform Building Code Uniform Mechanical Code Uniform Plumbing Code Standard Building Code National Electrical Code (NEC) ANSI C-2, national Electrical Safety Code (QIESC) Life Safety Code, NFPA 101 National Fire Protection Association (NFPA) MIL Handbook 1190 Southern Building Codes
C.18. CONSTRUCTION SITES:
18.1. GENERAL. TO construction sites must be operated and maintained according to these specifications and are subject to inspection and enforcement according to all federal, state and local codes / regulations.
18.2. AVAILABILITY AND USE OF UTILITY SERVICES. The Government will make available all reasonably required utilities to the Contractor from existing outlets and supplies, as specified in the TOs.
The Contractor shall fully comply with all current requirements, rules and regulations in regards to connecting with existing utility systems. Furthermore, the Contractor shall carefully conserve all utilities furnished. The Contractor shall be responsible for all connection and disconnection costs and pay for all utilities used by their facilities, regardless if they are reimbursable or non-reimbursable customers.
18.2.1. TEMPORARY UTILITY CONNECTIONS. The Contractor shall submit a DPW Demand Maintenance Order (DMO) and notify the COR, in writing, before contacting any utility service provider.
Demand Maintenance Orders are obtained by calling (910) 396-0321. Once the DMO has been approved, the Contractor will be responsible for contacting the utility provider and making arrangements for connections, disconnections and billing. The Contractor shall be responsible to provide and maintain all necessary temporary service lines and connections within 5 feet of their temporary facilities. Meters required to measure the amount of each utility being used for the purpose of determining charges will be provided and installed by the parties stated below.
18.2.2. TEMPORARY ELECTRICAL CONNECTIONS. For temporary electrical connections, the Government or its electrical utility partner, Sandhill’s Utility Services, LLC (SUS) will provide the meter (meter base provided by Contractor) and will make the final hot connection after inspection and approval of the Contractor's temporary wiring installation. The Contractor shall not make the final electrical connection.
Sandhill’s Utility Services, LLC Building 2-6503 Butner Road
Fort Bragg, North Carolina 28310
(910) 497-7399 Fax: (910) 497-5969
18.2.3. TEMPORARY WATER/SEWER CONNECTIONS. For temporary water and sewer connections, the Contractor shall apply for a connection permit through Old North Utility Services, Inc. (ONUS). ONUS will install a backflow prevention device and meter on all connections to the potable water system. If the Contractor requests the use of a fire hydrant and receives approval from the COR, a backflow prevention device and meter shall be installed by ONUS prior to use.
Old North Utility Services, Inc.
110 North Fourth Street
Spring Lake, North Carolina 28390
(910) 495-1311 Fax: (910) 495-131
18.2.3.1. TOILET FACILITIES: Contractor's personnel shall be permitted to use existing toilet facilities unless otherwise specified in the project SOW, on the premises subject to approval of the KO. Facilities must be kept cleaned by Contractor. It shall be the Contractor’s responsibility to request use of on-site facilities. No request infers “no necessity of use.”
18.2.4. TEMPORARY NATURAL GAS CONNECTIONS. For temporary gas connections, the Government or its natural gas utility partner Piedmont Natural Gas (PNG) will provide the meter and will make the final hot connection after inspection and approval of the Contractor's temporary installation. The Contractor shall not make the final gas connections. DPW will provide notification to PNG of any emergencies or problems encountered by TO work under this MATOC. PNG will be responsible for all routine and emergency maintenance and operations responsibilities associated with the gas mains on Fort Bragg.
Piedmont Natural Gas NC Military Base Construction
1069 Wilkes Road
Fayetteville, North Carolina 28306
(910) 321-2925 Fax: (910)
18.2.5. USE OF PERMANENT BUILDING UTILITY CONNECTIONS. Utilities consumed by the Contractor from permanent building utility connections shall also be metered and paid for by the Contractor. When the permanent system is activated, the initial meter reading shall be recorded and reported as specified below. On building renovation projects the initial meter reading shall be recorded when the Contractor is given possession of the building to perform the work. The Contractor shall pay for utilities consumed through the permanent building connection until the work has been completed or the government has occupied the facility, whichever occurs first.
18.2.6. PAYMENT FOR UTILITY SERVICES. Unless otherwise provided in a TO award, the amount of each utility service consumed shall be charged to and paid for by the Contractor at the prevailing rates. The rates listed below are current as of October 2014. Rates are subject to change every month without notice and are based on cost to Federal Government. For additional rate information contact: DPW Utilities Branch, 396-6369.
Utilities Charge Rates Electricity $0.07495 per KW hour Natural Gas $0.63249 per Therm.
Sewer $0.8565 per 1,000 gallons.
Water $1.6747 per 1,000 gallons
18.2.7. INITIAL METER READINGS. Upon installation of the meter, the initial reading shall be recorded (in the presence of the COR) and forwarded to the point of contact for utility service with a copy to the
COR.
18.2.8. FINAL METER READINGS. Before completion of the work and final acceptance of the work by the Government, the Contractor shall notify the KO and the non-government utility provider (SUS or ONUS) in writing 10 working days before termination is desired. The Government or the utility provider will take a final meter reading. The provider will disconnect the utility service. The Contractor shall then remove all the temporary distribution lines, meters, meter bases, and associated equipment. The Contractor shall pay all outstanding utility bills before final acceptance of the work by the Government.
18.3. GRASSED AREAS. Grass and weed growth in excavated materials that are stockpiled on site shall be controlled and / or cut weekly by the Contractor.Weeds and grass within the construction site shall also be controlled and / or cut weekly. Areas disturbed by construction and / or those areas required by the plans to be “re-seeded” shall be re-established by hydroseeding and seed or sod.
18.4. PARKING AREAS. Contractor or Contractor’s employees, including subcontractors, shall not park any personally owned vehicle (POV) or company and / or delivery vehicle on grassy areas near or in the construction site without prior approval from the COR. When allowed, parking on grassy areas will only be for short-term delivery purposes (to include heavy tools, equipment, construction materials, etc.). Use designated hard surfaces or existing parking lots near or within the project site for parking of POVs or company and / or delivery vehicles. Tire and track impressions (ruts) created on wet or soft soil by vehicles and / or equipment used in the Contractor’s operations shall not be left for more than one day after removal of such vehicle or equipment that caused the rutting. The Contractor shall restore the affected area(s) of the site to its original condition within that one-day period.
18.5. SITE CLEANUP. During construction, the Contractor shall maintain all areas in a neat and orderly manner. Contractor shall keep the construction site cleaned daily of all construction trash, trash generated by employees, debris, and / or demolished building materials. If the work areas are not kept neat and orderly, the Contractor must return to the area to correct the unacceptable condition. During the laying of asphalt roads, streets and / or parking surfaces, areas soiled by residual asphalt shall be cleaned daily. The Contractor shall treat with lime entrances and exits to asphalt work sites at its own expense.
18.7. HAUL ROUTES. The Contractor is required to use the haul routes shown on the TO drawings for transportation of borrow materials, construction debris, or demolition materials unless otherwise permitted in writing by the COR. When haul routes are not designated, the Contractor must obtain approval from the COR for the routes Contractor intends to use. The axle load of earth-hauling equipment operating on paved streets shall not exceed 12,000 pounds. All construction debris/trash that leaves the project site will be covered from the time that it leaves the construction site. Any mud, soil or other material left along the haul route will be cleaned up by the Contractor immediately upon discovery or notification of such an occurrence at the Contractor’s own expense.
18.8. PROJECT SIGN. When required in the TO, the Contractor shall furnish and install a project sign at the location selected by the COR. The project sign shall be painted on ½ inch thick exterior grade plywood.
The required graphic format, sign layout, and color will be provided at the Pre-Performance Conference, or can be viewed in the Fort Bragg IDG.
C.19. ENVIRONMENTAL PROTECTION:
19.1. PROTECTION OF LAND RESOURCES. Prior to the start of any construction, the Contractor shall identify all land resources to be preserved within the Contractor's work area. The Contractor shall not remove, cut, deface, injure, or destroy land resources, including trees, shrubs, vines, grasses, topsoil, and land forms, without special permission from the KO. No ropes, cables, or guides shall be fastened or attached to any trees for anchorage unless specifically authorized. Where such special emergency use is permitted, the Contractor shall provide effective protection for land and vegetation resources at all times.
19.1.1. FOREST RESOURCES. Merchantable timber and pine straw shall neither be cut nor removed from the construction site until it has been assessed by the Savannah District Timber Harvest Office in conjunction with DPW Natural Resources Branch (396-2510/2028). The Savannah District Timber Harvest Office will be given adequate time to arrange for the sale and removal of timber and pine straw. In the event that the Savannah District and Natural Resources Branch determine the amount or quality of timber or pine straw is not merchantable, they will inform the KO. The KO will authorize the Contractor to remove forest resources which are in the footprint of construction.
19.1.2. WORK AREA LIMITS. Prior to any construction, the Contractor shall mark the areas that are not required to accomplish all work to be performed under TOs under this contract. Isolated areas within the general work area which are to be saved and protected shall also be marked or fenced. Monuments, installed monitoring wells, and markers shall be protected before construction operations begin. Where construction operations are to be conducted during darkness (with prior approval from the COR), the markers shall still remain visible. The Contractor shall convey to its personnel the purpose of marking and/or protection of all necessary objects. Damage to protected areas/objects shall be repaired immediately by the Contractor at no additional cost to the Government.
19.1.3. INSTALLATION OR REMOVAL OF UNDERGROUND STORAGE TANKS, OIL/WATER
SEPARATORS, AND ABOVEGROUND STORAGE TANKS. Prior to any installation/removal of underground storage tanks (USTs), the Contractor will contact the DPW Environmental Compliance Branch, UST Program Manager (396-7432) and provide all UST installation/removal information. The DPW UST Program Manager will apply for all UST installation/removal and operating permits on behalf of the Contractor. Strict sampling requirements exist for removals of these structures.
19.1.4. PROTECTION OF LANDSCAPE. Trees, shrubs, vines, grasses, land forms, and other landscape features indicated and defined on the drawings to be preserved shall be clearly identified by marking provided by the COR fencing, wrapping, or any other approved techniques.
19.1.5. REDUCTION OF SOIL EROSION. Earthwork brought to final grade shall be finished as indicated and specified in the TO. Side slopes and back slopes shall be protected as soon as practicable upon completion of rough grading. All earthwork shall be planned and conducted to minimize the duration of exposure of unprotected soils. Except in instances where the constructed feature obscures borrow areas, quarries, and waste material areas, these areas shall not initially be cleared in total. Clearing of such areas shall progress in reasonably sized increments as needed to use the areas as approved by the KO.
19.1.5.1. EROSION AND SEDIMENTATION CONTROL PLAN. When the total area of land disturbed is 1 acre or more in size, an Erosion and Sedimentation Control Plan shall be prepared by the Contractor. The plan will be prepared in accordance with North Carolina Administrative Code (NCAC), Title 15, Department of Natural and Economic Resources, Chapter 4, Sedimentation Control, January 1978. This plan is to be prepared, approved, and filed as part of the design prior to the start of any land-disturbing activity. When the area to be disturbed is less than 1 acre, a formal plan will not be required, however, an erosion and sedimentation control plan must still be submitted to the Water Management Branch for approval and erosion and sedimentation control measures are required regardless of the size of the disturbance. The approved erosion and sedimentation control plan or Storm Water Discharge Permit/Certificate of Plan Approval must be maintained on site, along with any other documentation required by WMB or DEQ (e.g., control measure and rain gauge inspection documentation). The Contractor is responsible for installation and maintenance of sufficient erosion control measures to retain sediment within the boundaries of the site. If the installed protective measures do not work, additional measures must be taken. Surfaces shall be non-erosive and stable within 15 working days or 90 calendar days after completion of the activity, whichever period is shorter. The Contractor shall construct and maintain the erosion and sedimentation control measures identified in the TO and any further measures necessary to comply with NCAC Title 15A, Chapter 4. The Contractor shall maintain all constructed erosion and sedimentation control measures until they receive written removal approval by DPW’s Water Management Branch (WMB). To schedule an inspection for removal, contact the WMB at 907-5581.
19.1.5.2. CONTROL OF RUNOFF. Runoff from the construction site shall be controlled by the contractor with the construction of diversion ditches, benches, and silt basins; by checking dams and berms to reduce the velocity and to divert runoff to protected drainage courses and by any measures required by area wide plans approved under the Clean Water Act, paragraph 208.
19.1.5.3. SEDIMENT BASINS. Sediment from construction areas shall be trapped in temporary or permanent sediment basins in accordance with basin plans shown on the drawings. The basins shall accommodate the runoff of a local 5-year design storm. They shall be constructed as approved by the KO to prevent sedimentation of downstream or downslope areas.
19.2. DISPOSAL OF CHEMICAL WASTES. The Contractor is responsible for the proper use, storage, and disposal of chemical material and waste in accordance with Fort Bragg Regulation 200-2. The DPW has established the following requirements in order for the post to remain in compliance with hazardous waste requirements as established by both State of North Carolina and Federal environmental laws.
19.2.1. COMPATIBLE CONTAINERS. Chemical waste shall be contained in and stored in aboveground compatible containers. Hazardous wastes shall not be stored underground. Any release or spill to the environment will be immediately reported to the Fort Bragg Fire Department at telephone 396-7377/3015/1504 and to the DPW Environmental Compliance Branch at 396-2295.
19.2.2. CHEMICAL ANALYSIS. The Contractor is responsible for obtaining chemical analyses of all chemical wastes. All chemical waste shall be disposed of in accordance with Fort Bragg's Waste Analysis Plan. Sampling of suspected hazardous waste is required to determine the hazardous waste characterization of the material. The Contractor is required to notify the COR 1 day before the samples are taken. Samples shall be delivered by the COR to the DPW Environmental Compliance Branch for transmittal to an independent analytical laboratory. The laboratory shall be listed in the Environmental Protection Plan approved by the DPW Environmental Compliance Branch.
19.2.3. NONHAZARDOUS WASTE. Waste that has been certified as non-hazardous waste may be removed off the project site by the Contractor. These wastes shall be disposed of in accordance with all applicable State of North Carolina requirements and U.S. Army Center for Health Promotion and Preventive Medicine (CHPPM) guidance. The Contractor shall address the disposal method and location of the disposal site for each chemical waste in the Environmental Protection Plan for the project.
19.2.4. HAZARDOUS WASTE. The Contractor may not normally remove hazardous waste from Fort Bragg. Removal shall be performed by a licensed hazardous waste firm. The hazardous waste Contractor shall prepare the hazardous waste manifest form for signature by the Environmental Compliance Branch before each shipment of hazardous waste. Each container of hazardous waste shall be immediately labeled with a hazardous waste label and marked with the current date once any hazardous waste is put in the container. The Contractor shall keep the containers closed and inspect them weekly for signs of rust or deterioration. Inspection results shall be documented. Additionally, the U.S. Department of Transportation Shipping Name shall be marked on each container before it is removed from Fort Bragg. The Contractor shall ensure all of its employees who handle hazardous waste are trained in the management requirements for hazardous waste. Two hours of on-the-job training by the Environmental/Natural Resources Division will be scheduled for the first Wednesday of each month. All Contractor employees physically handling or managing waste media shall receive this training. Refer to Fort Bragg Regulation 200-2.
C.20. SEASONAL HVAC REQUIREMENTS: Unless otherwise allowed by specific TO provisions, air conditioning systems are required to be operational from 15 May through 15 September and heating systems are required to be operational from 15 October through 1 May. Contractor shall provide temporary heating or cooling during these periods if the air conditioning or heating systems are shut down to perform work and weather conditions would have required system operation. Submit shop drawings for approval of proposed method for providing temporary heating or cooling.
C.21. TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER: This provision specifies the procedure for the determination of time extensions for unusually severe weather. The listing below defines the adverse weather days that are anticipated monthly. The listing is based upon data from the National Oceanographic & Atmospheric Administration (NOAA) or similar data.
MONTHLY ANTICIPATED ADVERSE WEATHER CALENDAR DAYS
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
13 12 12 9 10 9 10 10 7 8 10 12
21.1. The above schedule of anticipated adverse weather will constitute the baseline for monthly (or portion thereof) weather time evaluations. Upon acknowledgment of the NTP and continuing throughout the TO on a monthly basis, actual adverse weather days will be recorded on a calendar-day basis (include weekends and holidays) and compared to the monthly anticipated adverse weather in the schedule above. The term “actual adverse weather days” shall include days impacted by actual adverse weather.
21.2. The number of actual adverse weather days shall be calculated chronologically from the first to the last day in each month. Once the number of actual adverse weather days anticipated in the schedule above have occurred, the COR, upon the Contractor's written request, will examine any subsequently occurring adverse weather days to determine whether the Contractor is entitled to a time extension and will provide a recommendation to the KO for approval.