BARRACKS_SPECS_VOL2_16May2016.pdf
PDF 2 MB Posted
- Attached to
- AIT Barracks- Phase III, Ft. Lee, Virginia Federal contract opportunity
- Solicitation number
- W91236-16-R-0010
About this file
BARRCKS_SPECS_VOL2_16May2016
View the file
Other files for this federal contract opportunity
Show all 50
AIT Barracks- Phase III, Ft. Lee, Virginia has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
28-APR
AIT Complex Phase III
-BARRACKS
VOLUME 2 OF 3
E4TSERCN
Text Box
Ft. Lee AIT Barracks Phase III FY15 041449FTLEE
PROJECT TABLE OF CONTENTS
VOLUME 1 OF 3
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 30 00.10 50 PROJECT WORK REQUIREMENTS AND RESTRICTIONS
01 30 00.20 50 ADMINISTRATIVE REQUIREMENTS
01 31 19.00 50 PROJECT MEETINGS
01 32 01.00 50 PROJECT S2CHEDULE
01 33 00.00 50 SUBMITTAL PROCEDURES
01 33 29 SUSTAINABILITY REPORTING
01 35 26.00 50 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 02.00 50 QUALITY CONTROL SYSTEM (QCS)
01 45 04.00 50 CONTRACTOR QUALITY CONTROL
01 50 02.00 50 TEMPORARY CONSTRUCTION FACILITIES
01 57 19.00 20 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 62 35.00 50 RECYCLED / RECOVERED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 02.00 50 CLOSEOUT SUBMITTALS
01 78 23.00 50 OPERATION AND MAINTENANCE DATA
01 91 00.80 COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED MATERIAL
02 65 00 UNDERGROUND STORAGE TANK REMOVAL
02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS MATERIALS
02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES
02 82 16.00 20 ENGINEERING CONTROL OF ASBESTOS CONTAINING MATERIALS
02 82 33.13 20 REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD
02 83 13.00 20 LEAD IN CONSTRUCTION
02 84 16 HANDLING OF LIGHTING BALLASTS AND LAMPS CONTAINING PCBs
AND MERCURY
VOLUME 2 OF 3
DIVISION 03 - CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 30 00.00 10 CAST-IN-PLACE CONCRETE
03 35 00.00 10 CONCRETE FINISHING
03 39 00.00 10 CONCRETE CURING
DIVISION 04 - MASONRY
04 20 00 MASONRY
DIVISION 05 - METALS
05 05 23 WELDING, STRUCTURAL
05 12 00 STRUCTURAL STEEL
05 21 19 OPEN WEB STEEL JOIST FRAMING
05 30 00 STEEL DECKS
05 40 00 COLD-FORMED METAL FRAMING
05 50 13 MISCELLANEOUS METAL FABRICATIONS
PROJECT TABLE OF CONTENTS Page 1
05 51 00 METAL STAIRS
05 51 33 METAL LADDERS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 20 00 FINISH CARPENTRY
06 41 16.00 10 LAMINATE CLAD ARCHITECTURAL CASEWORK
06 61 16 SOLID POLYMER (SOLID SURFACING) FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 05 23 PRESSURE TESTING AN AIR BARRIER SYSTEM FOR AIR TIGHTNESS
07 13 53 ELASTOMERIC SHEET WATERPROOFING
07 17 00 BENTONITE WATERPROOFING
07 21 16 MINERAL FIBER BLANKET INSULATION
07 22 00 ROOF AND DECK INSULATION
07 26 30 SPRAY POLYURETHANE FOAM INSULATING AIR BARRIER SYSTEM
(ABR)
07 27 10.00 10 BUILDING AIR BARRIER SYSTEM
07 42 63 FABRICATED WALL PANEL ASSEMBLIES
07 52 00 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 FLASHING AND SHEET METAL
07 61 14.00 20 STEEL STANDING SEAM ROOFING
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 STEEL DOORS AND FRAMES
08 11 16 ALUMINUM DOORS AND FRAMES
08 14 00 WOOD DOORS
08 33 13 METAL ROLLING COUNTER DOORS
08 33 23 OVERHEAD COILING DOORS
08 34 59 VAULT DOORS AND DAY GATES
08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
08 44 00 CURTAIN WALL AND GLAZED ASSEMBLIES
08 51 13 ALUMINUM WINDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL AND DOOR LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 13 CERAMIC TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 65 36 STATIC-CONTROL RESILIENT FLOORING
09 65 66 RESILIENT ATHLETIC FLOORING
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 10 00 VISUAL COMMUNICATIONS SPECIALTIES
10 14 00.20 INTERIOR SIGNAGE
10 14 01 EXTERIOR SIGNAGE
10 21 13 TOILET COMPARTMENTS
10 22 39 FOLDING PANEL PARTITIONS
PROJECT TABLE OF CONTENTS Page 2
10 26 13 WALL AND CORNER GUARDS
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
DIVISION 12 - FURNISHINGS
12 21 00 WINDOW BLINDS
12 31 00 MANUFACTURED METAL CASEWORK
12 48 13.13 FOOT GRID ENTRANCE SYSTEMS
DIVISION 14 - CONVEYING EQUIPMENT
14 21 23 ELECTRIC TRACTION PASSENGER ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 12 00 STANDPIPE SYSTEMS
21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
22 11 25 FACILITY GAS PIPING
VOLUME 3 OF 3
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 48.00 40 VIBRATION, SEISMIC AND ATFP CONTROLS FOR HVAC PIPING AND
EQUIPMENT
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 23 LONWORKS DIRECT DIGITAL CONTROL FOR HVAC AND OTHER
BUILDING CONTROL SYSTEMS
23 25 00 CHEMICAL TREATMENT OF WATER FOR MECHANICAL SYSTEMS
23 52 00 HEATING BOILERS
23 64 26 CHILLED, CHILLED-HOT, AND CONDENSER WATER PIPING SYSTEMS
23 65 00 CLOSED CIRCUIT COOLERS
23 73 13.00 40 MODULAR INDOOR CENTRAL-STATION AIR-HANDLING UNITS
23 81 47 WATER-LOOP HEAT PUMP SYSTEMS
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 08 01 APPARATUS INSPECTION AND TESTING
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 23 00 SWITCHBOARDS
26 28 01.00 10 COORDINATED POWER SYSTEM PROTECTION
26 29 23 VARIABLE FREQUENCY DRIVE SYSTEMS UNDER 600 VOLTS
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
PROJECT TABLE OF CONTENTS Page 3
28 20 00.00 20 ELECTRONIC SECURITY SYSTEMS (ESS) FOR ARMS VAULT,
COMMERCIAL
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 00 00 EARTHWORK
31 05 19 GEOTEXTILE
31 11 00 CLEARING AND GRUBBING
31 31 16.19 TERMITE CONTROL BARRIER SYSTEM
31 31 16 SOIL TREATMENT FOR SUBTERRANEAN TERMITE CONTROL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 05 33 LANDSCAPE ESTABLISHMENT
32 11 16 BASE COURSE FOR RIGID PAVING
32 11 24 GRADED CRUSHED AGGREGATE BASE COURSE FOR PERVIOUS PAVEMENT
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
32 13 43 PERVIOUS CONCRETE PAVING
32 16 13 CONCRETE SIDEWALKS AND CURBS AND GUTTERS
32 17 23.00 20 PAVEMENT MARKINGS
32 92 19 SEEDING
32 92 23 SODDING
32 93 00 EXTERIOR PLANTS
DIVISION 33 - UTILITIES
33 40 00 STORM DRAINAGE UTILITIES
33 51 15 NATURAL-GAS / LIQUID PETROLEUM GAS DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
SECTION 03 11 13.00 10
STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
08/10
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
ACI 347 (2004; Errata 2008; Errata 2012) Guide to Formwork for Concrete
AMERICAN HARDBOARD ASSOCIATION (AHA)
AHA A135.4 (1995; R 2004) Basic Hardboard
APA - THE ENGINEERED WOOD ASSOCIATION (APA)
APA L870 (2010) Voluntary Product Standard, PS 1-09, Structural Plywood
ASTM INTERNATIONAL (ASTM)
ASTM C1077 (2015) Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation
ASTM C31/C31M (2012) Standard Practice for Making and Curing Concrete Test Specimens in the Field
ASTM C39/C39M (2012) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens
1.2 SYSTEM DESCRIPTION
The design, engineering, and construction of the formwork is the responsibility of the Contractor. Design formwork in accordance with methodology of ACI 347 for anticipated loads, lateral pressures, and stresses, and capable of withstanding the pressures resulting from placement and vibration of concrete. Comply with the tolerances specified in Section 03 30 00.00 10 CAST-IN-PLACE CONCRETE, paragraph CONSTRUCTION TOLERANCES. However, for surfaces with an ACI Class A surface designation, limit the allowable deflection for facing material between studs, for studs between walers and walers between bracing to 0.0025 times the span. Design the formwork as a complete system with consideration given to the effects of cementitious materials and mixture additives such as fly ash, cement type, plasticizers, accelerators, retarders, air entrainment, and others. Monitor the adequacy of formwork design and construction prior to and during concrete placement as part of the
SECTION 03 11 13.00 10 Page 1
Contractor's approved Quality Control Plan.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00.00 50 SUBMITTAL PROCEDURES:
SD-03 Product Data
Design Form Materials Form Releasing Agents
SD-04 Samples
Sample Panels;
SD-06 Test Reports
Inspection
1.4 QUALITY ASSURANCE
Sample Panels shall be of sufficient size to contain joints and shall be not less than 6 feet long and 4 feet wide. The panels shall be of typical wall thickness and constructed containing the full allocation of reinforcing steel that will be used in the structure, with the forming system that duplicates in every detail the one that will be used in construction of the structure. Use the same concrete mixture proportion and materials, the same placement techniques and equipment, and the same finishing techniques and timing that are planned for the structure.
Construction of Class A finish will not be permitted until sample panels have been approved. Protect sample panels from construction operations in a manner to protect approved finish, and are not to be removed until all Class A finish concrete has been accepted. After shop drawings have been reviewed, submit sample panels for Class A finish with applied architectural treatment; panels shall be built on the project site where directed.
1.5 DELIVERY, STORAGE, AND HANDLING
Store fiber voids above ground level in a dry location. Fiber voids shall be kept dry until installed and overlaid with concrete.
PART 2 PRODUCTS
2.1 FORM MATERIALS
Submit manufacturer's data, including literature describing form materials, accessories, and form releasing agents.
2.1.1 Forms For Class A Finish
Forms for Class A finished surfaces shall be plywood panels conforming to APA L870, Grade B-B concrete form panels, Class I or II. Other form
SECTION 03 11 13.00 10 Page 2 materials or liners may be used provided the smoothness and appearance of concrete produced will be equivalent to that produced by the plywood concrete form panels. Forms for round columns shall be the prefabricated seamless type.
2.1.2 Forms For Class B Finish
This class of finish shall apply to all surfaces except those specified to receiveClass A, Class C, Class D. Forms for Class B finished surfaces shall be plywood panels conforming to APA L870, Grade B-B concrete form panels, Class I or II. Other form materials or liners may be used provided the smoothness and appearance of concrete produced will be equivalent to that produced by the plywood concrete form panels. Forms for round columns shall be the prefabricated seamless type. Steel lining on wood sheathing will not be permitted.
2.1.3 Forms For Class C Finish
Forms for Class C finished surfaces shall be shiplap lumber; plywood conforming to APA L870, Grade B-B concrete form panels, Class I or II;
tempered concrete form hardboard conforming to AHA A135.4; other approved concrete form material; or steel, except that steel lining on wood sheathing shall not be used. Forms for round columns may have one vertical seam.
2.1.4 Forms For Class D Finish
Forms for Class D finished surfaces, except where concrete is placed against earth, shall be wood or steel or other approved concrete form material.
2.1.5 Retain-In-Place Metal Forms
Retain-in-place metal forms for concrete slabs and roofs shall be as specified in Section 05 30 00 STEEL DECKS.
2.1.6 Pan-Form Units
Pan-form units for one-way or two-way concrete joist and slab construction shall be factory-fabricated units of the approximate section indicated.
Units shall consist of steel or molded fiberglass concrete form pans.
Closure units shall be furnished as required.
2.1.7 Form Ties
Form ties shall be factory-fabricated metal ties, shall be of the removable or internal disconnecting or snap-off type, and shall be of a design that will not permit form deflection and will not spall concrete upon removal. Provide solid backing for each tie. Except where removable tie rods are used, ties shall not leave holes in the concrete surface less than 1/4 inch nor more than 1 inch deep and not more than 1 inch in diameter. Terminate the embedded portion of metal ties not less that 2 inches from any concrete surface exposed to water. Removable tie rods shall be not more than 1-1/2 inches in diameter. Plastic snap ties may be used in locations where the surface will not be exposed to view.
2.1.8 Form Releasing Agents
Form releasing agents shall be commercial formulations that will not bond
SECTION 03 11 13.00 10 Page 3 with, stain or adversely affect concrete surfaces. Agents shall not impair subsequent treatment of concrete surfaces depending upon bond or adhesion nor impede the wetting of surfaces to be cured with water or curing compounds. If special form liners are to be used, follow the recommendation of the form coating manufacturer. Submit manufacturer's recommendation on method and rate of application of form releasing agents.
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Formwork
Forms shall be constructed true to the structural design and required alignment. Forms shall be mortar tight, properly aligned and adequately supported to produce concrete surfaces meeting the surface requirements specified in Section 03 30 00.00 10 CAST-IN-PLACE CONCRETE and conforming to construction tolerance given in TABLE 1. Continuously monitor the alignment and stability of the forms during all phases to assure the finished product will meet the required surface class or classes specified. Failure of any supporting surface either due to surface texture, deflection or form collapse shall be the responsibility of the Contractor as will the replacement or correction of unsatisfactory surfaces. Where concrete surfaces are to have a Class A or Class B finish, joints in form panels shall be arranged as approved. When forms for continuous surfaces are placed in successive units, care shall be taken to fit the forms over the completed surface to obtain accurate alignment of the surface and to prevent leakage of mortar. Forms shall not be re-used if there is any evidence of defects which would impair the quality of the resulting concrete surface. All surfaces of used forms shall be cleaned of mortar and any other foreign material before reuse.
Form ties that are to be completely withdrawn shall be coated with a nonstaining bond breaker.
3.2 CHAMFERING
All exposed joints, edges and external corners shall be chamfered by molding placed in the forms unless the drawings specifically state that chamfering is to be omitted or as otherwise specified. Chamfered joints shall not be permitted where earth or rockfill is placed in contact with concrete surfaces. Chamfered joints shall be terminated twelve inches outside the limit of the earth or rockfill so that the end of the chamfers will be clearly visible.
3.3 COATING
Forms for Class A and Class B finished surfaces shall be coated with a form releasing agent before the form or reinforcement is placed in final position. The coating shall be used as recommended in the manufacturer's printed or written instructions. Forms for Class C and D finished surfaces may be wet with water in lieu of coating immediately before placing concrete, except that in cold weather with probable freezing temperatures, coating shall be mandatory. Surplus coating on form surfaces and coating on reinforcing steel and construction joints shall be removed before placing concrete.
3.4 FORM REMOVAL
Forms shall not be removed without approval. The minimal time required
SECTION 03 11 13.00 10 Page 4 for concrete to reach a strength adequate for removal of formwork without risking the safety of workers or the quality of the concrete depends on a number of factors including, but not limited to, ambient temperature, concrete lift heights, type and amount of concrete admixture, and type and amount of cementitious material in the concrete. It is the responsibility of the Contractor to consider all applicable factors and leave the forms in place until it is safe to remove them. In any case forms shall not be removed unless the minimum time, minimum ambient temperature, and minimum compressive strength requirements below are met, except as otherwise directed or specifically authorized. When conditions are such as to justify the requirement, forms will be required to remain in place for a longer period. All removal shall be accomplished in a manner which will prevent damage to the concrete and ensure the complete safety of the structure. Where forms support more than one element, the forms shall not be removed until the form removal criteria are met by all supported elements. Form removal shall be scheduled so that all necessary repairs can be performed as specified in Section 03 30 00.00 10 CAST-IN-PLACE CONCRETE. Evidence that concrete has gained sufficient strength to permit removal of forms shall be determined by tests on control cylinders. All control cylinders shall be stored in the structure or as near the structure as possible so they receive the same curing conditions and protection methods as given those portions of the structure they represent. Control cylinders shall be removed from the molds at an age of no more than 24 hours. All control cylinders shall be prepared and tested in accordance with ASTM C31/C31M and ASTM C39/C39M at the expense of the Contractor by an independent laboratory that complies with ASTM C1077 and shall be tested within 4 hours after removal from the site.
3.4.1 Formwork Not Supporting Weight of Concrete
Formwork for walls, columns, sides of beams, gravity structures, and other vertical type formwork not supporting the weight of concrete shall not be removed in less than 24 hours after concrete placement is completed.
3.4.2 Formwork Supporting Weight of Concrete
Formwork supporting weight of concrete and shoring shall not be removed until structural members have acquired sufficient strength to safely support their own weight and any construction or other superimposed loads to which the supported concrete may be subjected. As a minimum, forms shall be left in place until control concrete test cylinders indicate evidence the concrete has attained at least 75 percent of the compressive strength required for the structure in accordance with the quality and location requirements.
3.4.3 Tunnel Forms
Tunnel lining bulkhead forms shall not be removed in less than 12 hours and tunnel lining forms in not less than 16 hours.
3.5 INSPECTION
Forms and embedded items shall be inspected in sufficient time prior to each concrete placement in order to certify to the Contracting Officer that they are ready to receive concrete. The results of each inspection shall be reported in writing. Submit field inspection reports for concrete forms and embedded items.
SECTION 03 11 13.00 10 Page 5
TABLE 1
TOLERANCES FOR FORMED SURFACES
1. Variations from the plumb:
a. In the lines and surfaces of columns, piers, walls and in arises
1/4 inch in any 10 feet of length Maximum for entire length -- 1 inch
b. For exposed corner columns, control-joint grooves, and other conspicuous lines
1/4 inch in any 20 feet of length Maximum for entire length -- 1/2 inch
2. Variation from the level or from the grades indicated on the drawings:
a. In slab soffits, ceilings beam soffits, and in arises,measured before removal of supporting shores
1/4 inch in any 10 feet of length 3/8 inch in any bay or in any 20 feet of length Maximum for entire length -- 3/4 inch
b. In exposed lintels, sills, parapets, horizontal grooves, and other conspicuous lines
1/4 inch in any bay or in any 20 feet of length Maximum for entire length -- 1/2 inch
3. Variation of the linear building lines from established position in plan
1/2 inch in any 10 feet 1 inch maximum
4. Variation of distance between walls, columns, partitions
1/4 inch per 10 feet of distance, but not more than 1/2 inch in any one bay, and not more than 1 inch total variation
5. Variation in the sizes and locations of sleeves, floor openings, and wall opening
Minus 1/4 inch, Plus 1/2 inch
6. Variation in cross-sectional dimensions of columns and beams and in the thickness of slabs and walls
Minus 1/4 inch, Plus 1/2 inch
7. Footings:
a. Variation of dimensions in plan Minus 1/2 inch, plus 2 inches when formed or plus 3 inches when placed against unformed excavation
b. Misplacement of eccentricity 2 percent of the footing width in the direction of misplacement but not more than 2 inches
SECTION 03 11 13.00 10 Page 6
TABLE 1
TOLERANCES FOR FORMED SURFACES
c. Reduction in thickness Minus 5 percent of the specified thickness
8. Variation in steps:
a. In a flight of stairs Riser -- 1/8 inch Tread -- 1/4 inch
b. In consecutive steps Riser -- 1/16 inch Tread -- 1/8 inch
-- End of Section --
SECTION 03 11 13.00 10 Page 7
SECTION 03 15 00.00 10
CONCRETE ACCESSORIES
08/10
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN HARDBOARD ASSOCIATION (AHA)
AHA A135.4 (1995; R 2004) Basic Hardboard
ASTM INTERNATIONAL (ASTM)
ASTM C 919 (2008) Use of Sealants in Acoustical Applications
ASTM D 1751 (2004; R 2008) Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)
ASTM D 1752 (2004a; R 2008) Standard Specification for Preformed Sponge Rubber Cork and Recycled PVC Expansion
ASTM D 2628 (1991; R 2005) Standard Specification for Preformed Polychloroprene Elastomeric Joint Seals for Concrete Pavements
ASTM D 2835 (1989; R 2007) Lubricant for Installation of Preformed Compression Seals in Concrete Pavements
ASTM D 5249 (2010) Backer Material for Use with Cold-and Hot-Applied Joint Sealants in Portland-Cement Concrete and Asphalt Joints
ASTM D 7116 (2005) Standard Specification for Joint Sealants, Hot Applied, Jet Fuel Resistant Types, for Portland Cement Concrete Pavement
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00.00 50 SUBMITTAL
PROCEDURES:
SECTION 03 15 00.00 10 Page 1
SD-02 Shop Drawings
SD-03 Product Data
Preformed Expansion Joint Filler Sealant
SD-04 Samples
Lubricant for Preformed Compression Seals Field-Molded Type
SD-07 Certificates
Preformed Expansion Joint Filler Sealant
1.3 DELIVERY, STORAGE, AND HANDLING
Protect material delivered and placed in storage off the ground from moisture, dirt, and other contaminants. Deliver sealants in the manufacturer's original unopened containers. Remove sealants from the site whose shelf life has expired.
PART 2 PRODUCTS
2.1 CONTRACTION JOINT STRIPS
Contraction joint strips shall be 1/8 inch thick tempered hardboard conforming to AHA A135.4, Class 1. In lieu of hardboard strips, rigid polyvinylchloride (PVC) or high impact polystyrene (HIPS) insert strips specifically designed to induce controlled cracking in slabs on grade may be used. Such insert strips shall have removable top section.
2.2 PREFORMED EXPANSION JOINT FILLER
Expansion joint filler shall be preformed material conforming to ASTM D 1751or ASTM D 1752. Unless otherwise indicated, filler material shall be 3/8 inch thick and of a width applicable for the joint formed.
Backer material, when required, shall conform to ASTM D 5249.
2.3 SEALANT
Joint sealant shall conform to the following:
2.3.1 Preformed Polychloroprene Elastomeric Type
ASTM D 2628.
2.3.2 Lubricant for Preformed Compression Seals
ASTM D 2835. Submit a piece not less than 9 ft of 1 inch nominal width or wider seal or a piece not less than 12 ft of compression seal less than 1
SECTION 03 15 00.00 10 Page 2 inch nominal width. Provide one quart of lubricant.
2.3.3 Field-Molded Type
ASTM D 7116. Sealant shall be Type M, Grade P or NS, Class 25, Use NT for horizontal joints. Type M, Grade NS, Class 25, Use NT for vertical joints.
Bond breaker material shall be polyethylene tape, coated paper, metal foil or similar type materials. The back-up material shall be compressible, non-shrink, nonreactive with sealant, and non-absorptive material type such as extruded butyl or polychloroprene rubber. Submit One gallon of field-molded sealant and one quart of primer (when primer is recommended by the sealant manufacturer) identified to indicate manufacturer, type of material, quantity, and shipment or lot represented.
PART 3 EXECUTION
3.1 INSTALLATION
Joint locations and details, including materials and methods of installation of joint fillers, shall be as specified and indicated. In no case shall any fixed metal be continuous through an expansion or contraction joint.
3.1.1 Contraction Joints
Contraction joints may be constructed by inserting tempered hardboard strips or rigid PVC or HIPS insert strips into the plastic concrete using a steel parting bar, when necessary, or by cutting the concrete with a saw after concrete has set. Make joints 1/8 inch to 3/16 inch wide and extend into the slab one-fourth the slab thickness, minimum, but not less than 1 inch.
3.1.1.1 Joint Strips
Provide strips of the required dimensions and as long as practicable.
After the first floating, groove the concrete with a tool at the joint locations. Insert the strips in the groove and depress them until the top edge of the vertical surface is flush with the surface of the slab. Float and finish the slab as specified. Working of the concrete adjacent to the joint shall be the minimum necessary to fill voids and consolidate the concrete. Where indicated, saw out the top portion of the strip after the curing period to form a recess for sealer. Discard the removable section of PVC or HIPS strips and leave the insert in place. Maintain true alignment of the strips during insertion.
3.1.1.2 Sawed Joints
Saw joints early enough to prevent uncontrolled cracking in the slab, but late enough that this can be accomplished without appreciable spalling.
Cutting shall be started as soon as the concrete has hardened sufficiently to prevent raveling of the edges of the saw cut. Cutting shall be completed before shrinkage stresses become sufficient to produce cracking.
Use concrete sawing machines that are adequate in number and power, and with sufficient replacement blades to complete the sawing at the required rate. Cut joints to true alignment and in sequence of concrete placement. Remove sludge and cutting debris. Form reservoir for joint sealant.
SECTION 03 15 00.00 10 Page 3
3.1.2 Expansion Joints
Use preformed expansion joint filler in expansion and isolation joints in slabs around columns and between slabs on grade and vertical surfaces where indicated. Extend the filler to the full slab depth, unless otherwise indicated. neatly finish the edges of the joint with an edging tool of 1/8 inch radius, except where a resilient floor surface will be applied. Where the joint is to receive a sealant, the filler strips shall be installed at the proper level below the finished floor with a slightly tapered, dressed and oiled wood strip temporarily secured to the top to form a recess to the size shown on the drawings. Remove the wood strip after the concrete has set. Contractor may opt to use a removable expansion filler cap designed and fabricated for this purpose in lieu of the wood strip. Thoroughly clean the groove of laitance, curing compound, foreign materials, protrusions of hardened concrete, and any dust. If blowing out the groove use oil-free compressed air.
3.1.3 Joint Sealant
Fill sawed contraction joints and expansion joints in slabs with joint sealant, unless otherwise shown. Joint surfaces shall be clean, dry, and free of oil or other foreign material which would adversely affect the bond between sealant and concrete. Apply joint sealant as recommended by the manufacturer of the sealant.
3.1.3.1 Joints With Preformed Compression Seals
Install compression seals with equipment capable of installing joint seals to the prescribed depth without cutting, nicking, twisting, or otherwise distorting or damaging the seal or concrete and with no more than 5 percent stretching of the seal. Cover the sides of the joint and, if necessary, the sides of the compression seal with a coating of lubricant.
Coat butt joints with liberal applications of lubricant.
3.1.3.2 Joints With Field-Molded Sealant
Do not seal joints when the sealant material, ambient air, or concrete temperature is less than 40 degrees F. When the sealants are meant to reduce the sound transmission characteristics of interior walls, ceilings, and floors the guidance provided in ASTM C 919 shall be followed. Coat joints requiring a bond breaker with curing compound or with bituminous paint. Install bond breaker and back-up material where required. Joints shall be primed and filled flush with joint sealant in accordance with the manufacturer's recommendations.
3.2 CONSTRUCTION JOINTS
Treat construction joints coinciding with expansion and contraction joints as expansion or contraction joints as applicable. Construction joints shall be as detailed on the drawings and if not detailed as specified here and in 03 30 00.00 10 CAST-IN-PLACE CONCRETE.
SECTION 03 15 00.00 10 Page 4
SECTION 03 20 00.00 10
CONCRETE REINFORCING
08/10
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
ACI 318 (2014; Errata 1-2 2014; Errata 3-4 2015) Building Code Requirements for Structural Concrete and Commentary
ACI SP-66 (2004) ACI Detailing Manual
AMERICAN WELDING SOCIETY (AWS)
AWS D1.4/D1.4M (2011) Structural Welding Code - Reinforcing Steel
ASTM INTERNATIONAL (ASTM)
ASTM A1035/A1035M (2011) Standard Specification for Deformed and Plain, Low-carbon, Chromium, Steel Bars for Concrete Reinforcement
ASTM A184/A184M (2006; E2011) Standard Specification for Fabricated Deformed Steel Bar Mats for Concrete Reinforcement
ASTM A53/A53M (2012) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
ASTM A615/A615M (2015a; E 2015) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM A675/A675M (2003; R 2009) Standard Specification for Steel Bars, Carbon, Hot-Wrought, Special Quality, Mechanical Properties
ASTM A706/A706M (2009b) Standard Specification for Low-Alloy Steel Deformed and Plain Bars for Concrete Reinforcement
ASTM A767/A767M (2009) Standard Specification for Zinc-Coated (Galvanized) Steel Bars for Concrete Reinforcement
ASTM A775/A775M (2007b) Standard Specification for
SECTION 03 20 00.00 10 Page 1
Epoxy-Coated Steel Reinforcing Bars
ASTM A82/A82M (2007) Standard Specification for Steel Wire, Plain, for Concrete Reinforcement
ASTM A934/A934M (2007) Standard Specification for Epoxy-Coated Prefabricated Steel Reinforcing Bars
CONCRETE REINFORCING STEEL INSTITUTE (CRSI)
CRSI 10MSP (2009; 28th Ed) Manual of Standard Practice
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00.00 50 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Reinforcement; G
SD-03 Product Data
Welding
SD-07 Certificates
Reinforcing Steel Qualification of Steel Bar Butt-Splicers
1.3 QUALITY ASSURANCE
1.3.1 Welding Qualifications
Welders shall be qualified in accordance with AWS D1.4/D1.4M.
Qualification test shall be performed at the worksite and notify the Contracting Officer 24 hours prior to conducting tests. Special welding procedures and welders qualified by others may be accepted as permitted by AWS D1.4/D1.4M. Submit a list of qualified welders names.
1.3.2 Qualification of Steel Bar Butt-Splicers
Qualification of steel bar butt-splicers shall be certified to have satisfactorily completed a course of instruction in the proposed method of butt-splicing or have satisfactorily performed such work within the preceding year. Submit certificates on the Qualifications of Steel Bar Butt-Splicers prior to commencing butt-splicing.
1.3.3 Qualification of Butt-Splicing Procedure
As a condition of approval of the butt-splicing procedure, make three test butt-splices of steel bars of each size to be spliced using the proposed butt-splicing method, in the presence of the Contracting Officer. These test butt-splices and unspliced bars of the same size shall be tension tested to destruction with stress-strain curves plotted for each test.
SECTION 03 20 00.00 10 Page 2
Test results shall show that the butt-splices meet the specified strength and deformation requirements in order for the splicing procedure to be approved.
1.4 DELIVERY, STORAGE, AND HANDLING
Reinforcement and accessories shall be stored off the ground on platforms, skids, or other supports.
PART 2 PRODUCTS
2.1 DOWELS
Dowels shall conform to ASTM A675/A675M, Grade 80. Steel pipe conforming to ASTM A53/A53M, Schedule 80, may be used as dowels provided the ends are closed with metal or plastic inserts or with mortar.
2.2 FABRICATED BAR MATS
Fabricated bar mats shall conform to ASTM A184/A184M.
2.3 REINFORCING STEEL
Reinforcing steel shall be deformed bars conforming to ASTM A615/A615M, ASTM A706/A706M, or ASTM A1035/A1035M grades and sizes as indicated. Cold drawn wire used for spiral reinforcement shall conform to ASTM A82/A82M.
In highly corrosive environments or when directed by the Contracting Officer, reinforcing steel shall conform to ASTM A767/A767M, ASTM A775/A775M, ASTM A1035/A1035M or ASTM A934/A934M as appropriate.
Submit certified copies of mill reports attesting that the reinforcing steel furnished contains no less than 25 percent recycled scrap steel and meets the requirements specified herein, prior to the installation of reinforcing steel.
2.4 WIRE TIES
Wire ties shall be 16 gauge or heavier black annealed steel wire.
2.5 SUPPORTS
Bar supports for formed surfaces shall be designed and fabricated in accordance with CRSI 10MSP and shall be steel or precast concrete blocks.
Precast concrete blocks shall have wire ties and shall be not less than 4 inches square when supporting reinforcement on ground. Precast concrete block shall have compressive strength equal to that of the surrounding concrete. Where concrete formed surfaces will be exposed to weather or where surfaces are to be painted, steel supports within 1/2 inch of concrete surface shall be galvanized, plastic protected or of stainless steel. Concrete supports used in concrete exposed to view shall have the same color and texture as the finish surface. For slabs on grade, supports shall be precast concrete blocks, plastic coated steel fabricated with bearing plates, or specifically designed wire-fabric supports fabricated of plastic.
SECTION 03 20 00.00 10 Page 3
PART 3 EXECUTION
3.1 REINFORCEMENT
Reinforcement steel and accessories shall be fabricated and placed as specified and shown and approved shop drawings. Fabrication and placement details of steel and accessories not specified or shown shall be in accordance with ACI SP-66 and ACI 318. Reinforcement shall be cold bent unless otherwise authorized. Bending may be accomplished in the field or at the mill.Bars shall not be bent after embedment in concrete. Safety caps shall be placed on all exposed ends of vertical concrete reinforcement bars that pose a danger to life safety. Wire tie ends shall face away from the forms. Submit detail drawings showing reinforcing steel placement, schedules, sizes, grades, and splicing and bending details. Drawings shall show support details including types, sizes and spacing.
3.1.1 Placement
Reinforcement shall be free from loose rust and scale, dirt, oil, or other deleterious coating that could reduce bond with the concrete.
Reinforcement shall be placed in accordance with ACI 318 at locations shown plus or minus one bar diameter. Reinforcement shall not be continuous through expansion joints and shall be as indicated through construction or contraction joints. Concrete coverage shall be as indicated or as required by ACI 318. If bars are moved more than one bar diameter to avoid interference with other reinforcement, conduits or embedded items, the resulting arrangement of bars, including additional bars required to meet structural requirements, shall be approved before concrete is placed.
3.1.2 Splicing
Splices of reinforcement shall conform to ACI 318 and shall be made only as required or indicated. Splicing shall be by lapping or by mechanical or welded butt connection; except that lap splices shall not be used for bars larger than No. 11 unless otherwise indicated. Welding shall conform to AWS D1.4/D1.4M. Welded butt splices shall be full penetration butt welds. Lapped bars shall be placed in contact and securely tied or spaced transversely apart to permit the embedment of the entire surface of each bar in concrete. Lapped bars shall not be spaced farther apart than one-fifth the required length of lap or 6 inches. Mechanical butt splices shall be in accordance with the recommendation of the manufacturer of the mechanical splicing device. Butt splices shall develop 125 percent of the specified minimum yield tensile strength of the spliced bars or of the smaller bar in transition splices. Bars shall be flame dried before butt splicing. Adequate jigs and clamps or other devices shall be provided to support, align, and hold the longitudinal centerline of the bars to be butt spliced in a straight line.
3.2 DOWEL INSTALLATION
Dowels shall be installed in slabs on grade at locations indicated and at right angles to joint being doweled. Dowels shall be accurately positioned and aligned parallel to the finished concrete surface before concrete placement. Dowels shall be rigidly supported during concrete placement. One end of dowels shall be coated with a bond breaker.
SECTION 03 20 00.00 10 Page 4
SECTION 03 20 00.00 10 Page 5
SECTION 03 30 00.00 10
CAST-IN-PLACE CONCRETE
11/10
PART 1 GENERAL
1.1 LUMP SUM CONTRACT
Under this type of contract, concrete items will be paid for by lump sum and will not be measured. The work covered by these items consists of furnishing all concrete materials, reinforcement, miscellaneous embedded materials, and equipment, and performing all labor for the forming, manufacture, transporting, placing, finishing, curing, and protection of concrete in these structures.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN CONCRETE INSTITUTE INTERNATIONAL (ACI)
ACI 117 (2010; Errata 2011) Specifications for Tolerances for Concrete Construction and Materials and Commentary
ACI 211.1 (1991; R 2009) Standard Practice for Selecting Proportions for Normal, Heavyweight and Mass Concrete
ACI 211.2 (1998; R 2004) Standard Practice for Selecting Proportions for Structural Lightweight Concrete
ACI 214R (2002; Errata 2010) Evaluation of Strength Test Results of Concrete
ACI 305.1 (2006) Specification for Hot Weather Concreting
ACI 318 (2014; Errata 1-2 2014; Errata 3-4 2015) Building Code Requirements for Structural Concrete and Commentary
ASTM INTERNATIONAL (ASTM)
ASTM C 1017/C 1017M (2007) Standard Specification for Chemical Admixtures for Use in Producing Flowing Concrete
ASTM C 1059/C 1059M (1999; R 2008) Standard Specification for Latex Agents for Bonding Fresh to Hardened Concrete
ASTM C 1064/C 1064M (2008) Standard Test Method for
SECTION 03 30 00.00 10 Page 1
Temperature of Freshly Mixed Hydraulic-Cement Concrete
ASTM C 1077 (2010d) Standard Practice for Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation
ASTM C 1107/C 1107M (2008) Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Nonshrink)
ASTM C 1116/C 1116M (2010a) Standard Specification for Fiber-Reinforced Concrete
ASTM C 1240 (2010a) Standard Specification for Silica Fume Used in Cementitious Mixtures
ASTM C 1260 (2007) Standard Test Method for Potential Alkali Reactivity of Aggregates (Mortar-Bar Method)
ASTM C 136 (2006) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM C 143/C 143M (2010) Standard Test Method for Slump of Hydraulic-Cement Concrete
ASTM C 150/C 150M (2009) Standard Specification for Portland Cement
ASTM C 1567 (2008) Standard Test Method for Potential Alkali-Silica Reactivity of Combinations of Cementitious Materials and Aggregate (Accelerated Mortar-Bar Method)
ASTM C 173/C 173M (2010b) Standard Test Method for Air Content of Freshly Mixed Concrete by the Volumetric Method
ASTM C 192/C 192M (2007) Standard Practice for Making and Curing Concrete Test Specimens in the Laboratory
ASTM C 31/C 31M (2010) Standard Practice for Making and Curing Concrete Test Specimens in the Field
ASTM C 33/C 33M (2011) Standard Specification for Concrete Aggregates
ASTM C 330 (2009) Standard Specification for Lightweight Aggregates for Structural Concrete
ASTM C 39/C 39M (2010) Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens
ASTM C 42/C 42M (2010a) Standard Test Method for Obtaining and Testing Drilled Cores and Sawed Beams
SECTION 03 30 00.00 10 Page 2 of Concrete
ASTM C 494/C 494M (2010a) Standard Specification for Chemical Admixtures for Concrete
ASTM C 552 (2007) Standard Specification for Cellular Glass Thermal Insulation
ASTM C 567 (2005a) Determining Density of Structural Lightweight Concrete
ASTM C 578 (2010a) Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation
ASTM C 591 (2009) Standard Specification for Unfaced Preformed Rigid Cellular Polyisocyanurate Thermal Insulation
ASTM C 618 (2008a) Standard Specification for Coal Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
ASTM C 881/C 881M (2010) Standard Specification for Epoxy-Resin-Base Bonding Systems for Concrete
ASTM C 937 (2010) Grout Fluidifier for Preplaced-Aggregate Concrete
ASTM C 94/C 94M (2010a) Standard Specification for Ready-Mixed Concrete
ASTM C 989 (2010) Standard Specification for Slag Cement for Use in Concrete and Mortars
ASTM C172/C172M (2014a) Standard Practice for Sampling Freshly Mixed Concrete
ASTM C231/C231M (2014) Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method
ASTM C260/C260M (2010a) Standard Specification for Air-Entraining Admixtures for Concrete
ASTM C78/C78M (2015a) Standard Test Method for Flexural Strength of Concrete (Using Simple Beam with Third-Point Loading)
ASTM D 75/D 75M (2009) Standard Practice for Sampling Aggregates
ASTM E 1155 (1996; R 2008) Standard Test Method for Determining Floor Flatness and Floor Levelness Numbers
ASTM E 96/E 96M (2010) Standard Test Methods for Water Vapor Transmission of Materials
SECTION 03 30 00.00 10 Page 3
NATIONAL READY MIXED CONCRETE ASSOCIATION (NRMCA)
NRMCA TMMB 100 (2001; R 2007) Truck Mixer, Agitator and Front Discharge Concrete Carrier Standards
U.S. ARMY CORPS OF ENGINEERS (USACE)
COE CRD-C 104 (1980) Method of Calculation of the Fineness Modulus of Aggregate
COE CRD-C 400 (1963) Requirements for Water for Use in Mixing or Curing Concrete
COE CRD-C 521 (1981) Standard Test Method for Frequency and Amplitude of Vibrators for Concrete
COE CRD-C 94 (1995) Corps of Engineers Specification for Surface Retarders
1.3 SYSTEM DESCRIPTION
Provide concrete composed of portland cement, other cementitious and pozzolanic materials as specified, aggregates, water and admixtures as specified.
1.3.1 Proportioning Studies-Normal Weight Conc
Trial design batches, mixture proportions studies, and testing requirements for various classes and types of concrete specified are the responsibility of the Contractor. Except as specified for flexural strength concrete, mixture proportions shall be based on compressive strength as determined by test specimens fabricated in accordance with ASTM C 192/C 192M and tested in accordance with ASTM C 39/C 39M.
a. Samples of all materials used in mixture proportioning studies shall be representative of those proposed for use in the project and be accompanied by the manufacturer's or producer's test reports indicating compliance with these specifications.
b. Make trial mixtures having proportions, consistencies, and air content suitable for the work based on methodology described in ACI 211.1, using at least three different water-cement ratios for each type of mixture, which will produce a range of strength encompassing those required for each class and type of concrete required on the project.
c. The maximum water-cement ratios required in subparagraph Water-Cement Ratio below will be the equivalent water-cement ratio as determined by conversion from the weight ratio of water to cement plus pozzolan, silica fume, and ground granulated blast furnace slag (GGBF slag) by the weight equivalency method as described in ACI 211.1. In the case where silica fume or GGBF slag is used, the weight of the silica fume and GGBF slag shall be included in the equations in ACI 211.1 for the term P, which is used to denote the weight of pozzolan. If pozzolan is used in the concrete mixture, the minimum pozzolan content shall be 15 percent by weight of the total cementitious material, and the maximum shall be 35 percent.
d. Design laboratory trial mixtures for maximum permitted slump and air content. Make separate sets of trial mixture studies for each
SECTION 03 30 00.00 10 Page 4 combination of cementitious materials and each combination of admixtures proposed for use. No combination of either shall be used until proven by such studies, except that, if approved in writing and otherwise permitted by these specifications, an accelerator or a retarder may be used without separate trial mixture study. Separate trial mixture studies shall also be made for concrete for any conveying or placing method proposed which requires special properties and for concrete to be placed in unusually difficult placing locations.
e. Report the temperature of concrete in each trial batch. For each water-cement ratio, at least three test cylinders for each test age shall be made, cured in accordance withASTM C 192/C 192M and tested at 7 and 28 days in accordance with ASTM C 39/C 39M. From these test results, plot a curve showing the relationship between water-cement ratio and strength for each set of trial mix studies. In addition, a curve shall be plotted showing the relationship between 7 day and 28 day strengths. Design each mixture to promote easy and suitable concrete placement, consolidation and finishing, and to prevent segregation and excessive bleeding.
f. Submit the results of trial mixture design studies along with a statement giving the maximum nominal coarse aggregate size and the proportions of ingredients that will be used in the manufacture of each strength or class of concrete, at least 14 days prior to commencing concrete placing operations. Aggregate weights shall be based on the saturated surface dry condition. Accompany the statement with test results from an approved independent commercial testing laboratory, showing that mixture design studies have been made with materials proposed for the project and that the proportions selected will produce concrete of the qualities indicated. No substitutions shall be made in the materials used in the mixture design studies without additional tests to show that the quality of the concrete is satisfactory.
1.3.2 Proportioning Studies-Flexural Strength Conc
Trial design batches, mixture proportioning studies, and testing requirements shall conform to the requirements specified in paragraph Proportioning Studies for Normal Weight Concrete above, except that proportions shall be based on flexural strength as determined by test specimens (beams) fabricated in accordance with ASTM C 192/C 192M and tested in accordance with ASTM C78/C78M. Modify procedures given in ACI 211.1 as necessary to accommodate flexural strength.
1.3.3 Proportioning Studies-Lightweight Aggregate Structural Conc
Trial design batches, mixture proportioning studies, and testing requirements shall conform to the requirements specified in paragraph Proportioning Studies for Normal Weight Concrete above, except as follows. Trial mixtures having proportions, consistencies and air content suitable for the work shall be made based on methodology described in ACI 211.2, using at least three different cement contents. Proportion trial mixes to produce air dry unit weight, concrete strengths, maximum permitted slump, and air content. Test specimens and testing shall be as specified for normal weight concrete except that 28-day compressive strength shall be determined from test cylinders that have been air dried at 50 percent relative humidity for the last 21 days. Determine air dry unit weight in accordance with ASTM C 567, designed to be at least 2.0 pcf less than the maximum specified air dry unit weight. Plot curves using
SECTION 03 30 00.00 10 Page 5 these results showing the relationship between cement factor and strength and air dry unit weight. Normal weight fine aggregate may be substituted for part or all of the lightweight fine aggregate, provided the concrete meets the strength and unit weight.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .