Attachment_9-_Question_and_Answer_Document.pdf

PDF 41 KB Posted

Attached to
Multi Area Renovation Federal contract opportunity
Solicitation number
W911YN-17-B-1001
Issued by
Department of the Army Florida Army National Guard

About this file

Attachment 9- Question and Answer Document

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Multi-Area Renovation

Question and Answer Document

GENERAL:

1. Would a Base contractor or an outside fire alarm contractor be required to relocate existing devices?

Existing devises will be disconnected and then reconnected in place after completed modifications of bldg. structure. The contractor will provide the necessary personnel to complete the assigned projects.

The scope of work will not necessitate a fire alarm contractor for BLDG 1005 and 1009.

BLDG1008 will require a fire alarm contractor to remove and relocate fire pull station and sound strobe for new shower construction. The scope of work will necessitate a fire alarm contractor.

2. Is certified engineering required?

Certified engineering would not be required for the assigned projects.

3. Are as-built drawings required after renovation?

Red line drawings will be sufficient at completion of construction / install and delivered to ANG/125th

CES.

BUILDING 1005:

1. Are sprinkler heads staying were located or would it be necessary to relocate them?

Sprinkler heads to remain in current fixed location. Contractor will disconnect / reconnect in current fixed locations during demo / construction of project

2. Please identify the location of Electrical Panels. Of the Access to service panels (Electrical / Water) will be the responsibility of ANG / 125th CES and will coordinate with contractor during assigned project if/when access is necessary.

3. Clarify the height of new walls. (up to ceiling, deck or midpoint with brazing) Walls will be secured from existing floor and extend 10’-0” through ceiling grid. Walls will be secured at 4’ intervals tied into existing roof truss system.

BUILDING 1008:

1. Indicate the location of the water supply for this building.

Access to service panels (Electrical / Water) will be the responsibility of ANG / 125th CES and will coordinate with contractor during assigned project if/when access is necessary.

2. Would hard ceiling be required for the bathroom areas?

Yes; hard ceiling shall be constructed in Bathrooms.

3. Indicate the type of windows or glazing required.

Window specifications will be presented to the contractor by the ANG 125th CES.

4. Please provide window dimensions.

Window manufacture and specifications will be sent to all bidding contractors by the ANG 125th CES.

5. Will toilet partitions be wall or floor to ceiling secured?

Toilet partitions to be wall mount and secured.

6. Are we installing potable water plumbing inside of demising wall between new showers?

Water supply line(s) will be provided through the demising wall for each shower.

BUILDING 1009:

1. Who will remove existing Direct TV antenna, and would it be eliminated or reinstalled?

Antenna will be removed by ANG / 125th CES.

2. Existing stair foundation may need to be replaced. Please clarify.

Concrete Landing pad for south side BLDG 1009 will be removed and replaced w/ 3000 psi 5’-0” x 5’- 0” pad prior to stair way install by contractor.

3. Would shop drawings for new awning and stairs need to be stamp and certified?

Shop drawings shall be provided by fabrication manufacture and as such stamped and certified.