Questions and Answers 27 May 2020.docx

DOCX document 34 KB Posted

Attached to
Squadron Operations Center Build / Upgrade Federal contract opportunity
Solicitation number
W50S8N20B0001
Issued by
Department of the Army National Guard

About this file

This document contains a solicitation for a construction contract and related questions and answers. The solicitation is for Project Nos. HAAW179035 and HAAW162100 to construct a new addition and renovate an existing building at the 174th Attack Wing in Syracuse, NY. Work includes building the 3,365 square foot addition and upgrading mechanical, electrical and communications systems in the existing building. The North American Industry Classification Code is 236220 and bids are sought from small businesses with average annual revenue under $39.5M. The pre-bid conference is mandatory and failure to bid on all items will result in rejection. Funds are currently unavailable for one contract line item but are expected to be available by September 30, 2020. The estimated value is between $1-5M. The solicitation, amendments and notices will be posted on SAM.gov. Questions and answers provide additional details on scope, schedules and materials.

View the file

Other files for this federal contract opportunity

Other files attached to Squadron Operations Center Build / Upgrade, newest first.
File Type Posted
Bid Abstract.pdf PDF
Bid Opening Sign In.pdf PDF
Questions and Answers 29 May 2020.docx DOCX document
W50S8N20B00010004 Amendment.pdf PDF
W50S8N20B00010004 Amendment.pdf PDF
W50S8N20B00010003 Amendment.pdf PDF
Questions and Answers 20 May 2020.docx DOCX document
HAAW179035-Addendum 02 - Dwg_R-A-601.pdf PDF
HAAW162100-Addendum 02 - Dwg_S-A-601.pdf PDF
W50S8N20B00010002 Amendment.pdf PDF
Questions and Answers 18 May 2020.docx DOCX document
Tax Form NY ST120_1_fill_in.pdf PDF
HAAW179035-Addendum 02 - Spec_08 14 00.pdf PDF
HAAW179035-Addendum 02 - Spec_23 11 25.pdf PDF
HAAW162100-Addendum 02 - Spec_08 14 00.pdf PDF
HAAW162100-Addendum 02 - Spec_09 29 00.pdf PDF
W50S8N20B00010001 Amendment.pdf PDF
HAAW179035-Addendum 02 - Spec_09 29 00.pdf PDF
W50S8N20B00010001 Amendment.pdf PDF
HAAW179035_Arch_ADDENDUM-001.pdf PDF
HAAW179035_Elec_Comm_ADDENDUM-001.pdf PDF
HAAW179035_Fire Alarm_ADDENDUM-001.pdf PDF
Pre-bid Slides HAAW179035-HAAW162100.pptx PPTX presentation
B643 Pre-Bid Sign In Sheet.pdf PDF
Attachment 7 - HAAW162100 Drawings.pdf PDF
Attachment 6 - HAAW179035 Drawings.pdf PDF
Attachment 3 - HAAW179035 Vol 2.pdf PDF
Attachment 1 - SOW HAAW179035_162100 25 Mar 2020.docx DOCX document
W50S8N20B0001 IFB Add_Alter B643.pdf PDF
Attachment 5 - HAAW162100 Vol 2.pdf PDF
Attachment 4 - HAAW162100 Vol 1.pdf PDF
Attachment 2 - HAAW179035 Vol 1.pdf PDF
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers Solicitation Number: W912PQ20B0001 Project Title: Squadron Operations Center Build / Uprade Project Number: HAAW179035 and HAAW162100 Current as of 27 May 2020

Number Question

Answer

1
For the Construction of the Reaper Operations Center, Project No. HAAW179035: Referring to drawings S-A-601 & R-A-601, as well as division 08 specifications:
Refer to drawings R-G-003 and S-G-003 which describes the overall construction phasing for each project. Door 181B is constructed under HAAW179035 project scope. Then, under the SOC renovation project scope (HAAW162100), door 181B will be replaced along with door hardware. Door 181B frame will remain.

Opening 181B appears to be included in both the Repair drawings (S) and the Construct drawings (R).

a. Construct door schedule has the opening as a new acoustical door, existing frame, hardware set 1.0.

b. Repair door schedule is new acoustical door, new acoustical frame, hardware set 2.0

c. 181B is in same location on both floor plans. Should one of these be eliminated from our quote?

2
For the Construction of the Reaper Operations Center, Project No. HAAW179035: Referring to drawings S-A-601 & R-A-601, as well as division 08 specifications:
Yes the maximum duty details apply to exterior acoustical doors and any acoustical door that is required for SCIF perimeter. For HAAW179035 project scope, provide maximum duty doors for the following doors: 164A, 164B, 180A, 180D, 181A, 181B. For HAAW162100 project scope provide maximum duty doors for the following doors: 147A, 147B, 154A, 163A, 181B.

Specification Section 08 11 13 Steel Doors and Frames – Do the Maximum Duty details apply to exterior acoustical doors?

a. Page 4 of the Repair 08 11 13 spec, under Maximum Duty Doors, at the end of the paragraph they call out 4 rooms where Maximum Duty doors are to be provided: PMATS 3, PMATS 4, FGCS-1 and FGCS-2. The Fixed GCS rooms are not numbered as 1 and 2, and I cannot locate a room with a name similar to PMATS or an acronym of that anywhere on the floor plans. 163A appears to be an exterior opening in the Fixed GCS room 163, so is there anywhere else we need to be furnishing Maximum duty doors rather than Extra Heavy Duty?

3
For the Construction of the Reaper Operations Center, Project No. HAAW179035: Referring to drawings S-A-601 & R-A-601, as well as division 08 specifications:

“Construct” 087100 hardware schedule:

Set 4 is assigned to openings 163A & 164A

a. 163A is not on the door schedule.

b. Hardware set describes the openings as both STC & Blast – Blast resistance isn’t described anywhere in the door schedule, door schedule remarks key, or door types. Is 164A to be blast resistant? If so, is there any level that needs to be met? Spec 083473 Sound Control Door Assemblies do not appear to show anything regarding blast doors or blast rating.
Refer to the door schedules on S-A-601 and R-A-601 for the door hardware set designations for each door. There are no requirements for Blast Resistant doors under the base bid on either project.

Blast reistant doors are to be included under ABI #1. Refer to response to RFI #75 below for further information.

4
For the Construction of the Reaper Operations Center, Project No. HAAW179035: Referring to drawings S-A-601 & R-A-601, as well as division 08 specifications:
Contractor must provide proper door hardware to achieve the required STC ratings. Butt hinges with closer is preferred.

“Construct” 087100 hardware schedule:

Spec 083473 calls for cam lift hinges; door hardware schedule in 087100 calls for heavy duty Butt hinges by McKinney with Sargent closers. Please advise if cam lift hinges are in fact required on acoustic doors.

5
In Section 8 there in no Blast Door Spec Section, but in HW Set 4.0 163A is an exterior door 164A is an interior door. Are either one of these a blast door? If it is a blast door we would need the correct information / specifications. Set: 4.0 Doors: 163A & 164A Description: Pair Exterior (STC, Blast)
See response to RFI 3 above.
6
Regarding Telecom, the General Notes 1-5 on Drawing# S-TN002-E Project#HAAW162100 references GFGI for much of the telecom responsibilities, while Project#179035 Drawing #R-TN002-E General Notes 1-5 reference CFCI. Is this accurate that half the job is the responsibility of the government and the other half the contractors? Does the government have their own Telecom vendor/subcontractor?
Telecommunications work shall be bid as noted on the drawings. The Contractor's responsibility varies for each contract. Work noted as 'GFGI' shall be provided by the Government.
7
Is the ESS Vendor supplying all materials to both projects? HAAW162100 and HAAW179035? Security notes on S-TN002-E reference GFGI while R-TN002-E reference CFCI? Note#4 says to “Meet with ESS vendor and contracting officer prior to the rough-in of all security equipment on the project………” Please advise.
Security work shall be bid as noted on the drawings. The Contractor's responsibility varies for each contract. Work noted as 'GFGI' shall be provided by the Government.
8
Project HAAW179035 - Addition: Drawing R-P-104 shows new gas piping running across the existing and the new building roof. Please provide details of how this should be supported.
For roof support of gas piping Contractor may use a commercial system like those manufactured by MIRO or refer to Detail 4 on drawing R-M-500. Also, see attached Facility Gas Piping Specification Section 23 11 25.
9
Project HAAW179035 - Addition: Drawing R-1-100 shows furnishings. Please indicate if this is part of this contract.
Furniture is for reference only and is not part of this contract.

Contractor is responsible for coordination of power and communications with Government's furniture vendor / installer.

10
Project HAAW179035 - Addition: Please provide a specification for the visual screening fencing and sound attenuating material shown on R-A-411.
Basis-of-Design for chain link screening fence sound attenuating material is AcoustiFence AF-6 by 'Acoustiblok'
11
Project HAAW179035 - Addition: Please provide a specification and manufacturer for the metal awning shown on R-A-411.
Basis-of-Design for prefab aluminum canopy is Lumishade by 'Mapes' with hanger rod supports, rear gutter and downspouts.
12
Project HAAW179035 - Addition: Drawing R-C-103 indicates that finished floor is at 412.67’. Drawing R-S-102 indicates finished floor is at 413.50. Please clarify which is correct.
The existing building and proposed expansion finished floors are at EL 412.67’ = 100’ which is based on the most recent NAVD 88 survey, and is the correct value.

Referenced existing building record drawings indicate a design finished floor elevation of 413.50'; however, this may be due to a different datum being used at the time for that project. The intent is that the finished floor of the new addition match the finished floor of the existing building.

13
Project HAAW179035 - Addition: I cannot find a description of ABI #1 in the specifications.
Refer to response to RFI #75 below.
14
Project HAAW179035 - Addition: In the “slab notes” section on drawing R-S-102 it indicates that a 6” layer of “porous fill” is required under each slab. Please provide a specification on this material.
Porous fill refers to typical crushed stone fill for capillary break below slab on grade. Refer to earthwork specification, 31 00 00, Section 2.4.
15
Project HAAW179035 - Addition: Details 1 and 3 on drawing R-C-501 indicate “aggregate base” is to be installed under concrete pavements. Please provide a specification for this material.
Aggregate base shall conform to the NYSDOT Standard Specifications, Section 304 from a NYSDOT approved source.
16
Project HAAW162100 - Renovations: Note 3 on drawing S-MD101 indicates that insulation on pipe fittings is to be considered asbestos. There is no asbestos specification.
Based on available documentation, no ACM should be present within Building 643. Should Contractor find Asbestos during demo work, Contractor shall immediately inform Base Civil Engineer and Contracting Officer.
17
Project HAAW162100 - Renovations: The fire protection work appears to be a delegated design. Is it acceptable to reuse existing piping if it complies with NFPA and the delegated design?
Refer to Keynote FD1 in drawings S-FD101A and S-FD101B demolition is as needed, existing pipe can be reused provided it complies with all applicable codes. Applicable code is UFC 3-600-01 - Fire Protection Engineering for Facilities.
18
Project HAAW162100 - Renovations: Note 1 on drawing S-MD101 indicates that all equipment within the shaded area is to be removed, however, no ductwork or piping associated with this equipment is shown. Is there ductwork and piping connected to these units and is it to be removed as well?
Existing ductwork and piping are only partially shown. All existing equipment and associated ductwork and piping in the area of contract are to be removed up to points of disconnection as indicated.
19
The solicitation indicates that we have 330 days to complete the contract. Section 00100.1 also says that there will be a pause of 6 to 12 months between constructing the addition and performing the renovations. Given the pause, 330 days is not adequate to complete both phases of the project. Can you provide a more detailed time frames for phase 1, the shutdown timeframe, and phase 2?
- HAAW179035 (Phase 1) 330 days. Phase 2 work in west boundary rooms should be completed during Phase 1 330 days. - The 6-12 month pause begins at completion of Phase 1 construction of HAAW179035. - HAAW162100 (Phase 2) 180 days to complete remaining work. The 180 days starts at the end of the 6-12 month pause.
20
SECTION 25 10 10 mentions an existing Utility Monitoring and Control System (UMCS) for the Building Automation System. What manufacturer is this?
Manufacturer is Alerton.
21
In Section 8 there in no Blast Door Spec Section but in HW Set 4.0 163A is an exterior door 164A is an interior door. Are either a blast door? If it is a blast door we would need the correct information. Set: 4.0 Doors: 163A & 164A Description: Pair Exterior (STC, Blast)
See response to RFI 3 above.
22
Who is currently contracted on the base for the fire alarm and security systems? Honeywell? Please Advise.
Contractor to coordinate with Base Civil Engineer.

The Base's security vendor is Vindicator Technologies by Honeywell as noted on R-TN002 and S-TN002.

The Base does not have a preferred fire alarm vendor for the FACU or ACU. The existing FACU in this facility is manufactured by Simplex. The existing transceiver and antenna are manufactured by Monaco Systems. The installed ACU (INWS) is a custom system that was installed under a government contract. There isn't a single manufacturer for the system.

23
After reviewing the drawings, we have been unable to locate any visual display units at either Reaper Operations Center or the Repair Squadron. Please advise which drawings reflect the visual display units.
The only new flat panel displays are in the Reaper Operations Center 181. They are annotated on R-A-101 via keynote A22 and can be seen on Building Section 5/R-A-301. Flat panel displays are GFGI. Contractor to coordinate blocking, electrical and communications requirements with equipment provided.
24
Regarding Project HAAW179035:

Drawing R-M-101-D Shows (1) Space Temperature Sensor in Open Office Room 165. This space temperature sensor is shown to be wired into HP-01. DX-1 and DX-1R Units are to be furnished with thermostats, yet these thermostats are not shown on this drawing. Can you please designate where on the drawings that these two thermostats are to be installed?

Temperature sensor in Room 165 shall be connected to HP-01. Temperature sensor for DX-1&1R shall be installed in MGCS container. See keyed note M13 on R-M-101.

25
Regarding Project HAAW179035:

Drawing R-M-101-D Does not show any Space Temperature Sensors for Server Room 180. CRAC-1 and CRAC-1R are to be furnished with thermostats, yet these thermostats are not shown on this drawing. Can you please designate where on the drawings that these two thermostats are to be installed?

Temperature sensor is located in the return ductwork. See drawing R-M-701.

26
Reference drawings S-FD101A-C, S-FD101B-C, S-FX101A-C, and S-FX101B-C. General Note #4 of the demo drawings states “All existing fire sprinklers and piping indicated in ‘Record As-Built Drawings’ shall be verified in field” and General Note #5 of the new installation drawings states “Refer to Associated Fire Protection Corp ‘Record As-Built Drawings’ dated 12-30-09 for the existing fire sprinkler system information”.

The above referenced as-builts of the existing areas within B643 were not included with the RFP. Please provide as-built drawings of the existing fire sprinkler system. If as-builts are unavailable, please provide bid assumptions for all bidders.

Referenced drawings are attached and are to be used for reference only. Contractor is responsible to verify existing conditions.

27
The W50S8N20B0001 Solicitation (SF 1442) states in Box 11 that the project duration is 330 calendar days from NTP. Attachment 1 SOW states in Section 4 that the period of performance for HAAW179035 (Construct Addition) was 330 days, and the period of performance for HAAW162100 (Renovation) was 300 days. Please clarify the overall period of performance for solicitation W508S8N20B0001.
- HAAW179035 (Phase 1) 330 days. Phase 2 work in west boundary rooms should be completed during Phase 1 330 days. - The 6-12 month pause begins at completion of Phase 1 construction of HAAW179035. - HAAW162100 (Phase 2) 180 days to complete remaining work. The 180 days starts at the end of the 6-12 month pause.
28
Attachment 1 SOW Section 1 Scope of Work states that the pause duration for the movement of operations from the current SCIF to the new addition is “estimated at 6-12 months”. Please confirm the government will be issuing a Stop-Work Order for this time period so that it will not negatively affect the overall period of performance for the contractor.
The government will issue a stop work order when for the pause.
29
SF 1442 states in Box 10 that “Funds are unavailable for CLIN 0003” (HAAW162100 B643 Renovation). Since CLIN 0003 is indicated to be “BASE BID”, does the government anticipate awarding all of Solicitation W50S8N-20-B-0001 (both the addition & renovation) only when funds become available for the renovation CLIN 0003, or can CLIN 0001 be awarded separately? Please confirm for scheduling purposes.
All CLIN's will be awarded at the same time.
30
Please clarify the scope of the existing raised Floor repair per HAAW162100. Is information available on the existing access floor other than the specification?
Scope is defined on drawing S-A-531. See attached record documentation for Rooms 158 & 161. This information is provided for reference only. Contractor to field verify existing conditions.
31
Expansion Area New Floor GCS 164. Is the new 8” FFH floor to be a stringerless or rigid grid understructure? Drawing notes conflict between Type AF-2 Stringerless and AF-1 Rigid Grid.
Room 164 raised floor is to be stringerless system.
32
Confirm that a factory applied Conductive High Pressure laminate tile is required per specification section 09 69 13 paragraph 2.2.4.1 as opposed to Standard grade High pressure laminate tile.
Yes this is required for Fixed GCS Room 164 and Server Room 180.
33
Confirm that CRAC units shown in Server Room 180 sit on their own stands necessitating the access floor be cut around the per-positioned stands.
Correct. Provide CRAC units with stands as indicated in the contract documents.
34
Confirm that Directional Air Flow panels are required in Server Room 180 as shown and per 09 69 13 paragraph 2.8, as opposed to standard perforated air flow panels. A cut sheet on a Directional Air Flow panel is attached.
Yes, this is required.
35
Reference Demo Note #3 of Drawing S-MD101-D (B643 Renovation project). Note #3 states “Insulation on pipe fittings considered to have asbestos and shall be disposed of in accordance with all local environmental requirements”.

Please confirm this insulation referenced above is the only location in which a hazardous material (asbestos, lead, PCB’s, mercury, etc) is expected to be encountered for both the new construction addition project, and the renovation project.

Based on available documentation, no ACM should be present within Building 643. Should Contractor find ACM or any other hazardous building materials during demo work, Contractor shall immediately inform Base Civil Engineer and Contracting Officer.

36
Specification 10 21 13 Toilet Compartments has been provided for project HAAW162100. Are toilet compartments required, and if so, where on the drawings are they located. Please advise?
The only requirement is for new urinal screens in Men's Room 151. Refer to S-A-401
37
Specification 10 11 00 Visual Display Units has been provided for project HAAW162100. Are visual display units required, and if so, where on the drawings are they located. Please advise?
Refer to response to RFI #23 above.
38
Specification 10 26 00 Wall and Door Protection has been provided for project HAAW162100. Are corner guards required, and if so, where on the drawings are they located. Please advise?
Corner guards are required on all outside wall corners within the HAAW162100 project scope of work area. Assume minimum 30 guards. There are also 3 corner guards identified in the Reaper Operations Center 181 under project HAAW179035 on drawings 1/R-A-101 with tag 'CG'.
39
Specifications 08 14 00 Wood Doors has been provided for project HAAW162100. The door schedule on drawing A-601 only lists Hollow Metal Doors. Please clarify if wood doors are required, and if so, where and how many?
Wood Doors are required for all interior doors. Refer to Addendum #2 drawings and specifications.
40
Drawings R-TN402-E & R-TN403-E, keyed notes T001 & T002 require aluminum wire basket cable tray. Please advise as to a manufacturer who makes an aluminum wire basket cable tray as we have confirmed with multiple vendors that this product is not made in aluminum? Is an equal of different material allowed?
Basket cable tray can be of steel construction that has been zinc-coated after fabrication.
41
Drawing R-TN504-E Shows a center hung (center spine) open end cable tray. Would a ladder type be allowed at these locations?
Provide basket cable tray.
42
Reference Drawing S-TN002-E, Project Inside Plant General Notes. Note 1 states "GFCI"; however, notes 2, 4, & 5 state "GFGI". Please advise to which is correct for this portion of the project.
Note 1 shall read GFGI, not GFCI.
43
Reference Drawing S-TN002-E, Security (IDS/ACS) Notes. Note 1 states "GFGI". Please advise if this is the case for the security portion of this project.
GFGI is correct.
44
Reference Drawing S-TN501-E, Communications – Modular Jack and Cabling Faceplate Information Schedule. Note 6 states "All new cabling shall be GFGI." Please advise if this is the case and will the contractor be responsible for equipment installations, terminating, and testing only?
GFGI is correct. Testing shall be performed by the Contractor.
45
Reference Drawing R-TN002-E, Project Inside Plant General Notes. Notes 1, 2, 4, 5 states "CFCI". Please confirm CFCI is correct.
CFCI is correct.
46
Reference Drawing R-TN002-E, Security (IDS/ACS) Notes. Note 1 states "CFCI". Please confirm CFCI is correct.
CFCI is correct.
47
Per specifications 09 69 13 & 09 69 19, both the rigid grid access flooring and stringerless access flooring are comprised of 24” x 24” panels with pedestals. If the pedestals in the grid systems are 24” OC, the 24” wide cable tray shown on drawings R-TN403-E & R-TN404-E will not fit. Are 20” wide cable trays acceptable under raised floor areas?
20" wide cable trays are acceptable below the raised floor.
48
Drawing R-A-701-F Finish Legend indicates CPT-1, 24"x24" ESC Carpet Tile by Staticworks, Shadow FX, Lake Tahoe. This carpet will have a minimum order of 250 square yards. The required square yard is much less, under 100. Confirm the government will pay for the minimum yardage and take ownership of the material not used. Or will the government want to change from the Lake Tahoe group of colors as all those colors have this minimum purchase of material? Please advise?
Provide equal product to basis of design that complies with Spec Section 09 68 00 - Carpeting.
49
HAAW179035

The demolition of the large air handling units on the south side of existing building 643 are not shown on the mechanical drawings, only the site drawings. There is a substantial amount of work required to remove these units and the associated ductwork. There is also refrigerant removal required that must be done by the mechanical contractor. I am concerned that this work will be missed by the mechanical contractors since it isn’t on their drawings.

Two existing units on the south side of existing building 643 are shown on Mechanical Demo drawing R-MD101.

50
HAAW162100

Please define the roof work associated with the mechanical demolition and new work. Drawing S-MD-101 shows mechanical equipment demolition which h must include associated roofing work, however, nothing is defined.

All mechanical demolition shown on S-MD-101 is inside the building. No roof demolition is required.

51
HAAW179035: Drawing R-G-002, VII Note 2 states that the contractor is responsible for all applicable permits.

A) What, if any, permits is the contractor responsible for?

No NY State or County permits are required. Contractor to coordinate required Base permits with Base Civil Engineer / Contracting Officer. Refer to Specification Section 01 11 00. Contractor is required to prepare and submit FAA Form 7460-1 – Notice of Proposed Construction or Alteration for all cranes to be used on site during construction. Forms to be submitted via FAA Obstruction Evaluation / Airport Airspace Analysis (OE/AAA) website (oeaaa.faa.gov).

52
HAAW179035: Drawing R-CD100, what is the thickness of the concrete apron to removed.
Per available record drawings, the apron is 8" thick with thickened edges along the north and south.
53
HAAW179035: Drawing R-CD100, Note 13 states to relocate existing security cabling and concrete deadman. This is not shown on the drawings. Please indicate where and to what extent needs to be relocated on the drawings.
Note to be deleted.
54
HAAW179035: Drawing R-C-101, Note 2 states “For Bid Option Stair and Fence layout, see structural and architectural drawings. There is no stair and fence on drawings, and there is also no bid option for stair and fence.
Note to be deleted.
55
HAAW179035: Drawing R-C-101, Note 3 states “Exact location of dumpster pad to be coordinated with contracting officer. Dumpster pad is not shown on drawings. Please provide information.
Note to be deleted.
56
HAAW179035: Drawing R-CD100, what is the depth of gravel to be removed?
Depth is 5 inches.
57
HAAW179035: Drawing ES-101, what is -S- conduit shown from inside Reaper Ops Center routed outside to close to Sanitary MH. Is this to be installed new by the contractor?
Refer to Drawing R-CD100. This is an existing sanitary line that is to be demolished. It should be deleted from Drawing R-ES101.
58
HAAW179035: Exterior wall details on R-A-311/312 indicate 1) a cementitious crystalline waterproofing for foundation as well as a rubberized moisture barrier for the foundation. Are these 2 separate products to be applied? If so, please clarify where is the Crystalline waterproofing to be installed as the note just points to the center of the foundation.
These are two separate products. Both are required. The crystalline waterproofing is an admixture within the concrete mix for the foundation. The rubberized moisture barrier is applied to the surface.
59
HAAW179035: Several details indicate (2) layers of 5/8” gwb over the metal decking and several details on R-A-571 do not. These details also do not indicate a cover board as shown on R-A-101. Please provide clarification on profile of entire roof.
The typical roof construction is as shown on the roof type schedule on R-A-101. This applies to all roof conditions and details.
60
HAAW179035: There is a specification for Wall and Door Protection, but we have not been able to locate these items on the drawings. Please advise where they are to be installed.
Refer to response to RFI #38 above.
61
HAAW179035: Hardware set #4.0 indicates it is for Doors 163A and 164A. There is no 163A on the drawings. Should this be 164A and 164B? Also, is the upgrade to ATFP for these doors what should be included in Bid Item 0002? If not, please provide more direction on what should be included in Bid Item 0002.
Door 163A is part of project HAAW162100 scope. Refer to response to RFI #3 above. ABI #1 is to provide ATFP compliant exterior doors. Refer to response to RFI #75 below for further information.
62
HAAW179035: Door specification refers to Civil drawings for Standoff Distance. The Civil dwgs do not indicate standoff distance. What is the standoff distance to figure for ATFP doors?
Refer to response to RFI #75 below.
63
HAAW179035: Is this project Sales Tax exempt?
IAW NYS tax law, in certain circumstances, a contractor or subcontractor can make a purchase without paying sales tax using Form ST-120.1. Please see the attached form.
64
HAAW179035: Is the Spray Applied Foam acting as the Air Barrier? If so, where is the self-adhering air barrier to be installed?
Yes the spray applied foam is acting as the air barrier. Self-adhering air barrier is only required at transition if necessary.
65
HAAW179035: Please provide detail and specification/manufacturer for Note A22 Flat Screen Display on R-A-101.
Flat panel displays are GFGI. Contractor to coordinate blocking, electrical and communications with equipment provided.
66
HAAW179035: How long does the NYANG anticipate for moving into the new addition (HAAW179035) once it is complete?
This is the pause time (6-12 months). The construction on HAAW179035 must be certified as a SCIF prior to starting operations.
67
HAAW179035: Details for framing behind metal panel wall on Drawing R-A-352 refer to 4” metal framing as well as 4” cold rolled framing. Cold rolled generally refers to heavier gauge framing, such as 16/18 ga, whereas regular metal framing would be 20ga. Which should be used?
The exterior metal framing must all be considered cold formed metal framing which is governed by specification section 05 40 00 and is delegated design. Bidders must have the cold formed framing engineered.
68
HAAW162100: What is height of deck in existing building for bidding purposes?
Underside of existing roof deck elevation is approx. 12'-8" A.F.F. Contractor to field verify.
69
HAAW162100: Please provide basis of design for auditorium seating.
Requirements are included in Spec Section 12 61 13 - Upholstered Audience Seating.
70
Storage Room 161 also has a note DA-20 to remove existing mechanical equipment, this is likely to to be large air conditioning units, which are typically installed on independent stands.

Q: Will we be required to fill back in these void space, where the A/C units have been removed with new floor system including grid and panels?

Many times this type of A/C removal will include new A/C units and potentially new Air-Flow panels. I don’t see anything on the mechanical drawings showing new A/C or sometimes known as CRAC units.

The existing Server Room 161 is being converted to a Storage Room 161. Voids in the floor supports must be infilled and new floor tiles must be installed to fill in any voids. There are no new CRAC units in this room.

71
Storage Room 161: Are there any indications or requirement for new air flow panels ( also know as grates, diffusers or perforated panels)?
No, see response to RFI #70 above.
72
TS ROC 158: The cross hatched plans showing the area to be modified does match between the demo plan (S-AD010) & floor plan (S-A531)

Q: Floor plan shows an area of 360 square feet of floor to be modified ( only underneath the new fixed seating) Demo plan shows a larger area of 608 square feet Assume the larger area for extent of scope.

73
The sections I am referencing are 27 51 16 and 27 54 00.00 20. What communication system is currently in the building? Looking for manufacturer if possible.
PA system head end equipment is located in Comm Room 117A. New PA system devices shall be wired to the panels in this room.

Provide new CATV fiber to coax converter and patch panels in the new Server Room. New CATV devices shall be wired to the patch panels. This converter shall be wired back to the existing coax converter in the existing Communications Room 117. The system is custom built, no manufacturer available.

74
HAAW162100

Note DA-20 on drawing S-AD010 indicates that mechanical equipment is to be removed from Room 161. Are these CRAC units sitting on stands? If so, will there be a void in the access floor that will need to be filled once the units are removed? Are these panels in addition to the 100 infill panels discussed on the drawing?

Refer to response to RFI #70 above.

75
The solicitation states that CLIN 0002 – Add AFPP compliant exterior doors as shown as option 1 in HAAW179035 specifications. There are no options or scopes shown within those specs. Please clarify.
Performance Requirements: Provide a Low Level of protection for the peak pressure and positive phase impulse that corresponds to Explosive Weight II as specified in UFC 4-010-02 at the actual standoff distance to parking, roadways or trash containers.
76
I don’t see an interior insulation spec anywhere and there is no info included in 092900 Gypsum board. There are several different kinds referenced in the drawings (batts, foil faced, safe and sound mineral wool).
Refer to relevant specifications provided in Addendum #2.
77
Addendum #1, Sheet R-A-101-G, contract HAAW179035, Note A06 was changed to A06.1 Does the same change need to be made to contract HAAW162100 where note AO6 is also referenced?
The change was unique to Contract HAAW179035. Note A06 shall NOT change in Contract HAAW162100.
78
Addendum #2 A06.1 reads to extend new layer of gyp board to underside of roof deck, and to paint all the way to the roof deck. Does gyp over a suspended ceiling need full finish or is fire tape adequate?
Full finish floor to ceiling even above ceiling grid.
79
On drawing R-Tn501-E; can you clarify Detail G,H, and I is looking for A SINGLE PORT SC coupler but the cable feeding it indicates a 2 strand fiber, is the fiber to support two couplers or to be left terminated but not used? This would affect all faceplates details that use these symbols.
The SC port is a wider port which usually only allows one port per available block on the faceplate. The 2-strand cable is to accommodate the two ports in that faceplate that are side by side. The fiber is to support two couplers.

See note below.

80
On Drawing S-TN502-E Floor Box Detail F1; can you clarify 36 MM FOC LC, is to be 36 strand of fiber or 36- 2 strand fibers? same question for all fiber indicated ?
We are looking for the specified strand of fiber which would provide for separate pairs of terminations for LC, SC, or ST. For instance, 36 strand = 18 paired terminations, 12 strand = 6 paired terminations.

See note below.

81
On Drawing R-TN502-E AV detail: can you clarify for the G faceplate which is for single SC coupler inserts, which would require 24 strand of fiber or 12- 2 strand fibers and the E faceplate which requires 24 duplex LC inserts and require 48 strand or 24- 2 strand fibers, totaling 36 -2 strands fiber cable not 48 fiber cables as indicated?
G Faceplate will require 12-2 Strand fibers to complete the SC pair port terminations.

E Faceplate will require 24-2 Strand fibers to complete the LC port terminations.

Your assessment totaling 36-2 strand fiber cables is correct.

See note below.

N/A
Gov't provided note for RFIs 79-81:
The different classifications will terminate in the server room in different racks and subsequently the “guest” connections of each classification will terminate in a separate LIU in the rack of that classification. For instance, where there are faceplates with Secret and TS ports those ports will terminate in completely different racks in the server room. Where there are Secret and Secret Guest (LG-Low Guest) those will terminate in the same rack but different LIUs within that rack. This is typical with the High Side and High side guest.
82
Will the government accept electronic bids?
No, electronic bids will not be accepted. Hard copy bids must be received before the public bid opening on 1 June 2020 at 3:00PM.
83
From the attached Q & A, there are numerous questions asked for doors including Blast resistant Doors (ATFP)- Bid Option 1

Please provide which exterior doors (qty) required blast criteria with standoff distance along with the door number.

None of the answers clarify, which doors are blast doors.

All exterior doors are blast doors.

84
The plumbing spec contains a table detailing what materials can be used for each piping system utilized on this project. If you look at the bottom of each schedule, it denotes the system and references that number throughout the piping material schedule. From my understanding and interpretation of the schedule, PVC piping may be used for all drain, waste and vent piping. On previous projects located at the 174th Attack Wing, cast iron was used for these systems. The domestic piping schedule also calls out many nontraditional materials may be used for these systems. CPVC and PEX are called out as acceptable materials for the domestic systems. On previous projects located at the 174th Attack Wing, copper with sweat fittings was specifically used. There is significant cost impact associated with installing these different materials. It would be more cost effective to use these specified materials but knowing what the rest of the base uses, I’m not positive that this was the intent of the specs. Running cast iron and copper is normally the accepted standard for these systems. Please clarify if these materials are acceptable for use on this project.
Polyethylene piping is not allowed for pipe and fitting materials for drainage, waste, vent and condensate piping systems.

All above grade sanitary waste and vent piping shall be cast iron, hubless, CISPI 301.

All below grade sanitary waste and vent piping shall be cast iron, hub and spigot, ASTM A74 ABS and PVC are not permitted for these applications and should be deleted from Spec Section 22 00 00 Table I for these services. (Deleted in amendment 0004) Roof drain piping shall be in accordance with Spec Section 22 00 00 Table I. Note that polyethylene piping (PE, PEX) is not included and is not permitted for roof drain piping.

85
The structural steel specification indicates that all fabrication and erection drawings be provided with a P.E. stamp by the subcontractor. Given that this is a conflict of interest, is it required? The subcontractor will prepare stamped drawings for any delegated design items.
Signing and sealing of erection and fabrication drawings is not required except for fabricator proposed connection revisions.

Signing and sealing of all delegated design items is required.

86
I had asked question 49 regarding the demo of the exterior HVAC units and the response was that the units are shown on R-MD101. Looking at the building on Google Earth, there is a substantial amount of demolition and associated roof work that is not indicated on MD101. Please clarify the demolition work, roofing work, and any deck infills associated with the removal of these units.
Drawing R-MD101 Key Note MD02 reads, “Contractor shall demolish all HVAC equipment and associated ductwork, piping, control and supports located within the demo boundary indicated.”

Existing units CU-E1 and CU-E2 and are shown within the area of demo work on the same drawing, Drawing R-AD010 Key Note reads, “Remove existing mechanical equipment and all associated components including concrete foundations.”

Drawing R-A-101 General Note 2 reads, “At locations if removed mechanical equipment or ductwork patch roof to match existing. Verify locations and sizes of openings to be patched in the field. Provide rigid insulation and PVC roof membrane above new roof deck to match and align with existing roof membrane.”

Drawing R-AG002 General Note 39 reads, “Remove abandoned pipe, ducts, conduits, and equipment including those above accessible ceilings back to the source of supply where possible. Where not possible cap, stub and tag with identification. Patch holes left by removal using materials specified for new construction.

The contractor should submit a proposed closure detail once they have field verified the actual condition after the ductwork has been removed.

New steel roof deck for the closures should meet the specifications for new steel roof deck on the addition. See Steel Deck notes on drawing R-S-001.