This document contains a door and window schedule for a construction project. It provides specifications for 41 doors and 2 windows to be installed at the new Squadron Operations Center. Door types include flush panel insulated, flush panel, and pairs of doors. Materials specified are hollow metal, wood, and aluminum. Frame details and hardware sets are identified. Dimensions, ratings, and other requirements are outlined. Related details are referenced. The schedule also notes general requirements for exterior doors and sound control assemblies.

The federal contract opportunity is a solicitation for construction of a new addition and renovations to an existing building at Hancock Field Air National Guard Base in Syracuse, New York. Work includes construction of a new 3,365 square foot one-story addition and upgrades to an existing Squadron Operations Facility building, in accordance with provided contract documents, plans, and specifications. The total project value is estimated between $1 million and $5 million. The NAICS code listed is 236220 and small businesses must meet the $39.5 million average annual revenue size standard to qualify. The pre-bid conference and site visit are encouraged for those intending to submit a bid. The Army National Guard is the issuing agency. Funds are currently unavailable for one contract line item.

View the file

Other files for this federal contract opportunity

Other files attached to Squadron Operations Center Build / Upgrade, newest first.
File Type Posted
Bid Opening Sign In.pdf PDF
Bid Abstract.pdf PDF
Questions and Answers 29 May 2020.docx DOCX document
W50S8N20B00010004 Amendment.pdf PDF
Questions and Answers 27 May 2020.docx DOCX document
W50S8N20B00010004 Amendment.pdf PDF
W50S8N20B00010003 Amendment.pdf PDF
Questions and Answers 20 May 2020.docx DOCX document
HAAW162100-Addendum 02 - Dwg_S-A-601.pdf PDF
HAAW162100-Addendum 02 - Spec_09 29 00.pdf PDF
W50S8N20B00010001 Amendment.pdf PDF
HAAW179035-Addendum 02 - Spec_09 29 00.pdf PDF
W50S8N20B00010002 Amendment.pdf PDF
Questions and Answers 18 May 2020.docx DOCX document
Tax Form NY ST120_1_fill_in.pdf PDF
HAAW179035-Addendum 02 - Spec_08 14 00.pdf PDF
HAAW179035-Addendum 02 - Spec_23 11 25.pdf PDF
HAAW162100-Addendum 02 - Spec_08 14 00.pdf PDF
W50S8N20B00010001 Amendment.pdf PDF
HAAW179035_Arch_ADDENDUM-001.pdf PDF
HAAW179035_Elec_Comm_ADDENDUM-001.pdf PDF
HAAW179035_Fire Alarm_ADDENDUM-001.pdf PDF
Pre-bid Slides HAAW179035-HAAW162100.pptx PPTX presentation
B643 Pre-Bid Sign In Sheet.pdf PDF
Attachment 7 - HAAW162100 Drawings.pdf PDF
W50S8N20B0001 IFB Add_Alter B643.pdf PDF
Attachment 5 - HAAW162100 Vol 2.pdf PDF
Attachment 4 - HAAW162100 Vol 1.pdf PDF
Attachment 2 - HAAW179035 Vol 1.pdf PDF
Attachment 6 - HAAW179035 Drawings.pdf PDF
Attachment 3 - HAAW179035 Vol 2.pdf PDF
Attachment 1 - SOW HAAW179035_162100 25 Mar 2020.docx DOCX document
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A

SCHEDULE

DOOR PER A

B

S C

H E

D U

L E

D O

O R

P E

R

D O

O R

P E

R S

C H

E D

U L E

SCHEDULE

DOOR PER

F1

S E

E S

C H

E D

U L E

S

IL

L H

E

IG

H T

S E

E S

C H

E D

U L E

H E

IG

H

T

SEE SCHEDULE

WIDTH

W1

FINISH FLOOR

LEVEL

CL

EQ EQ

HOLLOW METAL

FRAME

W2

SEALANT (TYPICAL)

EACH SIDE

HOLLOW METAL

FRAME

W

IN

D O

W

H E

IG

H

T S

E E

S C

H E

D U

LE

METAL STUD WALL - SEE

ENLARGED FLOOR PLANS

FOR WALL TYPE

1/2"

SERVER ROOM

HEAT STRENGTHENED

GLASS (HSG-1)

GLAZING TAPE

NEOPRENE SETTING

BLOCK

GLAZING STOP

1/2"

METAL STUD BOXED

HEADER

SEALANT (TYPICAL)

EACH SIDE

HOLLOW METAL

FRAME

W

IN

D O

W W

ID

T

H S

E E

S C

H E

D U

LE

METAL STUD WALL - SEE

ENLARGED FLOOR PLANS

FOR WALL TYPE

1/2"

SERVER ROOM

HEAT STRENGTHENED

GLASS (HSG-1)

GLAZING TAPE

NEOPRENE SETTING

BLOCK

GLAZING STOP

1/2"

DOUBLE STUD AT JAMB

SEALANT (TYPICAL)

EACH SIDE

HOLLOW METAL

FRAME

W

IN

D O

W

E

IG

H

T S

E E

S C

H E

D U

LE

METAL STUD WALL - SEE

ENLARGED FLOOR PLANS

FOR WALL TYPE

1/2"

SERVER ROOM

HEAT STRENGTHENED

GLASS (HSG-1)

GLAZING TAPE

NEOPRENE SETTING

BLOCK

GLAZING STOP

1/2"

W

IN

D O

W S

IL

L

H E

IG

H

T S

E E

S C

H E

D U

LE

date detailed checkeddesigned ofsheet sheets project contract rev.drawing file

no. date descriptionby ckd

1 1312111098765432

I

H

G

F

E

D

C

B

A

CONSTRUCT REAPER OPERATIONS

CENTER BUILDING 643

HAAW179035

174 ATTACK WING

HANCOCK FIELD AIR NATIONAL GUARD BASE

SYRACUSE, NEW YORK

10 N PARK PLACE, SUITE 330

MORRISTOWN, NEW JERSEY 07960

973-884-8701

BMCD LICENSE NO 000165

103179

H

/1

/2

:4

:4

P

M

Proj. No._A_CENTRAL

R-A-601

DOOR & WINDOW SCHEDULE

11/26/18

B. BAKAS B. BAKAS

V. VYAS

DOOR SCHEDULE

DOOR

NUMBER

DOOR FRAME

ASSEMBLY

RATING STC

DETAIL

CARD

READER HARDWARE SET REMARKS

SIZE

TYPE MATERIAL FINISH TYPE MATERIAL FINISH HEAD JAMB SILL

PAIR

DOOR WIDTH HEIGHT

GROUND FLOOR

164A PR. 3' - 0" 7' - 0" F-IN HM PE-3 1.1 HM PE-4 - 45 4A / R-A-611 4D&11D / R-A-611 4G / R-A-611 No 4.0 1,3

164B PR. 3' - 0" 7' - 0" F WD FF-1 1.1 HM PE-4 - - 1A / R-A-611 1D / R-A-611 1G / R-A-611 Yes 5.0

180A PR. 3' - 0" 7' - 0" F-IN HM PE-3 1.1 HM PE-4 - 45 4A / R-A-611 4D / R-A-611 4G / R-A-611 No 3.0 1,3

180B - 3' - 0" 7' - 0" F WD FF-1 1.1 HM PE-4 - - 8A / R-A-611 8D / R-A-611 8G / R-A-611 Yes 6.0

180C - 3' - 0" 7' - 0" F WD FF-1 1.1 HM PE-4 - 50 1A / R-A-611 1D / R-A-611 11G / R-A-611 No 7.0 3

180D - 4' - 0" 7' - 0" F-IN HM PE-3 1.1 HM PE-4 - 45 4A / R-A-611 4D / R-A-611 4G / R-A-611 No 2.0 1,3

181A PR. 3' - 0" 7' - 0" F WD FF-1 1.1 HM PE-4 - 50 8A / R-A-611 8D / R-A-611 8G / R-A-611 Yes 5.0 3

181B - 3' - 0" 7' - 0" F-IN HM PE-3 1.1 HM PE-4 - 50 4A / R-A-611 4D / R-A-611 4G / R-A-611 Yes 1.0 2,3

182 - 3' - 0" 7' - 0" F WD FF-1 1.1 HM PE-4 - - 8A / R-A-611 8D / R-A-611 8G / R-A-611 No 8.0

184 - 3' - 0" 7' - 0" F WD FF-1 1.1 HM PE-4 - - 8A / R-A-611 8D / R-A-611 8G / R-A-611 No 9.0

DOOR AND FRAME LEGEND

FINISH

FF-1* FACTORY FINISHED

PE-1** PAINT-EPOXY

MATERIAL

AL ALUMINUM

HM HOLLOW METAL

WD WOOD

SIZE

- SINGLE DOOR

PR PAIR OF DOORS

UPR UNEQUAL PAIR

*REFERENCE DOOR OR FRAME SPECIFICATION

**FIELD APPLY PER PAINT SPECIFICATION FOR

APPLICABLE SUBSTRATE AND EXPOSURE.

(DOOR FRAME)

TYPE A B

1.1 2" 2"

(FLUSH PANEL)

TYPE DESCRIPTION

F-IN FLUSH PANEL INSULATED

F FLUSH PANEL

REMARKS KEY:

1. EXIT ONLY, NO EXTERIOR DOOR HARDWARE.

2. X-10 LOCK

3. SOUND CONTROL DOOR ASSEMBLIES

GENERAL DOOR SCHEDULE NOTES:

1. ALL EXTERIOR DOORS SHALL HAVE

INSULATED CORE.

FRAME TYPES DOOR TYPES

WINDOW SCHEDULE

QUANTITY TYPE

SIZE SILL

HEIGHT

DETAIL

REMARKSWIDTH HEIGHT HEAD JAMB SILL

1 W01 5' - 0" 4' - 0" 3' - 0" 1/A-601 2/A-601 3/A-601

1 W02 2' - 0" 4' - 0" 3' - 0" 1/A-601 2/A-601 3/A-601

WINDOW ELEVATION

1HEAD DETAIL

2JAMB DETAIL 3SILL DETAIL

SCALE IN FEET

0 3" 6" 9"

SCALE IN FEET

0 3" 6" 9"

SCALE IN FEET

0 3" 6" 9"

C 01/18/19 VV BB TYPE B-1 SUBMITTAL

D 05/20/19 VV BB TYPE B-2 SUBMITTAL

E 07/26/19 VV BB TYPE B-2 SUBMITTAL TO NGB

F 12/09/19 VV BB TYPE B-3 SUBMITTAL

H 05/12/20 RA BB ADDENDUM 002

H

H

H

H

H

Sheets
R-A-601 - DOOR & WINDOW SCHEDULE

File details come from the government source that posted it. Updated .