HAAW179035-Addendum 02 - Spec_23 11 25.pdf

PDF 44 KB Posted

Attached to
Squadron Operations Center Build / Upgrade Federal contract opportunity
Solicitation number
W50S8N20B0001
Issued by
Department of the Army National Guard

About this file

This document package contains specifications for a gas piping system and a related federal contract opportunity for construction work. The specifications cover materials, submittals, testing, and installation requirements for a gas piping system serving Building 643 at Hancock Field Air National Guard Base in Syracuse, New York. The federal contract opportunity is a solicitation for construction of a new addition and renovations to the existing Squadron Operations Facility building on the base. Work includes a new 3,365 square foot addition and upgrades to the existing building, and will be performed according to the contract, plans and technical specifications. The NAICS code is 236220 for commercial and institutional building construction, with a small business size standard of $39.5 million average annual revenue. The project value is estimated between $1 million and $5 million. The solicitation is set aside for total small businesses and pre-bid attendance is encouraged. The submission deadline is not provided. Funding for one contract line item is currently unavailable but may be obtained by September 30, 2020.

View the file

Other files for this federal contract opportunity

Other files attached to Squadron Operations Center Build / Upgrade, newest first.
File Type Posted
Bid Abstract.pdf PDF
Bid Opening Sign In.pdf PDF
Questions and Answers 29 May 2020.docx DOCX document
W50S8N20B00010004 Amendment.pdf PDF
Questions and Answers 27 May 2020.docx DOCX document
W50S8N20B00010004 Amendment.pdf PDF
W50S8N20B00010003 Amendment.pdf PDF
Questions and Answers 20 May 2020.docx DOCX document
HAAW179035-Addendum 02 - Dwg_R-A-601.pdf PDF
HAAW162100-Addendum 02 - Dwg_S-A-601.pdf PDF
W50S8N20B00010002 Amendment.pdf PDF
Questions and Answers 18 May 2020.docx DOCX document
Tax Form NY ST120_1_fill_in.pdf PDF
HAAW179035-Addendum 02 - Spec_08 14 00.pdf PDF
HAAW162100-Addendum 02 - Spec_08 14 00.pdf PDF
HAAW162100-Addendum 02 - Spec_09 29 00.pdf PDF
W50S8N20B00010001 Amendment.pdf PDF
HAAW179035-Addendum 02 - Spec_09 29 00.pdf PDF
W50S8N20B00010001 Amendment.pdf PDF
HAAW179035_Arch_ADDENDUM-001.pdf PDF
HAAW179035_Elec_Comm_ADDENDUM-001.pdf PDF
HAAW179035_Fire Alarm_ADDENDUM-001.pdf PDF
Pre-bid Slides HAAW179035-HAAW162100.pptx PPTX presentation
B643 Pre-Bid Sign In Sheet.pdf PDF
Attachment 7 - HAAW162100 Drawings.pdf PDF
Attachment 6 - HAAW179035 Drawings.pdf PDF
Attachment 3 - HAAW179035 Vol 2.pdf PDF
Attachment 1 - SOW HAAW179035_162100 25 Mar 2020.docx DOCX document
W50S8N20B0001 IFB Add_Alter B643.pdf PDF
Attachment 5 - HAAW162100 Vol 2.pdf PDF
Attachment 4 - HAAW162100 Vol 1.pdf PDF
Attachment 2 - HAAW179035 Vol 1.pdf PDF
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HAAW162100 Construct Reaper Operations Center Building 643

Hancock Field Air National Guard Base, Syracuse, NY

103179

SECTION 23 11 25 Page 1

PART 1 GENERAL

1.1 SUMMARY

SECTION 23 11 25

FACILITY GAS PIPING

11/08

This specification section applies to gas piping installed within buildings incidental underground piping under building, above ground steel piping and corrugated stainless steel tubing (CSST) both outside (up to 5 feet beyond exterior walls) and within buildings in compliance with NFPA 54

/AGA Z223.1, "National Fuel Gas Code" NFPA 58, "Fuel Gas Piping".

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN GAS ASSOCIATION (AGA)

AGA Z223.1 (2012) National Fuel Gas Code

AMERICAN PETROLEUM INSTITUTE (API)

API Std 598 (2009) Valve Inspecting and Testing

API Std 607 (2016) Fire Test for Quarter-turn Valves and Valves Equipped with Non-metallic Seats

AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)

ASCE 25-16 (2016) Earthquake-Activated Automatic Gas

Shutoff Devices

ASME INTERNATIONAL (ASME)

ASME A13.1 (2015) Scheme for the Identification of

Piping Systems

ASME B1.20.2M (2006; R 2011) Pipe Threads, 60 Deg.

General Purpose (Metric)

ASME B16.1 (2015) Gray Iron Pipe Flanges and Flanged

Fittings Classes 25, 125, and 250

ASME B16.3 (2016) Malleable Iron Threaded Fittings, Classes 150 and 300

ASME B16.33 (2012; R 2017) Manually Operated Metallic

Gas Valves for Use in Gas Piping Systems

Up to 125 psi, (Sizes NPS 1/2 - NPS 2)

ASME B16.39 (2014) Standard for Malleable Iron

Threaded Pipe Unions; Classes 150, 250, SECTION 23 11 25 Page 2 and 300

ASME B36.10M (2015; Errata 2016) Welded and Seamless

Wrought Steel Pipe

ASTM INTERNATIONAL (ASTM)

ASTM A53/A53M (2018) Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless

CSA GROUP (CSA)

ANSI LC 1/CSA 6.26 (2018) Fuel Gas Piping Systems Using

Corrugated Stainless Steel Tubing (CSST)

FM GLOBAL (FM)

FM APP GUIDE (updated on-line) Approval Guide http://www.approvalguide.com/

MANUFACTURERS STANDARDIZATION SOCIETY OF THE VALVE AND FITTINGS

INDUSTRY (MSS)

MSS SP-25 (2013) Standard Marking System for Valves, Fittings, Flanges and Unions

MSS SP-58 (2009) Pipe Hangers and Supports -

Materials, Design and Manufacture, Selection, Application, and Installation

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 54 (2018) National Fuel Gas Code

NFPA 58 (2017; ERTA 17-1) Liquefied Petroleum Gas

Code

SOCIETY FOR PROTECTIVE COATINGS (SSPC)

SSPC SP 6/NACE No.3 (2007) Commercial Blast Cleaning

U.S. DEPARTMENT OF DEFENSE (DOD)

MIL-STD-101 (2014; Rev C) Color Code for Pipelines and for Compressed Gas Cylinders

UFC 3-310-04 (2013; with Change 1, 2016) Seismic Design of Buildings

UNDERWRITERS LABORATORIES (UL)

UL FLAMMABLE & COMBUSTIBLE (2012) Flammable and Combustible Liquids and Gases Equipment Directory

1.3 SYSTEM DESCRIPTION

The gas piping system includes natural gas piping and appurtenances from point of connection with supply system, as indicated, to gas operated

SECTION 23 11 25 Page 3 equipment within the facility. Submit operation and maintenance data in accordance with Section 01 78 23 OPERATION AND MAINTENANCE DATA, in three separate packages. Section 23 03 00.00 20 BASIC MECHANICAL MATERIALS AND

METHODS applies to this section, with additions and modifications specified herein.

1.3.1 Gas Facility System and Equipment Operation

Include shop drawings showing piping layout, locations of system valves, gas line markers; step-by-step procedures for system start up, operation and shutdown (index system components and equipment to the system drawings); isolation procedures including valve operation to shutdown or isolate each section of the system (index valves to the system maps and provide separate procedures for normal operation and emergency shutdown if required to be different). Submit Data package No. 4.

1.3.2 Gas Facility System Maintenance

Include maintenance procedures and frequency for system and equipment;

identification of pipe materials and manufacturer by locations, pipe repair procedures, and jointing procedures at transitions to other piping material or material from a different manufacturer. Submit Data Package

No.4.

1.3.3 Gas Facility Equipment Maintenance

Include identification of valves, shut-offs, disconnects, and other equipment by materials, manufacturer, vendor identification and location;

maintenance procedures and recommended tool kits for valves and equipment;

recommended repair methods (i.e., field repair, factory repair, or replacement) for each valve and piece of equipment; and preventive maintenance procedures, possible failure modes and troubleshooting guide.

Submit Data Package No. 3.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.

SD-02 Shop Drawings

Gas Piping System; G

SD-03 Product Data

Pipe and Fittings; G

Gas Piping System; G

Pipe Coating Materials; G

Valves; G

Warning and Identification Tape; G

SD-06 Test Reports

SECTION 23 11 25 Page 4

Testing; G

Pressure Tests; G

Test with Gas; G

SD-08 Manufacturer's Instructions

Pipe Coating Materials; G

SD-10 Operation and Maintenance Data

Gas Facility System and Equipment Operation; G

Gas Facility System Maintenance; G

Gas Facility Equipment Maintenance; G

1.5 QUALITY ASSURANCE

Submit manufacturer's descriptive data and installation instructions for approval for compression-type mechanical joints used in joining dissimilar materials and for insulating joints. Mark all valves, flanges and fittings in accordance with MSS SP-25.

1.5.1 Shop Drawings

Submit drawings for complete Gas Piping System, within 30 days of contract award, showing location, size and all branches of pipeline; location of all required shutoff valves; and instructions necessary for the installation of gas equipment connectors and supports.

PART 2 PRODUCTS

2.1 MATERIALS AND EQUIPMENT

Provide materials and equipment which are the standard products of a manufacturer regularly engaged in the manufacture of the products and that essentially duplicate items that have been in satisfactory use for at least 2 years prior to bid opening. Asbestos or products containing asbestos are not allowed. Submit catalog data and installation instructions for pipe, valves, all related system components, pipe coating materials and application procedures. Conform to NFPA 54NFPA 58 and with requirements specified herein. Provide supply piping to appliances or equipment at least as large as the inlets thereof.

2.2 GAS PIPING SYSTEM AND FITTINGS

2.2.1 Steel Pipe, Joints, and Fittings

a. Pipe: Black carbon steel in accordance with ASTM A53/A53M, Schedule 80, threaded ends for sizes 2 inches and smaller; otherwise, plain end beveled for butt welding.

b. Threaded Fittings: ASME B16.3, black malleable iron.

c. Unions: ASME B16.39, black malleable iron.

Provide steel pipe conforming to ASME B36.10M; and malleable-iron threaded

SECTION 23 11 25 Page 5 fittings conforming to ASME B16.1 and ASME B16.3.

2.2.2 Sealants for Steel Pipe Threaded Joints

Provide joint sealing compound as listed in UL FLAMMABLE & COMBUSTIBLE, Class 20 or less. For taping, use tetrafluoroethylene tape conforming to

UL FLAMMABLE & COMBUSTIBLE.

2.2.3 Warning and Identification

Provide pipe flow markings, warning and identification tape, and metal tags as required.

2.2.4 Pipe Threads

Provide pipe threads conforming to ASME B1.20.2M.

2.2.5 Escutcheons

Provide chromium-plated steel or chromium-plated brass escutcheons, either one piece or split pattern, held in place by internal spring tension or set screw.

2.2.6 Insulating Pipe Joints

2.2.6.1 Insulating Joint Material

Provide insulating joint material between flanged or threaded metallic pipe systems where shown to control galvanic or electrical action.

2.2.6.2 Threaded Pipe Joints

Provide threaded pipe joints of steel body nut type dielectric unions with insulating gaskets.

2.3 VALVES

Provide lockable shutoff or service isolation valves as indicated in the drawings conforming to the following:

2.3.1 Valves 2 Inches and Smaller

Provide valves 2 inches and smaller conforming to ASME B16.33 of materials and manufacture compatible with system materials used.

2.4 PIPE HANGERS AND SUPPORTS

Provide pipe hangers and supports conforming to MSS SP-58.

2.5 IDENTIFICATION FOR ABOVEGROUND PIPING

MIL-STD-101 for legends and type and size of characters. For pipes 3/4 inch od and larger, provide printed legends to identify contents of pipes and arrows to show direction of flow. Color code label backgrounds to signify levels of hazard. Make labels of plastic sheet with pressure-sensitive adhesive suitable for the intended application. For pipes smaller than 3/4 inch od, provide brass identification tags 1 1/2 inches in diameter with legends in depressed black-filled characters.

SECTION 23 11 25 Page 6

PART 3 EXECUTION

3.1 EXAMINATION

After becoming familiar with all details of the work, verify all dimensions in the field, and advise the Contracting Officer of any discrepancy or areas of conflict before performing the work.

3.2 GAS PIPING SYSTEM

Provide a gas piping system from the point of delivery, defined as the outlet of the service regulator, to the connections to each gas utilization device that is in compliance with NFPA 54.

3.2.1 Protection and Cleaning of Materials and Components

Protect equipment, pipe, and tube openings by closing with caps or plugs during installation. At the completion of all work, thoroughly clean the entire system.

3.2.2 Workmanship and Defects

Piping, tubing and fittings must be clear and free of cutting burrs and defects in structure or threading and must be thoroughly brushed and chip-and scale-blown. Repair of defects in piping, tubing or fittings is not allowed; replace defective items when found.

3.3 PROTECTIVE COVERING

3.3.1 Aboveground Metallic Piping Systems

3.3.1.1 Ferrous Surfaces

Touch up shop primed surfaces with ferrous metal primer. Solvent clean surfaces that have not been shop primed . Mechanically clean surfaces that contain loose rust, loose mill scale and other foreign substances by power wire brushing or commercial sand blasted conforming to

SSPC SP 6/NACE No.3 and prime with ferrous metal primer or vinyl type wash coat. Finish primed surfaces with two coats of exterior oil paint or vinyl paint.

3.4 INSTALLATION

Install the gas system in conformance with the manufacturer's recommendations and applicable provisions of NFPA 54, and as indicated.

Perform all pipe cutting without damage to the pipe, with an approved type of mechanical cutter, unless otherwise authorized. Use wheel cutters where practicable. On steel pipe 6 inches and larger, an approved gas cutting and beveling machine may be used.

3.4.1 Concealed Piping in Buildings

Do not use combinations of fittings (unions, tubing fittings, running threads, right- and left-hand couplings, bushings, and swing joints) to conceal piping within buildings.

3.4.1.1 Piping and Tubing in Partitions

Locate concealed piping and tubing in hollow, rather than solid, SECTION 23 11 25 Page 7 partitions. Protect tubing passing through walls or partitions against physical damage both during and after construction, and provide appropriate safety markings and labels. Provide protection of concealed pipe and tubing in accordance with ANSI LC 1/CSA 6.26.

3.4.1.2 Piping in Floors

Laying piping in solid floors shall not be permitted.

3.4.2 Aboveground Piping

Run aboveground piping as straight as practicable along the alignment and elevation indicated, with a minimum of joints, and separately supported from other piping system and equipment. Install exposed horizontal piping no farther than 6 inches from nearest parallel wall and at an elevation which prevents standing, sitting, or placement of objects on the piping.

3.4.3 Final Gas Connections

Unless otherwise specified, make final connections with rigid metallic pipe and fittings. Provide accessible gas shutoff valve and coupling for each gas equipment item.

3.4.4 Seismic Requirements

Support and brace piping and attached valves to resist seismic loads in conformance with ASCE 25-16. CSST tubing and fittings that are seismically qualified in accordance with the FM APP GUIDE: Flexible

Piping Systems for Flammable Gases must meet the seismic requirements in accordance with the manufacturer's installation instructions.

3.5 PIPE JOINTS

Design and install pipe joints to effectively sustain the longitudinal pull-out forces caused by contraction of the piping or superimposed loads.

3.5.1 Threaded Metallic Joints

Provide threaded joints in metallic pipe with tapered threads evenly cut and made with UL approved graphite joint sealing compound for gas service or tetrafluoroethylene tape applied to the male threads only. Threaded joints up to 1-1/2 inches in diameter may be made with approved tetrafluoroethylene tape. Threaded joints up to 2 inches in diameter may be made with approved joint sealing compound. After cutting and before threading, ream pipe and remove all burrs. Caulking of threaded joints to stop or prevent leaks is not permitted.

3.6 PIPE SLEEVES

Provide pipes passing through concrete or masonry walls or concrete floors or roofs with pipe sleeves fitted into place at the time of construction.

Do not install sleeves in structural members except where indicated or approved. Make all rectangular and square openings as detailed. Extend each sleeve through its respective wall, floor or roof, and cut flush with each surface, except in mechanical room floors not located on grade where clamping flanges or riser pipe clamps are used. Extend sleeves in

SECTION 23 11 25 Page 8 mechanical room floors above grade at least 4 inches above finish floor.

Unless otherwise indicated, use sleeves large enough to provide a minimum clearance of 1/4 inch all around the pipe. Provide steel pipe for sleeves in bearing walls, waterproofing membrane floors, and wet areas . Provide sleeves in nonbearing walls, floors, or ceilings of steel pipe, galvanized sheet metal with lock-type longitudinal seam, or moisture-resistant fiber or plastic. For penetrations of fire walls, fire partitions and floors which are not on grade, seal the annular space between the pipe and sleeve with fire-stopping material and sealant that meet the requirement of

Section 07 84 00 FIRESTOPPING.

3.7 PIPES PENETRATING WATERPROOFING MEMBRANES

Install pipes penetrating waterproofing membranes as specified in Section

22 00 00 PLUMBING, GENERAL PURPOSE.

3.8 FIRE SEAL

Fire seal all penetrations of fire rated partitions, walls and floors in accordance with Section 07 84 00 FIRESTOPPING.

3.9 ESCUTCHEONS

Provide escutcheons for all finished surfaces where gas piping passes through floors, walls, or ceilings except in boiler, utility, or equipment rooms.

3.10 SPECIAL REQUIREMENTS

Provide drips, grading of the lines, freeze protection, and branch outlet locations as shown and conforming to the requirements of NFPA 54.

3.11 BUILDING STRUCTURE

Do not weaken any building structure by the installation of any gas piping. Do not cut or notch beams, joists or columns. Attach piping supports to metal decking. Do not attach supports to the underside of concrete filled floors or concrete roof decks unless approved by the

Contracting Officer.

3.12 PIPING SYSTEM SUPPORTS

Support gas piping systems in buildings with pipe hooks, metal pipe straps, bands or hangers suitable for the size of piping or tubing. Do not support any gas piping system by other piping. Conform spacing of supports in gas piping and tubing installations to the requirements of

NFPA 54. Conform the selection and application of supports in gas piping and tubing installations to the requirements of MSS SP-58. In the support of multiple pipe runs on a common base member, use a clip or clamp where each pipe crosses the base support member. Spacing of the base support members is not to exceed the hanger and support spacing required for any of the individual pipes in the multiple pipe run. Rigidly connect the clips or clamps to the common base member. Provide a clearance of 1/8 inch between the pipe and clip or clamp for all piping which may be subjected to thermal expansion.

3.13 TESTING

Submit test procedures and reports in booklet form tabulating test and

SECTION 23 11 25 Page 9 measurements performed; dated after award of this contract, and stating the Contractor's name and address, the project name and location, and a list of the specific requirements which are being certified. Test entire gas piping system to ensure that it is gastight prior to putting into service. Prior to testing, purge the system, clean, and clear all foreign material. Test each joint with an approved gas detector, soap and water, or an equivalent nonflammable solution. Inspect and test each valve in conformance with API Std 598 and API Std 607. Complete testing before any work is covered, enclosed, or concealed, and perform with due regard for the safety of employees and the public during the test. Install bulkheads, anchorage and bracing suitably designed to resist test pressures if necessary, and as directed and or approved by the Contracting

Officer. Do not use oxygen as a testing medium.

3.13.1 Pressure Tests

Submit test procedures and reports in booklet form tabulating test and measurements performed; dated after award of this contract, and stating the Contractor's name and address, the project name and location, and a list of the specific requirements which are being certified. Before appliances are connected, test by filling the piping systems with air or an inert gas to withstand a minimum pressure of 3 pounds gauge for a period of not less than 10 minutes as specified in NFPA 54 without showing any drop in pressure. Do not use Oxygen for test. Measure pressure with a mercury manometer, slope gauge, or an equivalent device calibrated to be read in increments of not greater than 0.1 pound. Isolate the source of pressure before the pressure tests are made.

3.13.2 Test With Gas

Before turning on gas under pressure into any piping, close all openings from which gas can escape. Immediately after turning on the gas, check the piping system for leakage by using a laboratory-certified gas meter, an appliance orifice, a manometer, or equivalent device. Conform all testing to the requirements of NFPA 54. If leakage is recorded, shut off the gas supply, repair the leak, and repeat the tests until all leaks have been stopped.

3.13.3 Purging

After testing is completed, and before connecting any appliances, fully purge all gas piping. Do not purge piping into the combustion chamber of an appliance. Do not purge the open end of piping systems into confined spaces or areas where there are ignition sources unless the safety precautions recommended in NFPA 54 are followed.

3.13.4 Labor, Materials and Equipment

Furnish all labor, materials and equipment necessary for conducting the testing and purging.

3.14 PIPE COLOR CODE MARKING

Provide color code marking of piping conforming to ASME A13.1.

-- End of Section --