The file's text, extracted by GovTribe without its formatting.
DEPARTMENT OF VETERANS AFFAIRS VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
VOLUME 1
| DIVISION 00 - SPECIAL SECTIONS |
| DATE |
| 00 01 15 |
| List of Drawing Sheets |
| 09-11 |
DIVISION 01 - GENERAL REQUIREMENTS
| 01 00 00 |
| General Requirements |
| 10-14 |
| 01 30 00 |
| Electronic Submittal Requirements |
| 01 32 16.15 |
| Project Schedules (Small Projects – Design/Bid/Build) |
| 01 33 23 |
| Shop Drawings, Product Data, and Samples |
| 03-12 |
| 01 35 26 |
| Safety Requirements |
| 10-14 |
| 01 42 19 |
| Reference Standards |
| 09-11 |
| 01 58 16 |
| Temporary Interior Signage |
| 01 74 19 |
| Construction Waste Management |
| 09-13 |
| 01 91 00 |
| General Commissioning Requirements |
| 06-13 |
DIVISION 02 – EXISTING CONDITIONS
| 02 41 00 |
| Demolition |
| 04-13 |
| 02 82 11 |
| Class I Negative Pressure Enclosure Asbestos Abatement Specifications |
| 07-11 |
DIVISION 05 – METALS
| 05 50 00 |
| Metal Fabrications |
| 07-14 |
DIVISION 06 – WOOD,PLASTICS AND COMPOSITES
| 06 40 23 |
| Architectural Woodwork |
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
| 07 21 13 |
| Thermal Insulation |
| 06-12 |
| 07 84 00 |
| Firestopping |
| 10-11 |
| 07 92 00 |
| Joint Sealants |
| 12-11 |
DIVISION 08 - OPENINGS
| 08 11 13 |
| Hollow Metal Doors and Frames |
| 01-13 |
| 08 14 00 |
| Interior Wood Doors |
| 10-12 |
| 08 31 13 |
| Access Doors and Frames |
| 10-11 |
| 08 35 13.13 |
| Accordion Folding Doors |
| 10-11 |
| 08 41 13 |
| Aluminum-Framed Entrances and Storefronts |
| 10-11 |
| 08 42 43 |
| ICU / CCU Sliding Entrances |
Expand Specialty Care - Building 1 Renovate 6th Floor D-Wing May 10, 2017 Project # 583-331
00 01
10-
| 08 56 19 |
| Pass Windows |
| 10-11 |
| 08 71 00 |
| Door Hardware |
| 11-14 |
| 08 71 13.11 |
| Low Energy Power Assist Door Operators |
| 12-13 |
DIVISION 09 – FINISHES
| 09 05 16 |
| Subsurface Preparation for Floor Finishes |
| 04-14 |
| 09 06 00 |
| Schedule for Finishes- 6th Floor D-Wing |
| 10-11 |
| 09 22 16 |
| Non-Structural Metal Framing |
| 10-14 |
| 09 29 00 |
| Gypsum Board |
| 11-14 |
| 09 30 13 |
| Ceramic/Porcelain Tiling |
| 11-14 |
| 09 51 00 |
| Acoustical Ceilings |
| 12-13 |
| 09 54 23 |
| Linear Metal Ceilings |
| 10-11 |
| 09 65 13 |
| Resilient Base and Accessories |
| 10-11 |
| 09 65 16 |
| Resilient Sheet Flooring |
| 07-13 |
| 09 65 19 |
| Resilient Tile Flooring |
| 03-11 |
| 09 72 18 |
| Digital Image Wall Covering |
DIVISION 10 – SPECIALTIES
| 10 11 13 |
| Chalkboards and Markerboards |
| 10-11 |
| 10 11 23 |
| Tackboards |
| 11-11 |
| 10 14 15 |
| Signage Identifying Devices – Interior Signs |
| 11-11 |
| 10 21 23 |
| Cubicle Curtain Tracks |
| 11-11 |
| 10 26 00 |
| Wall and Door Protection |
| 01-11 |
| 10 26 10 |
| Fiber Reinforced Laminate Panels (FRL) |
| 10 28 00 |
| Toilet, Bath, and Laundry Accessories |
| 11-11 |
| 10 44 13 |
| Fire Extinguisher Cabinets |
| 08-14 |
DIVISION 11 – EQUIPMENT
| 11 73 00 |
| Ceiling Mounted Patient Lift System |
| 09-14 |
DIVISION 12 – FURNISHINGS
| 12 34 00 |
| Integrated Patient Care Modular System |
| 12 36 00 |
| Countertops |
| 06-13 |
VOLUME 2
DIVISION 21- FIRE SUPPRESSION
| 21 05 11 |
| Common Work Results for Fire Suppression |
| 11-09 |
| 21 13 13 |
| Wet-Pipe Sprinkler Systems |
| 05-08 |
DIVISION 22 – PLUMBING
| 22 05 11 |
| Common Work Results for Plumbing |
| 07-14 |
| 22 05 23 |
| General-Duty Valves for Plumbing Piping |
| 07-14 |
| 22 07 11 |
| Plumbing Insulation |
| 05-11 |
| 22 11 00 |
| Facility Water Distribution |
| 01-14 |
| 22 13 00 |
| Facility Sanitary and Vent Piping |
| 07-14 |
| 22 40 00 |
| Plumbing Fixtures |
| 01-14 |
| 22 62 00 |
| Vacuum Systems for Laboratory and Healthcare Facilities |
| 08-12 |
| 22 63 00 |
| Gas Systems for Laboratory and Healthcare Facilities |
| 12-10 |
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
| 23 05 11 |
| Common Work Results for HVAC |
| 11-10 |
| 23 05 12 |
| General Motor Requirements for HVAC and Steam Generation Equipment |
| 11-10 |
| 23 05 41 |
| Noise and Vibration Control for HVAC Piping and Equipment |
| 11-10 |
| 23 05 93 |
| Testing, Adjusting, and Balancing for HVAC |
| 05-11 |
| 23 07 11 |
| HVAC and Boiler Plant Insulation |
| 05-11 |
| 23 08 00 |
| Commissioning of HVAC Systems |
| 06-13 |
| 23 09 23 |
| Direct-Digital Control System for HVAC |
| 09-11 |
| 23 21 13 |
| Hydronic Piping |
| 09-12 |
| 23 21 23 |
| Hydronic Pumps |
| 02-10 |
| 23 22 13 |
| Steam and Condensate Heating Piping |
| 03-10 |
| 23 25 00 |
| HVAC Water Treatment |
| 02-10 |
| 23 31 00 |
| HVAC Ducts and Casings |
| 03-13 |
| 23 36 00 |
| Air Terminal Units |
| 03-10 |
| 23 37 00 |
| Air Outlets and Inlets |
| 11-09 |
| 23 40 00 |
| HVAC Air Cleaning Devices |
| 02-12 |
| 23 74 13 |
| Packaged, Outdoor, Central-Station Air-Handling Units |
| 12-14 |
DIVISION 26 – ELECTRICAL
| 26 05 11 |
| Requirements for Electrical Installations |
| 12-12 |
| 26 05 19 |
| Low-Voltage Electrical Power Conductors and Cables |
| 07-13 |
| 26 05 26 |
| Grounding and Bonding for Electrical Systems |
| 12-12 |
| 26 05 33 |
| Raceway and Boxes for Electrical Systems |
| 05-14 |
| 26 05 39 |
| Underfloor Raceways for Electrical Systems |
| 08-14 |
| 26 05 73 |
| Overcurrent Protective Device Coordination Study |
| 26 09 23 |
| Lighting Controls |
| 05-14 |
| 26 22 00 |
| Low-Voltage Transformers |
| 08-14 |
| 26 24 16 |
| Panelboards |
| 05-14 |
| 26 27 26 |
| Wiring Devices |
| 08-14 |
| 26 29 11 |
| Motor Controllers |
| 08-14 |
| 26 29 21 |
| Enclosed Switches and Circuit Breakers |
| 12-12 |
| 26 41 00 |
| Facility Lightning Protection |
| 12 12 |
| 26 43 13 |
| Surge Protective Device |
| 12-12 |
| 26 51 00 |
| Interior Lighting |
| 08-14 |
VOLUME 3
DIVISION 27 – COMMUNICATIONS
| 27 05 11 |
| Requirements for Communications Installations |
| 11-09 |
| 27 05 26 |
| Grounding and Bonding for Communications Systems |
| 10-06 |
| 27 05 33 |
| Raceways and Boxes for Communications Systems |
| 12-05 |
| 27 08 00 |
| Commissioning of Communications System |
| 13-06 |
| 27 10 00 |
| Structured Cabling |
| 12-05 |
| 27 11 00 |
| Communications Equipment Room Fittings |
| 06-13 |
| 27 15 00 |
| Communications Horizontal Cabling |
| 06-13 |
| 27 41 31 |
| Master Antenna Television Equipment and Systems |
| 06-13 |
| 27 51 16 |
| Public Address and Mass Notification Systems |
| 06-13 |
| 27 52 23 |
| Nurse Call and Code Blue Systems |
| 06-13 |
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
| 28 05 00 |
| Common Work Results for Electronic Safety and Security |
| 09-11 |
| 28 05 13 |
| Conductors and Cables for Electronic Safety and Security |
| 09-11 |
| 28 05 26 |
| Grounding and Bonding for Electronic Safety and Security |
| 09-11 |
| 28 05 28.33 |
| Conduits and Backboxes for Electronic Safety and Security |
| 09-11 |
| 28 08 00 |
| Commissioning of Electronic Safety and Security |
| 13-06 |
| 28 13 00 |
| Physical Access Control System |
| 10-11 |
| 28 23 00 |
| Video Surveillance |
| 09-11 |
| 28 31 00 |
| Fire Detection and Alarm |
| 10-11 |
SECTION 00 01 15 LIST OF DRAWINGS
The drawings listed below accompanying this specification form a part of the contract.
General
| 1-GI-002 |
| Abbreviations & UL Ratings |
| 1-LS-001 |
| Sixth Floor-Life Safety Plan |
| 1-LS-002 |
| Eighth Floor-Life Safety Plan |
Architecture
| 1-AD-101 |
| Sixth Floor Demolition Plan |
| 1-AD-102 |
| Eighth Floor Demolition Plan |
| 1-AS-001 |
| Wall Types & Rated Partitions |
| 1-AS-101 |
| Sixth Floor-Overall |
| 1-AS-102A |
| Sixth Floor-Area 'A' |
| 1-AS-102B |
| Sixth Floor-Area 'B', 7th Floor Work |
| 1-AS-103A |
| Eighth Floor-Overall & Area 'A' |
| 1-AS-103B |
| Eighth Floor-Area 'B' |
| 1-AS-111 |
| Sixth Floor-Reflected Ceiling Plan |
| 1-AS-112 |
| Eighth Floor-Reflected Ceiling Plan |
| 1-AS-301 |
| Sixth Floor-Sections & Details |
| 1-AS-401 |
| Sixth Floor-Signage |
| 1-AS-402 |
| Sixth Floor-Wall Protection |
| 1-AS-403 |
| Eighth Floor-Signage |
| 1-AS-404 |
| Eight Floor-Wall Protection |
00 01
15-
| 1-AS-411 |
| Sixth Floor - Oncology Interior Elevation Key Plan |
| 1-AS-412 |
| Sixth Floor - Oncology Interior Elevations |
| 1-AS-413 |
| Sixth Floor - Oncology Interior Elevations |
| 1-AS-414 |
| Sixth Floor - Oncology Interior Elevations |
1-AS-415
Eighth Floor - Compensation & Pension Interior Elevation Key Plan
1-AS-416
Eighth Floor - Compensation & Pension Interior Elevations
1-AS-417
Sixth Floor – Oncology Pharmacy & Med Prep Interior Elevations
| 1-AS-420 |
| Interior Sections & Details |
| 1-AS-501 |
| Sixth & Eighth Floor-Common Details |
| 1-AS-601 |
| Sixth Floor-Door Schedule & Storefronts |
| 1-AS-602 |
| Eighth Floor-Door Schedule |
| 1-AS-701A |
| Sixth Floor - Oncology Finish Plan - Area "A" |
| 1-AS-701B |
| Sixth Floor - Oncology Finish Plan - Area "B" |
1-AS-702A
Eighth Floor - Compensation & Pension Finish Plan - Overall & Area "A"
1-AS-702B
Eighth Floor - Compensation & Pension Finish Plan – Area "B"
| 1-AS-801 |
| Sixth Floor - Oncology Equipment Plan - Overall |
| 1-AS-801A |
| Sixth Floor - Oncology Equipment Plan - Area "A" |
| 1-AS-801B |
| Sixth Floor - Oncology Equipment Plan - Area "B" |
| 1-AS-802A |
| Sixth Floor - Oncology Equipment Schedule |
| 1-AS-802B |
| Sixth Floor - Oncology Equipment Schedule |
| 1-AS-802C |
| Sixth Floor - Oncology Equipment Schedule |
1-AS-803A
Eight Floor - Compensation & Pension Equipment Plan - Overall & Area "A"
1-AS-803B
Eighth Floor - Compensation & Pension Equipment Plan Area "B"
| 1-AS-804A |
| Eighth Floor - Compensation & Pension Equipment Schedule |
| 1-AS-804B |
| Eighth Floor - Compensation & Pension Equipment Schedule |
MECHANICAL
| 1-MI-001 |
| Mechanical Notes, Abbreviations, and Legend |
| 1-MD-101 |
| Sixth Floor Mechanical Demolition Plan |
| 1-MD-102 |
| Sixth Floor Mechanical Piping Demolition Plan |
| 1-MD-103 |
| Eighth Floor Mechanical Demolition Plan |
| 1-MD-104 |
| Eighth Floor Mechanical Piping Demolition Plan |
| 1-MD-105 |
| D Wing Roof Mechanical Demolition Plan |
| 1-MH-101 |
| Sixth Floor Mechanical HVAC Plan |
| 1-MH-102 |
| Eighth Floor Mechanical HVAC Plan |
| 1-MH-103 |
| D Wing Roof Mechanical Plan |
| 1-MP-101 |
| Sixth Floor Mechanical Piping Plan |
| 1-MP-102 |
| Eighth Floor Mechanical Piping Plan |
| 1-MP-103 |
| D Wing Roof Mechanical Piping Plan |
| 1-MP-104 |
| Partial D Wing Basement Mechanical Piping Plan |
| 1-M-501 |
| Mechanical Details |
| 1-M-502 |
| Mechanical Details |
| 1-M-503 |
| Mechanical Details |
| 1-M-601 |
| Mechanical Schedules |
| 1-M-602 |
| Mechanical Schedules |
Plumbing
| 1-P-001 |
| Plumbing Notes, Abbreviations, Legend and Schedules |
| 1-FD-101 |
| Sixth Floor D Wing Fire Protection Demolition Plan |
| 1-FD-102 |
| Eighth Floor C Wing Fire Protection Demolition Plan |
| 1-FX-101 |
| Sixth Floor D Wing Fire Protection Plan |
| 1-FX-102 |
| Eighth Floor C Wing Fire Protection Plan |
| 1-PD-101 |
| Fifth Floor D Wing Plumbing Demolition Plan |
| 1-PD-102 |
| Sixth Floor D Wing Plumbing Demolition Plan |
| 1-PD-103 |
| Sixth Floor D Wing Medical Gas Demolition Plan |
| 1-PD-104 |
| Seventh Floor C Wing Plumbing Demolition Plan |
| 1-PD-105 |
| Eighth Floor C Wing Plumbing Demolition Plan |
| 1-PD-106 |
| Eighth Floor C Wing Medical Gas Demolition Plan |
| 1-PP-101 |
| Fifth Floor D Wing Plumbing Plan |
| 1-PP-102 |
| Sixth Floor D Wing Waste and Vent Plan |
| 1-PP-103 |
| Sixth Floor D Wing Domestic Water Plan |
| 1-PP-104 |
| Sixth Floor D Wing Medical Gas Plan |
| 1-PP-105 |
| Seventh Floor C Wing Plumbing Plan |
| 1-PP-106 |
| Seventh Floor D Wing Plumbing Plan |
| 1-PP-107 |
| Eighth Floor C Wing Waste and Vent Plan |
| 1-PP-108 |
| Eighth Floor C Wing Domestic Water Plan |
| 1-P-901 |
| Sixth Floor D Wing Waste, Vent and Storm Isometric |
| 1-P-902 |
| Sixth Floor D Wing Domestic Water Isometric |
| 1-P-903 |
| Eighth Floor C Wing Waste, Vent and Storm Isometric |
| 1-P-904 |
| Eighth Floor C Wing Domestic Water Isometric |
Electrical
| 1-E-001 |
| Electrical, Symbols and Abbreviations |
| 1-ED-101 |
| Sixth Floor Electrical Demolition Plan |
| 1-ED-102 |
| Sixth Floor Lighting Demolition Plan |
1-ED-103
Sixth Floor Electrical Demolition Above Ceiling Conduit Plan
| 1-ED-104 |
| Sixth Floor Technology Demolition Plan |
| 1-ED-105 |
| Eighth Floor Electrical Demolition Plan |
| 1-ED-106 |
| Eighth Floor Lighting Demolition Plan |
1-ED-107
Eighth Floor Electrical Demolition Above Ceiling Conduit Plan
| 1-ED-108 |
| Eighth Floor Technology Demolition Plan |
| 1-EP-101 |
| Sixth Floor Power Plan |
| 1-EP-102 |
| Eighth Floor Power Plan |
| 1-EM-101 |
| Sixth Floor Mechanical Power Plan |
| 1-ME-102 |
| Eighth Floor Mechanical Power Plan |
| 1-ME-103 |
| D Wing Roof Mechanical Power Plan |
| 1-ET-101 |
| Sixth Floor Technology Systems Plan |
| 1-ET-102 |
| Eighth Floor Technology Systems Plan |
| 1-EL-101 |
| Sixth Floor Lighting Plan |
| 1-EL-102 |
| Eighth Floor Lighting Plan |
| 1-E-401 |
| Enlarged Plan Enlargements |
| 1-E-501 |
| Electrical Details |
| 1-E-502 |
| Electrical Details |
| 1-E-503 |
| Electrical Details |
| 1-E-601 |
| Electrical Single-Line Diagram and Equipment Schedule |
| 1-E-602 |
| Electrical Panel Schedules |
| 1-E-603 |
| Electrical Panel Schedules |
| 1-E-604 |
| Electrical Panel Schedules |
| 1-F-101 |
| Sixth Floor Fire Alarm & Life Safety Demolition Plan |
| 1-F-102 |
| Eighth Floor Fire Alarm Life Safety Demolition Plan |
| 1-FA-101 |
| Sixth Floor Fire Alarm Life Safety Plan |
| 1-FA-102 |
| Eighth Floor Fire Alarm Life Safety Plan |
- - - E N D - - -
SECTION 01 00 00 GENERAL REQUIREMENTS
TABLE OF CONTENTS
| 1.1 SAFETY REQUIREMENTS | 1 |
| 1.2 GENERAL INTENTION | 1 |
| 1.3 STATEMENT OF BID ITEM(S) | 1 |
| 1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR | 3 |
| 1.5 CONSTRUCTION SECURITY REQUIREMENTS | 3 |
| 1.6 OPERATIONS AND STORAGE AREAS | 6 |
| 1.7 ALTERATIONS | 6 |
| 1.8 DISPOSAL AND RETENTION | 6 |
| 1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS | 10 |
| 1.10 RESTORATION | 12 |
| 1.11 PHYSICAL DATA | 13 |
| 1.12 PROFESSIONAL SURVEYING SERVICES | 14 |
| 1.13 LAYOUT OF WORK | 14 |
| 1.14 AS-BUILT DRAWINGS | 15 |
| 1.15 USE OF ROADWAYS | 16 |
| 1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT | 16 |
| 1.17 TEMPORARY USE OF NEW ELEVATORS | 17 |
| 1.18 TEMPORARY USE OF EXISTING ELEVATORS | 17 |
| 1.19 TEMPORARY TOILETS | 19 |
| 1.20 AVAILABILITY AND USE OF UTILITY SERVICES | 20 |
| 1.21 TESTS | 21 |
i Expand Specialty Care - Building 1 Renovate 6th Floor
D-Wing May 10, Project #
583-331
| 1.22 INSTRUCTIONS | 22 |
| 1.23 GOVERNMENT-FURNISHED PROPERTY | 23 |
| 1.24 RELOCATED EQUIPMENT AND ITEMS | 24 |
| 1.25 CONSTRUCTION SIGN | 25 |
| 1.26 SAFETY SIGN | 25 |
| 1.27 PHOTOGRAPHIC DOCUMENTATION | 26 |
| 1.28 FINAL ELEVATION DIGITAL IMAGES | 29 |
ii
Expand Specialty Care - Building 1 Renovate 6th Floor
D-Wing May 10, Project #
583-331
SECTION 01 00 00 GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations and furnish labor, materials, supervision and equipment to perform work for New Building 5 and work for Renovation of Building 1 and 6th Floor of D- Wing including demolition and removal of existing interiors, as required by drawings and specifications.
B. Visits to the site by Bidders shall be in accordance with the Site Visit provision (52.236-27) of the solicitation.
C. Offices of American Structurepoint and Apogee Consulting Group, as Architect-Engineers, shall render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by the Contractor, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 PROPOSAL INSTRUCTIONS
An offeror that wishes to submit a proposal for Expand Specialty Care Clinic must propose on base Item 1 (Item 0001) and 2-9 (ALT Items 0002-0009). A single award will be made on Item No. I (Base Proposal), but in the event the offer exceeds the funds available, a single award will be made on ALT Item 0002 or Item 0003, or Item 0004, or Item 0005, or Item 0006, or Item 0007, or Item 0008, or Item 0009, in that order, based on available funding. Offerors’ proposals that do not submit pricing on each and every item will be rendered technically unacceptable and will not be eligible for award.
SCHEDULE
Project: Expand Specialty Care Clinic Project Contractor: _______________________________
SCHEDULE OF ITEM(S)
ITEM 0001, BASE PROPOSAL: Furnish all labor, materials, equipment, tools, supervision, and all other necessary resources to construct a new Building 5 and to renovate Building 1, 6th Floor D-Wing. The new Building 5 shall be accepted by the VA for beneficial use and occupancy before the renovation of Building 1,6th Floor, D-Wing can begin;
1. Completion time for the new Building 5 is 480 calendar days after receipt of the Notice to Proceed.
2. Contractor shall allow 21 calendar days for the VA to completely vacate Building 1, 6th Floor, D-Wing once the new Building 5 has been accepted by the VA for beneficial use and occupancy.
3. Completion time for renovation of Building 1, 6th Floor, D-Wing is 365 calendar days after receipt of the Notice to Proceed.
4. Total completion time for the base bid is 866 calendar days from receipt of the Notice to Proceed
B. ITEM 0002 ALT No. 1: Perform all work in Bid Item 1, except DELETE the custom frit pattern as detailed on Glazing Type 3 for Building 5. Completion time for new Building 5 is decreased from 480 to 450 calendar days after receipt of the Notice to Proceed.
C. ITEM 0003 ALT No. 2: Perform all work in Bid Item 2 except DELETE vertical fins located on curtain walls 1 and 2 for Building 5. Completion time for new Building 5 is 435 calendar days after Notice to Proceed.
D. ITEM 0004 ALT No. 3: Perform all work in Bid Item 3, except DELETE high-impact beveled wall panels for Building 5. Completion time for new Building 5 is 415 calendar days after receipt of Notice to Proceed.
E. ITEM 0005 ALT No. 4: Perform all work in Bid Item 4, except DELETE the concrete topping slab as indicated on the structural sheets for Building 5. Completion time for new Building 5 is 400 calendar days after Notice to Proceed.
F. ITEM 0006 ALT No. 5: Perform all work in Bid Item 5, except DELETE the demountable partition system and install interior aluminum storefront with standard swing doors with acoustical gaskets. Coordinate door hardware requirements to be equivalent to the items as specified in the base bid. All window films to be applied on storefront glazing in pattern as indicated on the base bid. Modify any televisions shown on demountable partitions drawings to be ceiling hung at the same finish elevation as shown on the drawings. Modify associated electrical work to facilitate a ceiling mounted application. Completion time for new Building 5 is 375 calendar days after Notice to Proceed.
G. ITEM 0007 ALT No. 6: Perform all work in Bid Item 6, except REMOVE all perennial/ornamental grass landscape beds and replace with sod. Completion time for new Building 5 is 365 calendar days after Notice to Proceed.
H. ITEM 0008 ALT No. 7: Perform all work in Bid Item 7, except DELETE CCTV (cameras, file servers, switches and NVR) for Building 5. Completion time for new Building 5 is 335 calendar days after Notice to Proceed.
I. ITEM 0009 ALT No. 8: Perform all work in Bid Item 8, except DELETE the renovation of Building 1 – 6th Floor, D-Wing. Completion time for new Building 5 is 335 calendar days after notice to proceed.
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. After award, no specifications and drawings shall be furnished to the contractor. Contract drawings and specifications can be downloaded by the contractor at www.fbo.gov . Hard copies shall be at the contractor’s expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that shall remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub- contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
| 1. General Contractor’s employees shall not enter the project site without appropriate badge. | They shall also be subject to inspection of their personal effects when entering or leaving the project site. Contractor shall complete and submit ID badge submission forms. | | |
| 2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. | This notice is separate from any notices required for utility shutdown described later in this section. | For working outside the “regular hours” as defined in the contract, The General Contractor shall give three (3) days’ notice to the COR for review. | This notice is separate from any notices required for utility shutdown described later in this section. |
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
Expand Specialty Care – Building 1 Renovate 6th Floor
D-Wing May 10, Project #
583-331
01 00 00
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor shall return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”. The VA definition of “sensitive information” from VA Handbook 6500.6 dated 3/12/10:
a. Sensitive Information - VA sensitive information is all Department data, on any storage media or in any form or format, which requires protection due to the risk of harm that could result from inadvertent or deliberate disclosure, alteration, or destruction of the information. The term includes information whose improper use or disclosure could adversely affect the ability of an agency to accomplish its mission, proprietary information, records about individuals requiring protection under various confidentiality provisions such as the Privacy Act and the HIPAA Privacy rule, and information that can be withheld under the Freedom of Information Act. Examples of VA sensitive information include the following: individually-identifiable medical, benefits, and personnel information; financial, budgetary, research, quality assurance; confidential commercial, critical infrastructure, investigatory, and law enforcement information; information that is confidential and privileged in litigation such as information protected by the deliberative process privilege, attorney work-product privilege, and the attorney client privilege; and other information which, if released, could result in violation of law or harm or unfairness to any individual or group, or could adversely affect the national interest or the conduct of federal programs.
| 2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. | This information shall be shared only with those with a specific need to accomplish the project. | |
| 3. Certain documents, sketches, videos or photographs and drawings shall be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”. | Secure such information in separate containers and limit the access to only those who need it for the project. | Return the information to the Contracting Officer upon request. |
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.
b. “Sensitive information” including drawings and other documents shall be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only.
a. Only one (1) permit shall be issued, upon request, for the General Contractor and its employees for parking in designated areas only. All others shall park offsite. Use of VA offsite parking and shuttle services by the Contractor is allowed.
1.6 OPERATIONS AND STORAGE AREAS
A. Working space and space available for storing materials shall be within the limits of the construction areas.
B. Workmen are subject to rules of Medical Center applicable to their conduct.
C. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
D. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment shall be permitted subject to fire and safety requirements.
F. Phasing:
1. Building 5 shall be completed first; ready for occupancy.
2. The work on both floors in Building 1 shall be done concurrently and no phasing is planned for this project. The Medical Center shall maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service shall be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.
To insure such executions, Contractor shall furnish the COR with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of building or portion thereof. Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to Medical Center Director, COR and Contractor.
G. Parts of Building 1 to be renovated shall be vacated by Medical Center, beginning immediately after date of receipt of Notice to Proceed, and turned over to Contractor.
Building 1 shall be occupied during performance of work; but immediate areas of alterations shall be vacated.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Center’s operations shall not be hindered. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations shall continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding Subparagraph 1 shall be temporarily vacated while alterations are performed.
H. When a portion of a building is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. The existing sprinkler system shall be removed during demolition for this project. Remove smoke detectors from the existing fire alarm system to prevent false alarms and connect heat detectors at the deck throughout the area of renovation. The heat detectors shall be tied into the existing fire alarm system; coordinate with the VA’s fire alarm contractor. A fire inspection shall be required at least two times daily. Contractor shall coordinate with VA Chiller Plant Operator to provide an evening (off-hours) inspection. In addition, combustible material shall not be allowed to be stored in the construction areas.
I. Utilities Services: Maintain existing utility services for Medical Center Building 1 at all times. Provide labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, and cables of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
2. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems shall be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS.
3. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
4. Contractor shall be advised (in writing) of approval of request, or of which other date and/or time such interruption shall cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center can occur at other than Contractor's normal working hours.
5. Major interruptions of any system shall be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
6. In case of a contract construction emergency, service shall be interrupted on approval of COR. Such approval shall be confirmed in writing as soon as practical.
J. Existing Building No. 5 shall be occupied during performance of work.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment, building and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Center’s operations shall not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel through construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces and lighting to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations shall continue during the construction period.
K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane shall be open to traffic at all times with approval.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances shall be approved by the COR.
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
01 00 00
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, and shades, required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by the Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which shall be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract shall be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR 852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, shall form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused shall be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS A. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, and walks) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, and cables, of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown shall be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).
1.11 PHYSICAL DATA
A. Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Cardno ATC.
B. A copy of the soil report has been attached as Appendix A and shall be considered part of the contract documents.
C. Government does not guarantee that other materials could not be encountered nor that proportions, conditions or character of several materials could not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of Veterans Affairs, bidders shall be permitted to make subsurface explorations of their own at site.
1.12 PROFESSIONAL SURVEYING SERVICES
A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.
1.13 LAYOUT OF WORK
A. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, and parking lots are in accordance with lines and elevations shown on contract drawings.
B. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as shall be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
C. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.
1. Lines of each building and/or addition.
2. Elevations of bottoms of footings and tops of floors of each building and/or addition.
3. Lines and elevations of sewers and of all outside distribution systems.
5. Lines of elevations of all swales and interment areas.
6. Lines and elevations of roads, streets and parking lots.
D. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
E. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work, including burial monuments and fifty foot stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
F. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying Services".
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which shall be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.15 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they shall be protected by well-constructed bridges.
B. When new permanent roads are a part of this contract, Contractor shall construct them immediately for use to facilitate building operations. These roads shall be used by all who have business thereon within zone of building operations.
C. When certain buildings (or parts of certain buildings) are required to be completed in advance of general date of completion, all roads leading thereto shall be completed and available for use at time set for completion of such buildings or parts thereof.
1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power shall be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system shall be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR shall withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned. Vibrations shall be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use shall be repaired replaced by the contractor at the contractor’s expense.
1.17 TEMPORARY USE OF NEW ELEVATORS
A. The Contractor and his personnel shall be permitted use of new elevator(s) subject to the following provisions:
1. Contractor shall make arrangements with the COR for use of elevator(s). Contractor shall obtain elevator(s) for exclusive use.
2. Prior to the use of elevator(s), the Contractor shall have the elevator(s) inspected and accepted by an ASME accredited, certified elevator safety inspector. The acceptance report shall be submitted to the COR.
3. Submit to the COR the schedule and procedures for maintaining equipment. Indicate the day or days of the week and total hours required for maintenance. A report shall be submitted to the COR monthly indicating the type of maintenance conducted, hours used, and any repairs made to the elevator(s).
4. The Contractor shall be responsible for enforcing the maintenance procedures as per VA and manufacturers recommendations and requirements.
5. During temporary use of elevator(s) all repairs, equipment replacement and cost of maintenance shall be the responsibility of the Contractor.
6. Personnel for operating elevator(s) shall not be provided by the Department of Veterans Affairs.
7. Contractor shall cover and provide maximum protection of the entire elevator(s) installation.
8. The Contractor shall arrange for the elevator company to perform operation of the elevator(s) so that an ASME accredited, certified elevator safety inspector can evaluate the equipment. The Contractor shall be responsible for any costs of the elevator company.
9. All elevator(s) parts worn or damaged during temporary use shall be removed and replaced with new parts at the contractor’s expense.
This is the start of the file's text. The full file is on GovTribe.