Special_Provision.pdf
PDF 136 KB Posted
- Attached to
- Large Valve Vault Replacement
- Solicitation number
- 107595
- Issued by
- Montgomery County, Maryland
About this file
This is a Special Provisions document issued by the Washington Suburban Sanitary Commission (WSSC) Water in Maryland, providing technical guidance for water main replacement projects. The document addresses procedures for handling existing Lead Service Lines (LSL), Galvanized Requiring Replacement (GRR) service lines, and unknown material service lines encountered during water main replacement work in the public right of way. The related contract opportunity involves replacement of approximately 87 feet of 30-inch water main, 48 feet of 72-inch water main, and one 30-inch valve and vault in the Silver Spring area of Montgomery County, Maryland, with sealed responses due by 2:00 pm on Wednesday, July 22, 2026, via WSSC's eProcurement Portal.
The Special Provisions establish mandatory coordination requirements between the contractor and the WSSC Contract Manager prior to construction commencement, particularly when construction will impact homes with known LSL, GRR, or unknown service line materials. The contractor must immediately cease work and notify the WSSC Contract Manager if LSL or GRR materials are unexpectedly encountered during construction, pending verification of pipe material and coordination of service line replacement before water main construction can resume. These provisions ensure proper handling of lead service line issues in compliance with public health and safety requirements during infrastructure replacement activities.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SP-01500-1
SPECIAL PROVISIONS
SECTION 01500
TEMPORARY FACILITIES AND CONTROLS
Follow requirements of Standard Specifications Section 01500 except as specified herein.
PART 1 GENERAL
1.4 PROJECT SIGNS
B. Water Main Replacements, Relocations and Cleaning and Lining Contracts.
ADD
5. Provide at:
a. 1200 W. University Boulevard
SP-02514 April 2024
SPECIAL PROVISION
SECTION 02514
WATER MAIN REPLACEMENT WITH EXISTING LEAD,GRR OR UNKNOWN SERVICE LINE
PART 1 GENERAL
1.1 INTENT
A. It is the intent of this section to provide guidance in the event existing Lead Service Line (LSL), Galvanized Requiring Replacement (GRR) or unknown material service are encountered during watermain replacement located in the public Right of Way.
B. Commission records available may not confirm the presence of LSL,GRR service line within the project limits.
1.2 DESCRIPTION
A. The Contractor shall coordinate with WSSC Contract Manager before the construction begins.
If the construction is known to impact any homes with LSL, Galvanized Requiring Replacement (GRR), or homes with unknown service line material, construction shall not begin until WSSC notifies customers and verifies pipe material and/or coordinates for replacement of the service line prior to water main construction.
B. If the Contractor unexpectedly encounters an LSL or GRR during construction, the Contractor shall immediately cease further activities on the service line and report to WSSC Contract Manager on additional actions before construction resumes.