This is a Corrosion Condition Assessment Report submitted by DACCO SCI, INC. to The Wilson T. Ballard Company on behalf of the Washington Suburban Sanitary Commission (WSSC) in Maryland. The report documents initial field observations for two large valve vault replacement projects in Silver Spring, Montgomery County, Maryland: Project BT7370A22 located at 1200 W University Boulevard (30-inch diameter relocation) and Project BT7373A22 located at 12501 Old Columbia Pike (24-inch diameter retrofit). The assessment was conducted using the WSSC Corrosion Survey Checklist and was completed on February 15, 2023. No stray current sources were identified in the areas surrounding either valve vault replacement.

DACCO SCI, INC. determined that soil corrosivity testing is required for BT7370A22 due to the 30-inch pipe diameter, with design recommendations to be provided in a preliminary report following completion of testing and analysis. For BT7373A22, no recommendations were issued as it is expected to be a retrofit with no new pipe installation outside the valve vault; however, if pipe replacement becomes necessary outside the vault, the report recommends using zinc-coated ductile iron pipe with V-BIO encasement and field coating of connections to existing ductile iron pipe for five feet on either side. Testing may not be required at BT7373A22 due to its retrofit nature.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVISED REPORT

INITIAL FIELD OBSERVATIONS

CORROSION CONDITION ASSESSMENT

LARGE VALVE VAULT REPLACEMENT

WSSC JOB NO. BT7370A22 AND BT7373A22

Submitted by

Chester Dacres

DACCO SCI, INC.

10260 Old Columbia Road Suite A1

Columbia, Maryland 21046

Submitted to

Jeffrey Ziegenfuss The Wilson T. Ballard Company

17 Gwynns Mill Court Owings Mills, Maryland 21117

February 15, 2023

DSI-WTBCO-2275

DACCO SCI, INC.

CORROSION ENGINEERING - MATERIALS TECHNOLOGY - ELECTROCHEMISTRY

10260 OLD COLUMBIA ROAD, SUITE A1, COLUMBIA, MARYLAND 21046

BALT. (410) 381-9475 • DC (301) 596-7019 • FAX (410) 381-9643

dacres@daccosci.com www.daccosci.com

DSI

February 15, 2023

Jeffrey Ziegenfuss, P.E.

Vice President The Wilson T. Ballard Company 17 Gwynns Mill Court Owings Mills, Maryland 21117

RE: REVISED – INITIAL FIELD OBSERVATIONS – CORROSION

CONDITION ASSESSMENT OF THE LARGE VALVE VAULT

REPLACEMENT - WSSC JOB NOS. BT7370A22 AND BT7373A22

Dear Mr. Ziegenfuss:

DACCO SCI, INC. has completed the initial field observations using the WSSC Corrosion Survey Checklist for the corrosion assessment of the BT7370A22 and BT7373A22 Valve Vault Replacements.

No stray current source was identified in the area around either valve vault replacement. Soil corrosivity testing is required to be conducted at BT7370A22 because the proposed replacement is 30-inches in diameter.

BT7373A22 is expected to be a retrofit with no new pipe being installed outside the valve vault.

As a result, DACCO SCI, INC. had no recommendations for the proposed replacement.

Recommendations for the design of BT7370A22 will be provided after the completion of soil corrosivity testing and included in the Preliminary Report.

If there are any questions or revisions to the report, please do not hesitate to contact me.

Sincerely, Chester Dacres, Ph.D., P.E.

President

CMD/ng mailto:dacres@daccosci.com

• DACCO SCI, INC. • 10260 Old Columbia Road, Suite A1, Columbia, MD 21046 • (410) 381-9475 • DSI-WTBCO-2275 www.daccosci.com 2/15/2023

TABLE OF CONTENTS

EXECUTIVE SUMMARY

Location of Project

RECOMMENDATIONS

CORROSION SURVEY CHECKLIST

DSI-WTBCO-2275 www.daccosci.com 2/15/2023

EXECUTIVE SUMMARY

Location of Project

Table 1 below summarizes the Large Valve Vault (LVV) replacement project. Figure 1 and Figure 2 show the alignment of BT7370A22 and BT7373A22, respectively.

Table 1 – Summary of the Valve Vault Replacements

Project No. Location Size (inch)

Retrofit/Relocation

BT7370A22 1200 W University Blvd, Silver Spring, Montgomery County, Maryland

30 Relocation

BT7373A22 12501 Old Columbia Pike, Silver Spring, Montgomery County, Maryland

24 Retrofit

Figure 1 – Map of the BT7370A22 LVVR

DSI-WTBCO-2275 www.daccosci.com 2/15/2023

Figure 2 – Map of the BT7373A22 LVVR

Soil corrosivity testing should be conducted at BT7370A22 because the proposed replacement is 30-inches in diameter. Testing may not be required at BT7373A22 because it is expected to be a retrofit.

RECOMMENDATIONS

DACCO SCI, INC. recommends that:

1. MV7370A22: The design of the proposed valve vault replacement will be provided after the completion of soil corrosivity testing and included in the Preliminary Report.

2. MV7373A22: No recommendations are applicable. No pipe replacement is expected outside of the proposed valve vault. If pipe replacement is required outside of the valve vault, design using zinc-coated ductile iron pipe (DIP) with V-BIO encasement.

Additionally, connections to existing DIP should be field coated five (5)-feet on either side of the connection and V-BIO encased.

The WSSC Corrosion Survey Checklist is shown below.

CORROSION SURVEY CHECKLIST

a) Existing Pipe Analysis: (all pipe sizes, list only the pipe sizes to be replaced/relocated).

b) Identify Sources of Stray Currents (crossing, parallel or within 2000 feet).

c) Additional Corrosion Considerations.

d) Field Soil And Groundwater Testing Requirements for All Ductile Iron Pipelines 16-inch and Larger.

(See Appendix "E" for Specific Testing Requirements; submit with second submittal).

Noah Typewritten Text Noah Geier

Noah Typewritten Text Corrosion Engineer

Noah Typewritten Text 11/28/22

Noah Typewritten Text

DACCO SCI, INC.

Noah Typewritten Text

BT7370A22

Noah Typewritten Text W University Blvd

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text Large Valve Vault

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text Unknown

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text 24, 30-inch

Noah Typewritten Text X

Noah Typewritten Text To be determined after testing completed and results analyzed

CORROSION SURVEY CHECKLIST

a) Existing Pipe Analysis: (all pipe sizes, list only the pipe sizes to be replaced/relocated).

b) Identify Sources of Stray Currents (crossing, parallel or within 2000 feet).

c) Additional Corrosion Considerations.

d) Field Soil And Groundwater Testing Requirements for All Ductile Iron Pipelines 16-inch and Larger.

(See Appendix "E" for Specific Testing Requirements; submit with second submittal).

Noah Typewritten Text Noah Geier

Noah Typewritten Text Corrosion Engineer

Noah Typewritten Text 11/28/22

Noah Typewritten Text

DACCO SCI, INC.

Noah Typewritten Text 24-inch

Noah Typewritten Text X

Noah Typewritten Text Large Valve Vault

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text Unknown

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text X

Noah Typewritten Text Old Columbia Pike

Noah Typewritten Text

BT7373A22

Noah Typewritten Text Field coat five (5)-feet on each side of the connection with V-BIO encasement

EXECUTIVE SUMMARY
Location of Project
RECOMMENDATIONS
Corrosion Survey Checklist

File details come from the government source that posted it. Updated .