This is a Cathodic Protection System Design Report prepared by DACCO SCI, INC. for the Washington Suburban Sanitary Commission (WSSC) Large Valve Vault Replacement Project (BT7370A22) located in Silver Spring, Montgomery County, Maryland. The project involves replacement of approximately 87 feet of 30-inch ductile iron pipe (DIP) and 48 feet of 72-inch steel water main, with connections to existing prestressed concrete cylinder pipes. The design specifies installation of PRITEC-coated pipe, five insulating joints to ensure electrical isolation, and five test stations to monitor system effectiveness. The cathodic protection system design includes three zinc anode beds (GA-S-30, 30-pound each) for the 72-inch steel main and two zinc anode beds for the 30-inch DIP main, with a design life of 30 years. The report was submitted on June 7, 2024, by Chester Dacres, Ph.D., P.E., President of DACCO SCI, INC., to Daniel Savage at The Wilson T. Ballard Company.
The estimated total cost for the galvanic cathodic protection system (GCPS) is $42,468.42, including material costs of $22,988.74 and installation labor costs of $10,986.00, with a 25 percent contractor markup applied. Materials include five zinc anodes, five test stations with Cu-CuSO4 reference electrodes, thermite weld metal and molds, HMWPE and THWN cables, five insulating joints (three 30-inch and two 72-inch), and testing and reporting. The construction timeline estimates 20 total days for completion, with concurrent installation of cathodic protection components and main construction activities, including 5 days for test station installation, 5 days for anode bed installation, 5 days for insulating joint installation, 3 days for wire bond connections, and 2 days for contingencies.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REPORT
CATHODIC PROTECTION SYSTEM DESIGN
LARGE VALVE VAULT REPLACEMENT
WSSC JOB NO. BT7370A22
Submitted by
Chester Dacres
DACCO SCI, INC.
10260 Old Columbia Road, Suite A1
Columbia, Maryland 21046
Submitted to
Daniel Savage
The Wilson T. Ballard Company
17 Gwynns Mill Court
Owings Mills, Maryland 21117
June 7, 2024
DSI-WTBCO-2424
DACCO SCI, INC.
CORROSION ENGINEERING - MATERIALS TECHNOLOGY - ELECTROCHEMISTRY
10260 OLD COLUMBIA ROAD, SUITE A1, COLUMBIA, MARYLAND 21046
BALT. (410) 381-9475 • DC (301) 596-7019 • FAX (410) 381-9643
dacres@daccosci.com www.daccosci.com
DSI
June 7, 2024
Daniel Savage
Design Engineer
The Wilson T. Ballard Company
17 Gwynns Mill Court
Owings Mills, Maryland 21117
RE: CATHODIC PROTECTION SYSTEM DESIGN – LARGE VALVE VAULT
REPLACEMENT - WSSC JOB NOS. BT7370A22
Dear Mr. Savage:
DACCO SCI, INC. was tasked to design a cathodic protection system for the BT7370A22 Large
Valve Vault Replacement (LVVR) Project with a design life of 30 years, to be constructed under
WSSC Job No. BT7370A22.
DACCO SCI, INC., recommends installing PRITEC (or equivalent) coating and a zinc galvanic cathodic protection system (GCPS) with five (5) insulating joints and five (5) test stations.
The proposed GCPS will be completed at an estimated cost of $42,397.32. The design calculations, cost, and time estimates are included in this report.
If there are any questions or revisions to the report, please do not hesitate to contact me.
Sincerely, Chester Dacres, Ph.D., P.E.
President
CMD/nb mailto:dacres@daccosci.com
• DACCO SCI, INC. • 10260 Old Columbia Road, Suite A1, Columbia, MD 21046 • (410) 381-9475 •
DSI-WTBCO-2424 www.daccosci.com 6/7/2024
TABLE OF CONTENTS
EXECUTIVE SUMMARY
Location of Project
RECOMMENDATIONS
CATHODIC PROTECTION SYSTEM DESIGN PROCEDURE
Current Requirement Calculations
Size and Location of Anodes
DESIGN CALCULATIONS AND COST ESTIMATES
Engineers Construction Cost and Completion Time Estimate
EXECUTIVE SUMMARY
Location of Project
DACCO SCI, INC. designed a galvanic cathodic protection system for the BT7370A22 LVVR project. The proposed LVVR contains approximately 48-feet of 72-inch diameter Steel pipe and
87-feet of 30-inch ductile iron pipe (DIP) located in Silver Spring, Montgomery County, Maryland. The proposed replacement will connect to existing prestressed concrete cylinder pipes built under Contract Nos. 1961-5411 (30-inch) and 1966-2621J (72-inch). The project location is shown below in Figure 1.
Figure 1 – Map of the BT7370A22 LVVR
Proposed
BT7370A22 Vault
SB-01
RECOMMENDATIONS
DACCO SCI, INC. recommends, a galvanic cathodic protection system with a design life of 30 years. The system should be in accordance with WSSC Specifications 02510 and 13110 that include:
1. 72-inch Steel Water Main:
a. Design using PRITEC (or equivalent) coated steel pipe.
b. Follow WSSC Standard Detail C/3.3 and C/3.4. Install an insulating joint (IJ) between the proposed steel and existing prestressed concrete cylinder pipe
(PCCP) to ensure electrical isolation of the alignment. Field coat the connection for five (5)-feet of the new side of the connection.
c. Follow WSSC Standard Detail C/3.0. Install an IJ between the proposed Steel
72x30-inch outlet and the proposed 30-inch DIP to ensure electrical isolation of the alignment. Field coat the connection for five (5)-feet of each side of the connection.
d. Install a pole mounted “insulating joint with anodes” (“IJ w/A”) type test station to each insulating joint to monitor the effectiveness of the new insulating joints and cathodic protection system for a total of three (3) “IJ w/A” test stations.
e. Install a GCPS system consisting of one (1) 30-pound GA-S-30 zinc anodes (or equivalent) attached to each test station for a total of three (3) beds of one (1) zinc anode.
2. 30-inch Ductile Iron Water Main:
a. Design using PRITEC (or equivalent) coated DIP.
b. Externally bond pipe segments to ensure electrical continuity.
c. Follow WSSC Standard Detail C/3.3 and C/3.4. Install an IJ between the proposed DIP and existing PCCP to ensure electrical isolation of the alignment.
Field coat the connection for five (5)-feet of the new side of the connection.
d. Install a flush mounted “IJ w/A” type test station to each insulating joint to monitor the effectiveness of the new insulating joints and cathodic protection system for a total of two (2) “IJ w/A” test stations.
e. Install a GCPS system consisting of one (1) 30-pound GA-S-30 zinc anodes (or equivalent) attached to each test station for a total of two (2) beds of one (1) zinc anode.
f. Bond around the vault per WSSC Standard Detail C/1.3.
Table 1 below shows the location of all new insulating joint test stations and anode beds.
Table 1 - Test Station Schedule for BTBR7370A22
ANODES
DRAWING
TEST
STATION
NUMBER
TEST
STATION
LOCATION
PIPE
SIZE
(IN)
TEST
STATION
TYPE NUMBER
SIZE
(LB) MATERIAL STATION NUMBER
CP 1 TBD
72-in STEEL X PCCP 72 IJ w/A
1 30 ZINC
0+00 72IN
CP 1 TBD
72-in STEEL X PCCP 72 IJ w/A
1 30 ZINC
0+48 72IN
CP 1 TBD
30-in DIP X PCCP 30 IJ w/A
1 30 ZINC
0+00 30IN
CP 1 TBD
30-in DIP X STEEL 30 IJ w/A
1 30 ZINC
0+35 30IN, LEFT 0+34 30IN
CP 1 TBD
30-in DIP X PCCP 30 IJ w/A
1 30 ZINC
0+48 30IN
*TBD – To be determined
**IJ w/A – Insulating Joint (IJ) with Anodes
CATHODIC PROTECTION SYSTEM DESIGN PROCEDURE
The cathodic protection design has followed specified American Society of Metals (ASM) guidelines0F
1 and examples from the American Iron and Steel Institute publication. 1F
2 Design procedures vary among organizations, but DACCO SCI, INC. is observing the following general guidelines based on the Association for Materials protection and Performance (AMPP, formerly
NACE) practices.3
1. Determination regarding whether impressed current or sacrificial anodes will be used;
2. Determination regarding the design life of the system;
3. Calculation of the maximum electric current required;
4. Determination of the number and type of anodes required and their respective spacing;
5. Calculation of the lead wire size; and
6. Determination of the location of the anodes.
1 Robert H. Heidersbach, "Cathodic Protection" reprinted in Metals Handbook: Ninth Edition, Volume 13
Corrosion, ASM International, 1987, pp. 470-477.
2 "Handbook of Corrosion Protection For Steel Pile Structures In Marine Environments", 1st edition, American Iron and Steel Institute, 1981.
3 "CP 3-Cathodic Protection Technologist COURSE MANUAL", Version 1.0, NACE International, 2014.
Current Requirement Calculations
Current requirements are calculated by determining the amount of ductile iron exposed to a corrosive environment. The pipelines for Contract No. BT7370A22 are assumed to be 98% coated.
The calculation of the current required to maintain cathodic protection is based on the following:
1. Determine the type of anode material to use as sacrificial anode anodes.
2. Calculate the current required to maintain protection of the coated ductile iron pipe for 30 years.
Size and Location of Anodes
The following three (3) factors were taken into consideration in designing the size of the anodes:
1. Total current requirement
2. Designed life of anodes
3. Soil resistivity
The total weight of anode material required to maintain protection of the pipe is dependent on the following:
1. Consumption rate of the anode material
2. Efficiency factor of the anode material
3. Utilization factor of the anode material
4. The average total current to protect the pipe
5. Design life (specified as 30 years)
After the total weight of the anode material was determined, the anode resistance was calculated.
DESIGN CALCULATIONS AND COST ESTIMATES
Table 3 and Table 2 display the results of the galvanic anode cathodic protection system design calculations.
Table 2 - Cathodic protection calculations for the 72-inch Steel
Nominal Pipe Diameter: 72 in
Pipe Outer Diameter: 72 in
Length: 48 ft
Design Life: 30 yrs
Total: 905 ft2
Coated: 887 ft2
Uncoated: 18 ft2
Current Required: 0.04 A
Anode
Type
Working
Potential
(Volts)
Efficiency
Factor
Util ization
Factor
Anode
Weight*
(lbs)
GA-S-30 -1.10 90% 0.85 35
* Based on Current Requirement Analysis.
Input
Anode Type: GA-S-30
Number of Anodes Used (N): 3
Anode Mass (Each): 30 lbs
Anode Length (L ): 5.00 ft
Anode Diameter (d ): 1.58 in
Anode Consumption Rate (CR ): 24.70 lbs / A · yr
Center-to-Center Spacing (S ): 7 ft
Anode Working Potential: -1.10 V (vs Cu/CuSO4)
Structure Potential: -0.850 V (vs Cu/CuSO4)
Soil Resistivity (r): 5,121 Ohm · cm
Output
Total Anode System Mass: 90 lbs
Single Anode Resistance (R V): 15.91 Ohm
Anode Bed Resistance: 15.91 Ohm
Anode System Resistance (R gb): 5.31 Ohm
Current Output: 0.05 A
Anode Driving Potential: 0.25 V
Anode Consumption: 41 lbs
Anode Bed Output
CATHODIC PROTECTION CURRRENT REQUIREMENT ANALYSIS
Design Parameters
Estimated Surface Area at Time of Installation
Current Requirement Analysis
SACRIFICIAL ANODE SYSTEM CALCULATIONS
Anode Bed Requirement Analysis
Consumption
Rate
(lbs / A × yr)
24.70
Anode Bed Design
Table 3 - Cathodic protection calculations for the 30-inch DIP
Nominal Pipe Diameter: 30 in
Pipe Outer Diameter: 32 in
Length: 87 ft
Design Life: 30 yrs
Total: 729 ft2
Coated: 714 ft2
Uncoated: 15 ft2
Current Required: 0.03 A
Anode
Type
Working
Potential
(Volts)
Efficiency
Factor
Util ization
Factor
Anode
Weight*
(lbs)
GA-S-30 -1.10 90% 0.85 26
* Based on Current Requirement Analysis.
Input
Anode Type: GA-S-30
Number of Anodes Used (N): 2
Anode Mass (Each): 30 lbs
Anode Length (L ): 5.00 ft
Anode Diameter (d ): 1.58 in
Anode Consumption Rate (CR ): 24.70 lbs / A · yr
Center-to-Center Spacing (S ): 7 ft
Anode Working Potential: -1.10 V (vs Cu/CuSO4)
Structure Potential: -0.850 V (vs Cu/CuSO4)
Soil Resistivity (r): 4,700 Ohm · cm
Output
Total Anode System Mass: 60 lbs
Single Anode Resistance (R V): 14.61 Ohm
Anode Bed Resistance: 14.61 Ohm
Anode System Resistance (R gb): 7.32 Ohm
Current Output: 0.03 A
Anode Driving Potential: 0.25 V
Anode Consumption: 30 lbs
Anode Bed Output
CATHODIC PROTECTION CURRRENT REQUIREMENT ANALYSIS
Design Parameters
Estimated Surface Area at Time of Installation
Current Requirement Analysis
SACRIFICIAL ANODE SYSTEM CALCULATIONS
Anode Bed Requirement Analysis
Consumption
Rate
(lbs / A × yr)
24.70
Anode Bed Design
Engineers Construction Cost and Completion Time Estimate
Table 4 and Table 5 below display the detailed cost and time estimates for construction of the
GCPS including labor. The cathodic protection construction time estimate is expected to be accomplished concurrently (not sequentially) with construction efforts.
Table 4 – GCPS Cost Estimate
Table 5 – GCPS Time Estimate
MATERIALS INSTALLATION
UNIT COST TOTAL COST UNIT COST TOTAL COST
5 each Zinc Anodes (GA-S-30) $123.15 $615.75 $75.00 $375.00
5 each Test Stations $65.00 $325.00 $150.00 $750.00
5 each Splice Kits (#8 AWG) $11.29 $56.45 $33.00 $165.00
5 each Cu-CuSO4 Reference Electrode $133.00 $665.00 $33.00 $165.00
28 ft 24-inch #2 AWG HMWPE Jumper Bond $7.71 $215.88 $0.00 $0.00
59 ft #8 AWG HMWPE Cable $0.76 $44.84 $0.00 $0.00
100 ft #6 AWG THWN Cable $0.98 $98.00 $0.00 $0.00
100 ft #12 AWG THWN Cable $0.22 $22.00 $0.00 $0.00
3 each 20Pk Thermite Weld Metal (#2, #4 AWG) $107.46 $322.38 $440.00 $1,320.00
2 each 20Pk Thermite Weld Metal (#6, #8, #10, #12 AWG) $59.70 $119.40 $440.00 $880.00
2 each 50 Use Thermite Weld Mold (#2 AWG) $79.25 $158.50 $0.00 $0.00
1 each 50 Use Thermite Weld Mold (#6 AWG) $79.25 $79.25 $0.00 $0.00
1 each 50 Use Thermite Weld Mold (#8, #10, #12 AWG) $79.25 $79.25 $0.00 $0.00
7 each 10Pk Handicaps (#2, #4, #6 AWG) $22.20 $155.40 $0.00 $0.00
1 each 20Pk Handicaps (#8, #10, #12 AWG) $8.90 $8.90 $0.00 $0.00
10 cubic ft Concrete $5.07 $50.70 $75.00 $750.00
3 each Insulating Joint (30'') $521.78 $1,565.34 $300.00 $900.00
2 each Insulating Joint (72'') $6,787.62 $13,575.24 $300.00 $600.00
1 lot Misc. Supplies $1,000.00 $1,000.00 $0.00 $0.00
2.5 days Testing $0.00 $0.00 $500.00 $1,250.00
1 each Test Report $0.00 $0.00 $2,000.00 $2,000.00
Subtotal $19,157.28 $9,155.00
20% contingency $3,831.46 $1,831.00
Subtotal $22,988.74 $10,986.00
Cathodic Protection Cost $33,974.74
25% Contractor Markup $8,493.68
Total Cathodic Protection Cost $42,468.42
USE
QUANTITY UNIT MATERIALS ITEM
Item Quantity Days Total Days
Test station Installation 5 1.0 per TS 5
Anode Beds 5 1.0 per anode 5
IJ Installation 5 1.0 per IJ 5
Wire Bond Connections 28 0.083 per bond 3
SUBTOTAL 18
Contingencies (10%) 2
TOTAL DAYS 20