SF 30 amendment 0007.doc

DOC document 80 KB Posted

Attached to
Northeastern Regional HW Incineration Contract
Solicitation number
SP450023R0002
Issued by

About this file

This document provides an amendment to a solicitation for the Northeastern Regional Hazardous Waste Incineration Contract. The amendment gives more detailed answers to previously asked questions to provide additional clarity, revises the price schedule, and moves 10% of the quantities for certain CLINs to new CLINs at the offeror's request. The responses clarify that certain CLINs will remain priced per pound rather than container size for continuity, describe changes to the description and addition of a CLIN for non-reactive paints with isocyanates, and explain that turn-in history data provided reflects actual past volumes but not guaranteed future volumes. The amendment also explains that generators will decide which contract to use for waste disposal and task orders will initially prioritize generators with the most urgent storage needs.

View the file

Other files

File Type Posted
Attachment 01 v2 Price Schedule Northeastern Regional HW Incineration v11.29.2022.xlsx XLSX spreadsheet
SF 30 amendment 0006.doc DOC document
SF 30 amendment 0005.doc DOC document
Attachment 1 Price Schedule - Northeastern Regional HW Incineration 09292022.xlsx XLSX spreadsheet
SF 30 amendment 0004.doc DOC document
Attachment 3 Pickup Locations Non-Exhaustive.pdf PDF
Attachment 2 PWS - Northeastern Regional HW Incineration 09292022.pdf PDF
Northeastern Regional Incineration_Combo Notice Description.pdf PDF
SF 30 amendment 0003.doc DOC document
Attachment 01 Price Schedule - Northeastern Regional HW Incineration 09292022.xlsx XLSX spreadsheet
SF 30 amendment 0002.doc DOC document
SF 30 amendment 0001.doc DOC document
Attachment 04 Past Performance Information Questionnaire.pdf PDF
Northeastern Regional Incineration_Combo Notice Description.pdf PDF
Attachment 05 Wage Determination.pdf PDF
Attachment 07 KTR Work Surveillance Checklist_Placement or Removal Empty ROB or Vac Box.pdf PDF
Attachment 03 Pick Up Points.pdf PDF
Evaluation _Addenda to 52.212-2_rv1.docx DOCX document
Attachment 01 Price Schedule - Northeastern Regional HW Incineration 09292022.xlsx XLSX spreadsheet
Attachment 08 KTR Work Surveillance Checklist_Placement or Removal Empty ROB or Vac Box.pdf PDF
Instructions to Offerors _Addenda to 52.212-1.docx DOCX document
Attachment 06 KTR Work Surveillance Checklist - ICS Work.pdf PDF
Contract Terms and Conditions_Northeastern Regional Incineration.docx DOCX document
Attachment 02 PWS - Northeastern Regional HW Incineration.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

PAGE OF PAGES

1 | 3

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

4. REQUISITION/PURCHASE REQ. NO. see block 14
5. PROJECT NO. (If applicable)

6. ISSUED BY CODE

SP4500
7. ADMINISTERED BY (If other than Item 6) CODE
SP4500

DLA DISPOSITION SERVICES

DLA Acquisition, J-763

74 WASHINGTON AVENUE NORTH

BATTLE CREEK, MI 49037-3092

8.

NAME AND ADDRESS OF CONTRACTOR (NO., street,city,county,State,and ZIP Code)

X
9a. AMENDMENT OF SOLICITATION NO.

SP450023R0002

X
9b. DATED (SEE ITEM 11)

2022 October 28

10a. MODIFICATION OF CONTRACT/ORDER NO.

10b. DATED (SEE ITEM 13)

CODE:
FACILITY CODE:

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

[ X ] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [ ] is extended, [ X ] is not extended

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15 and returning __1___ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. Accounting And Appropriation Data (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b)

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor [ ] is not, [ ] is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

See Continuation Sheet

15A. NAME AND TITLE OF SIGNER (Type or print)

16A. NAME OF CONTRACTING OFFICER

Raymond Empie

15B. NAME OF CONTRACTOR/OFFEROR

BY

(Signature of person authorized to sign)

15C.DATE SIGNED
16B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C.DATE SIGNED

NSN 7540-01-152-9070 – Electronically Reproduced PerFORM (DLA) STANDARD FORM 30 REV. 10-83)

PREVIOUS EDITION UNUSABLE

Prescribed by GSA

FAR (48 CFR) 53.243

SP4500-23-R-0002

Amendment 0007:

The purpose of Amendment 0007 is to give more detailed answers to previously ask questions that DLA felt required more clarity. With this amendment it is also noted that an update/revised price schedule is being posted and shall replace the previous version. Also at the Offeror’s request, and per the DLA Response to Question #2, we moved 10% of the quantities for CLINs FL03C1-C6 to new CLINs FL13C1-C6, respectively. The CLIN description for FL03 in the Price Schedule was also changed to remove the reference to non-reactive paints with isocyanates.

Responses to Contractor Questions Pertaining to DLA Regional HW Incineration Contracts v.11/28/2022

1.

The following ‘C7” suffixed CLINs FL01C7, FL04C7, FL99C7, RX01C7, RX98C7, TX98C7, TX99C7, have the U/M as per “LB”. This offeror is requesting that these line item be priced by the container size, i.e., CLIN suffixes C1, C2, C3, C4, C5, C6 similar to the other hazardous CLINs.

DLA Response: While DLA appreciates the convenience in formulating competitive pricing for container sizes (CLIN Suffixes C1-C6) over container weights in pounds (C7), waste streams covered under the referenced CLINs remain as C7 under most of our contracts for a couple reasons. (1) Aerosols, we have learned, are more commonly priced and managed by industry on a per-pound basis in the private sector. (2) Demil-required property has been retained as per-pound pricing from the old CLIN structure mostly at Generators’ requests for continuity of tracking, although some contracts have transitioned to C1-C6 where Generators were agreeable. This may have been a missed opportunity for DLA to “force” the transition, but in the interest of time, we defaulted to C7 for Demil-required property.

Given the urgent customer demands for these contracts, DLA will not convert the seven subject CLINs to container-size pricing, as this would require the addition of up to 35 CLINs and substantially delay the solicitation process. Offerors may refer to the “18-Mo Turn-In Hx” tab/attachment in each solicitation to determine average weights per TO and container for each CLIN.

2. CLIN FL03xx should change to NEW Description in Master CLIN Catalog, Date of Publication: May 13, 2022, stating… "No isocyanates (See FL16). Use LP03 for loose packs.”; Add CLIN FL16xx to Price Schedule.

DLA Response: DLA will change the description for Base CLIN FL03 in the NE, SE, and Western regional Price Schedules to match the CLIN description for FL03 used in the Mid-America Price Schedule as follows: “Flammable Liquids/Solids/Sludges/Debris, e.g., tank sludge, lubricants, adhesives, miscellaneous debris, primarily consists of incinerable, non-fuels-blendable materials. Use LP03 for loose packs. For non-reactive paints with isocyanates, see FL16 and LP16.” Further, we will add CLIN FL16 to the NE and Western contracts. Since this CLIN has not been previously used under contracts in these regions, we will move 10% of the estimated quantities under CLINs FL03C1-C6 to CLINs FL16C1-C6, respectively.

3. Please explain the 18-Month Turn-In Hx information. Is this historical data that we may likely see, OR is this actual material that is currently in back-log storage that will be removed on this contract?

DLA Response: The “18-Month Turn-In Hx” spreadsheet reflects the actual turn-in history over the most recent 18 months for current pickup locations in the region. Some of these items have been removed, some have not, and other items have been added since the report was queried. Incineration backlog inventories for the various locations are fluid and not plausible for DLA to provide at the time of solicitation.

4. Will the Lab Packs / Loose Pack CLINs already be prepackaged? If so, we will require a complete container inventory report to be provided at time of TO. How will this be accomplished?

DLA Response: Lab Pack and Loose Pack containers will be packaged prior to turn-in and issuance of a written TO. Lab packing services are performed by the local DLA HW Contractor and require provision of a detailed inventory of containerized item(s). This inventory will be provided to the regional incineration Contractor. There are some DoD Generators who utilize their own base Contractor or are themselves authorized to perform lab packing services. They too must provide a detailed inventory IAW RCRA. Loose packs do not require a detailed inventory of containerized items, but only compatible, like items shall be packaged together. Packaging/Repackaging CLINs 6311AA-6311EE are available to Generators for use as described in PWS Section 1.2.13.

5. Will the government be REQUIRED to use this contract for disposal of ALL the future HW turned in requiring incineration?

DLA Response: No, DLA will not dictate to Generators which contract they must use for turn-in of their incinerable wastes.

6. If not a requirements contract, please explain who and, or what will decide when this Incineration Contract will be used vs the existing HW contract in place.

DLA Response: Generators will decide which contract they will use to best meet their regulatory compliance, storage space, and other requirements.

7. We have concerns that this HW Incineration contract will be used by Contractors to rid itself of the difficult / high-cost incineration items issued on its TO’s. How will a Contractor on an existing HW contract with DLA be held accountable so that this does not happen?

DLA Response: DLA has no practical means to determine whether certain waste items are manageable or unmanageable by the local DLA HW Contractor under the current nationwide incineration backlog conditions. Generators will decide which contract they will use. Use of the regional HW incineration contract does not require that the local HW Contractor first reject or decline to remove the subject items.

8. Will this be a single or multiple award contract?

DLA Response: Each of the four (4) standalone Regional HW Incineration contracts will be separately evaluated and awarded as single-award IDIQ contracts.

9. How will the DLA schedule out the volume of material once the contract is awarded to ensure that the winning bidder has the available capacity? With the high volume of waste present at the locations, we’re concerned that task orders will be cut in large volumes that will exceed the available capacity to receive the material.

DLA Response: DLA intends to initially issue Task Orders with priority given to those Generators having the most urgent needs, i.e., those facing regulatory penalties based on current accumulation times and permitted storage capacities.

File details come from the government source that posted it. Updated .