Bid Abstract signed 23B0001.pdf
PDF 193 KB Posted
- Attached to
- 12KV Overhead to Underground Powerline Replacement At DDJC Federal contract opportunity
- Solicitation number
- SP330023B0001
- Issued by
- Defense Logistics Agency Distribution
About this file
This abstract of offers is for solicitation number SP330023B0001 to replace an overhead 12kV powerline with an underground system at the Defense Distribution Depot in New Cumberland, Pennsylvania. The work includes removing overhead lines, poles, and installing underground conduits, duct banks, manholes, transformers and other accessories. Three offers were received by the July 6, 2023 deadline from GCJ Inc. DBA Silver State Construction, Midwest Electrical Construction Inc., and Creative Builders Inc. CBSE JV. All three bids included the required bid security and amendments. Offer prices ranged from $5.5 million to $9.7 million. The government estimate was $8.5 million. The Defense Logistics Agency Distribution will award the contract.
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABSTRACT OF OFFERS
Solicitation Number: SP330023B0001
Date Issued:
Date Opened:
Issuing Office: DLA Distribution Acquisition Operations 430 Mifflin Avenue Suite 3102A New Cumberland, PA 17070 Project Title: 12KV Overhead to Underground Powerline Replacement at DDJC Amendments (SF30) Issued: 0001‐0004
Certifying Official: Joshua L. Woodworth, Contracting Officer
Signature:
USG USG Offeror GCJ INC DBA Silver State Construction
Offeror Midwest Electrical Construction Inc
Offeror Creative Builders, Inc
CBSE JV
Bid Security y Bid Security y Bid Security y Amendments 4 Amendments 2, 4 Amendments 4
CLIN DESCRIPTION
EST
QTY
UNIT UNIT PRICE
ESTIMATED
AMOUNT
UNIT PRICE
ESTIMATED
AMOUNT
UNIT PRICE
ESTIMATED
AMOUNT
UNIT PRICE ESTIMATED AMOUNT
0001 From pole A4 to pole 18A 1 JB 4,156,056.30$ 4,156,056.30$ $3,508,024.00 3,508,024.00$ $2,237,200.00 2,237,200.00$ $5,582,000.00 5,582,000.00$
0002 Building 205 Disconnect Switch 1 JB 127,417.13$ 127,417.13$ $410,104.00 410,104.00$ $257,700.00 257,700.00$ $375,000.00 375,000.00$
0003 From pole 34 to pole 36 1 JB 511,603.95$ 511,603.95$ $1,361,274.00 1,361,274.00$ $873,400.00 873,400.00$ $1,120,000.00 1,120,000.00$
0004 From pole 36 to pole 41 1 JB 1,242,558.90$ 1,242,558.90$ $1,722,659.00 1,722,659.00$ $1,373,000.00 1,373,000.00$ $1,225,000.00 1,225,000.00$
0005 From pole 41 to 47 1 JB 887,403.83$ 887,403.83$ $1,497,964.00 1,497,964.00$ $769,300.00 769,300.00$ $1,400,000.00 1,400,000.00$
TOTAL 6,925,040.11$ 8,500,025.00$ 5,510,600.00$ 9,702,000.00$
Bidder #3
5/24/2023 7/6/2023
Government Estimate Bidder #1 Bidder #2
| 2023-07-06T14:00:24-0400 | |
| WOODWORTH.JOSHUA.LYLE.1245848133 |
File details come from the government source that posted it. Updated .