About this file
This document is a Schedule of Unit Prices for the City of Edgewater's Menard May Park Observation Pier Replacement project. The schedule details a comprehensive replacement of an existing pier, including mobilization, site preparation, and construction of a new observation pier. Key elements include removing the existing pier and piles, installing 8" diameter wood piles, constructing decking, railings, and associated structural components, and adding lighting infrastructure. The project involves 41 wood piles, 1,683 board feet of decking, 1,440 board feet of railing, and various cross beams and braces.
The total project cost is $172,710.66, with major cost components including $25,000 for mobilization, $43,050 for wood piles, and $24,640 for pile guards. Additional costs cover survey control, concrete sidewalk installation, hardware, electrical work, and bonding requirements. The bid includes a bid bond of $840 and a 110% payment and performance bond of $5,170. The unit pricing provides a detailed breakdown of materials and labor, with prices ranging from $3.68 for silt fence linear feet to $1,050 per wood pile, offering transparency in the project's cost structure.
View the file
Other files for this state and local contract opportunity
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Description Quantity Unit Unit Price Contract Value
1 Mobilization 1 LS 25,000.00$ 25,000.00$ 2 Silt Fence 42 LF 3.68$ 154.56$ 3 Floating Turbidity Barrier 130 LF 16.00$ 2,080.00$
Remove Existing Pier & Piles & Dispose 1 LS 20,400.00$ 20,400.00$
5 Survey Control 1 LS 4,000.00$ 4,000.00$ 6 Rebuild Revetment 1 LS 2,400.00$ 2,400.00$ 7 Concrete Sidewalk w/ Thicken Edge 81 SF 18.00$ 1,458.00$ 8 8" Diameter Wood Piles 41 EA 1,050.00$ 43,050.00$ 9 Pile Guard 320 LF 77.00$ 24,640.00$
10 2 x 10 Cross Beam 324 BF 6.00$ 1,944.00$ 11 2 x 6 Cross Brace 384 BF 3.75$ 1,440.00$ 12 2 x 8 Joist 905 BF 4.90$ 4,434.50$ 13 2 x 6 Scab Block 80 BF 3.75$ 300.00$ 14 2 x 8 Decking 1683 BF 5.20$ 8,751.60$ 15 2 x 8 Railing 1440 BF 4.90$ 7,056.00$ 16 2 x 12 Railing Cap 288 BF 9.00$ 2,592.00$ 17 6 x 6 Light Post 1 EA 200.00$ 200.00$
EXO Light, Conduit & Wire to Existing Circuit 1 LS 1,800.00$ 1,800.00$
Hardware (Bolts, Nuts, Washers, Screws, Nails, & Hurricane Straps) 1 LS 15,000.00$ 15,000.00$
Subtotal 166,700.66$ 20 Bid Bond 1 LS 840.00$ 840.00$
110% Payment & Performance Bond 1 LS 5,170.00$ 5,170.00$
Total Price 172,710.66$