This document is a Schedule of Unit Prices for the City of Edgewater's Menard May Park Observation Pier Replacement project, detailing an alternative bid for a fortified structure. The project involves comprehensive pier reconstruction, including mobilization, removal of existing pier and piles, survey control, revetment rebuilding, and installation of various structural components such as eco piles, pile guards, cross beams, decking, and railing. The scope encompasses 19 primary line items and two additional bonding items, with quantities specified for each component like silt fence (42 LF), floating turbidity barrier (130 LF), concrete sidewalk (81 SF), and various lumber and structural elements.

The total project cost is $208,639.06, with a subtotal of $202,629.06 for construction materials and labor, and an additional $6,010.00 for bid and performance bonds. The most significant line item expenses include 10" Eco Piles at $57,400.00 (41 each), removal of existing pier and piles at $20,400.00, mobilization at $25,000.00, and thru flow decking at $30,330.00. The pricing is presented as a unit price contract, allowing flexibility in final costs based on actual quantities used, with each item having a specified unit price and calculated contract value.

View the file

Other files for this state and local contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Description Quantity Unit Unit Price Contract Value

1 Mobilization 1 LS 25,000.00$ 25,000.00$ 2 Silt Fence 42 LF 3.68$ 154.56$ 3 Floating Turbidity Barrier 130 LF 16.00$ 2,080.00$

Remove Existing Pier & Piles & Dispose 1 LS 20,400.00$ 20,400.00$

5 Survey Control 1 LS 4,000.00$ 4,000.00$ 6 Rebuild Revetment 1 LS 2,400.00$ 2,400.00$ 7 Concrete Sidewalk w/ Thicken Edge 81 SF 18.00$ 1,458.00$ 8 10" Eco Pile 41 EA 1,400.00$ 57,400.00$ 9 Pile Guard 320 LF 77.00$ 24,640.00$

10 2 x 10 Cross Beam 324 BF 6.00$ 1,944.00$ 11 2 x 6 Cross Brace 384 BF 3.75$ 1,440.00$ 12 2 x 8 Joist 905 BF 4.90$ 4,434.50$ 13 2 x 6 Scab Block 80 BF 3.75$ 300.00$

Thru Flow Decking (1 x 3 Surge Series 50) 337 EA 90.00$ 30,330.00$

15 2 x 8 Railing 1440 BF 4.90$ 7,056.00$ 16 2 x 12 Railing Cap 288 BF 9.00$ 2,592.00$ 17 6 x 6 Light Post 1 EA 200.00$ 200.00$

EXO Light, Conduit & Wire to Existing Circuit 1 LS 1,800.00$ 1,800.00$

Hardware (Bolts, Nuts, Washers, Screws, Nails, & Hurricane Straps) 1 LS 15,000.00$ 15,000.00$

Subtotal 202,629.06$ 20 Bid Bond 1 LS 840.00$ 840.00$

110% Payment & Performance Bond 1 LS 5,170.00$ 5,170.00$

Total Price 208,639.06$

CITY OF EDGEWATER

MENARD MAY PARK OBSERVATION PIER REPLACEMENT, EDGEWATER

SCHEDULE OF UNIT PRICES - ALT FOR FORTIFIED STRUCTURE

8-27-24