SOV_7-23-24_revised_8-27-24.pdf

PDF 41 KB Posted

Attached to
Menard May Park Observation Pier Replacement - Construction State and local contract opportunity
Solicitation number
ITB 25-PR-04
Issued by
Volusia County, Florida

About this file

This document is a Schedule of Unit Prices for the Menard May Park Observation Pier Replacement project for the City of Edgewater, Florida. The schedule details a comprehensive reconstruction of an observation pier, including multiple construction components such as mobilization, removal of existing pier and piles, survey control, revetment rebuilding, and various wooden structural elements. The project involves 21 line items covering everything from silt fence installation and floating turbidity barriers to wood pile placement, decking, railings, and electrical work like light post installation and conduit wiring.

The total project cost is $172,710.66, with a subtotal of $166,700.66 for direct construction activities and additional costs for a bid bond ($840.00) and a 110% payment and performance bond ($5,170.00). Unit prices range from $3.68 for linear feet of silt fence to $25,000.00 for mobilization, with significant expenses for key components like 8" diameter wood piles at $1,050.00 each and pile guards at $77.00 per linear foot. The project appears to be a FEMA-related reconstruction effort located at 413 South Riverside Drive in Edgewater, with specific GPS coordinates provided for the site.

View the file

Other files for this state and local contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Description Quantity Unit Unit Price Contract Value

1 Mobilization 1 LS 25,000.00$ 25,000.00$ 2 Silt Fence 42 LF 3.68$ 154.56$ 3 Floating Turbidity Barrier 130 LF 16.00$ 2,080.00$

Remove Existing Pier & Piles & Dispose 1 LS 20,400.00$ 20,400.00$

5 Survey Control 1 LS 4,000.00$ 4,000.00$ 6 Rebuild Revetment 1 LS 2,400.00$ 2,400.00$ 7 Concrete Sidewalk w/ Thicken Edge 81 SF 18.00$ 1,458.00$ 8 8" Diameter Wood Piles 41 EA 1,050.00$ 43,050.00$ 9 Pile Guard 320 LF 77.00$ 24,640.00$

10 2 x 10 Cross Beam 324 BF 6.00$ 1,944.00$ 11 2 x 6 Cross Brace 384 BF 3.75$ 1,440.00$ 12 2 x 8 Joist 905 BF 4.90$ 4,434.50$ 13 2 x 6 Scab Block 80 BF 3.75$ 300.00$ 14 2 x 8 Decking 1683 BF 5.20$ 8,751.60$ 15 2 x 8 Railing 1440 BF 4.90$ 7,056.00$ 16 2 x 12 Railing Cap 288 BF 9.00$ 2,592.00$ 17 6 x 6 Light Post 1 EA 200.00$ 200.00$

EXO Light, Conduit & Wire to Existing Circuit 1 LS 1,800.00$ 1,800.00$

Hardware (Bolts, Nuts, Washers, Screws, Nails, & Hurricane Straps) 1 LS 15,000.00$ 15,000.00$

Subtotal 166,700.66$ 20 Bid Bond 1 LS 840.00$ 840.00$

110% Payment & Performance Bond 1 LS 5,170.00$ 5,170.00$

Total Price 172,710.66$

CITY OF EDGEWATER

MENARD MAY PARK OBSERVATION PIER REPLACEMENT, EDGEWATER

SCHEDULE OF UNIT PRICES

8-27-24