This is a Short-Form Construction Contract template issued by the Palm Desert Housing Authority for the California Villas Pool Improvement Project (Project No. CHA00016). The project scope consists of full removal of existing pool and spa plaster finish, surface preparation and bond coat application, installation of new plaster finish, waterline tile cleaning and restoration, installation of three LED pool and spa lights, application of brick clay coping sealer, and repair and repainting of pool and spa deck surfacing. All work must be performed in accordance with industry standards and safety regulations. The contract specifies a performance period of 30 calendar days from the Notice to Proceed, with the contractor required to maintain a C-53 Swimming Pool Contractor license classification. The contractor must submit all required documentation concurrently with contract execution, including Performance Bond, Payment Bond, Insurance Documents, and certifications as specified in the exhibits.

The Total Contract Price is to be inserted by the parties and will be subject to adjustment through change orders approved in writing by the Authority. Payment will be made upon completion and approval if work is scheduled for 30 days or less; for longer projects, monthly progress payments will be issued with 5% retention withheld from each estimate. Liquidated damages of $1,000 per calendar day will be assessed for delays beyond the Contract Time, except for delays caused by Force Majeure Events on the critical path, which are non-compensable. The contractor must maintain general liability insurance of $1,000,000 per occurrence with $2,000,000 general aggregate, automobile liability insurance of $1,000,000 combined single limit, workers' compensation insurance per California law, pollution liability insurance of $1,000,000, and builder's risk insurance. The contract incorporates prevailing wage requirements under California Labor Code Section 1720 et seq., public works contractor registration requirements, and compliance with all applicable federal, state, and local laws. The contract may be terminated by the Authority at any time with three days' advance written notice, or immediately for cause.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PALM DESERT HOUSING AUTHORITY

SHORT FORM CONSTRUCTION CONTRACT

1. Parties and Date. This Agreement is made and entered into on Date, by and between the Palm Desert Housing Authority, a Public Body, Corporate and Politic, a political subdivision organized under the laws of the State of California with its principal place of business 73-510 Fred Waring Drive, Palm Desert, California 92260-2578, (“Authority”) and COMPANY NAME, Choose an item., with its principal place of business at COMPANY ADDRESS ("Contractor"). The Authority and Contractor are sometimes individually referred to herein as "Party" and collectively as "Parties."

2. Recitals.

2.1Authority. Authority is a public agency organized under the laws of the State of California, with power to contract for services necessary to achieve its purpose.
2.2Contractor. Contractor desires to perform and assume responsibility for the provision of certain construction services required by the Authority on the terms and conditions set forth in this Contract. Contractor represents that it is duly licensed and experienced in providing the scope of work consists of full removal of existing pool and spa plaster finish. Surface preparation, bond coat application, and installation of new plaster finish. Waterline tile cleaning and restoration. Installation of three LED’s pool/spa lights. Application of brick clay coping sealer to protect and extend lifespan of coping. Repair and repainting of pool/spa deck surfacing. All work to be performed in accordance with industry standards and safety regulations. Related construction services to public clients, that it and its employees or subcontractors have all necessary licenses and permits to perform the services in the State of California, and that it is familiar with the plans of Authority. The following license classifications are required for this Project: C-53, Swimming Pool Contractor
2.3Project.

The Authority desires to engage Contractor to render such services as set forth in this Contract for the following project:

California Villas Pool Improvement Project Project No. CHA00016 (hereinafter referred to as “the Project”).

2.4 Project Documents & Certifications. Contractor has obtained, and delivers concurrently herewith, Performance Bond, Payment Bond, Insurance Documents and Other Certifications as required by the Contract.

3. Terms.

3.1 Incorporation of Documents. This Contract includes and hereby incorporates in full by reference the following documents, including all exhibits, drawings, specifications, and documents therein, and attachments and addenda thereto:

· Services/Schedule (Exhibit “A”)

· Plans and Specifications (Exhibit “B”)

· Special Conditions (Exhibit “C”)

· CDBG General Conditions City of Plam Desert

· Contractor’s Certificate Regarding Workers’ Compensation (Exhibit “D”)

· Public Works Contractor Registration Certification (Exhibit “E”)

· Payment and Performance Bonds

· Federal Requirements (Exhibit “F”)

· Addenda

· Davis Bacon and Related Acts

· Change Orders executed by the Authority Latest Edition of the Standard Specifications for Public Works Construction (The Greenbook), Excluding Sections 1-9

· Notice Inviting Bids, if any

· Instructions to Bidders, if any

· Contractor’s Bid

3.1.1Precedence. To the extent there is a conflict between any portions of this Contract, the order of precedence shall be as follows: change orders, special conditions, technical specifications, plans/construction drawings, general contract terms, scope of work, standard plans, advertisements for bid/proposals, bids/proposals or other documents submitted by Contractor.
3.2Contractor’s Basic Obligation; Scope of Work. Contractor promises and agrees, at its own cost and expense, to furnish to the Authority all labor, materials, tools, equipment, services, and incidental and customary work necessary to fully and adequately complete the Project, including all structures and facilities necessary for the Project or described in the Contract (hereinafter sometimes referred to as the “Work”), for a Total Contract Price as specified pursuant to this Contract. All Work shall be subject to, and performed in accordance with the above referenced documents, as well as the exhibits attached hereto and incorporated herein by reference. The plans and specifications for the Work are further described in Exhibit “B” attached hereto and incorporated herein by this reference. Special Conditions, if any, relating to the Work are described in Exhibit “C” attached hereto and incorporated herein by this reference.
3.2.1Change in Scope of Work. Any change in the scope of the Work, method of performance, nature of materials or price thereof, or any other matter materially affecting the performance or nature of the Work shall not be paid for or accepted unless such change, addition or deletion is approved in advance and in writing by a valid change order executed by the Authority (“Change Order”).
3.2.1.1Change Orders. Changes to the Contract Time (as defined in Section 3.3) or Total Contract Price shall be in the form of a written Change Order, either signed by both parties or issued unilaterally by the Authority. No adjustment shall be made to the Contract Time unless the delay impacts the critical path to completion and the delay was not caused in whole or in part by the Contractor. The Authority’s liability to Contractor for delays for which the Authority is responsible shall be limited to only an extension of time unless such delays were unreasonable under the circumstances. Failure to timely request a Change Order shall constitute a waiver of any right to adjust the Contract Time or the Total Contract Price. All requests for Change Orders shall be accompanied by detailed supporting documentation, including but not limited to payroll records, invoices, schedules, and any other documentation requested by the Authority for the purpose of determining the additional costs or the impact of any delay. If the change involves Work bid at a unit price, then the Total Contract Price shall be increased at the unit price. If there is no unit price, then the Total Contract Price shall be adjusted to account for costs actually incurred plus an allowed mark-up of fifteen percent (15%), which shall constitute the entire amount of profit, mark-ups, field or home office overhead costs, including personnel, equipment or office space, any materials, or any costs of equipment idle time for such work. Regardless of ownership, equipment rates shall not exceed the listed prevailing rates at local equipment rental agencies, or distributors, at the time the work is performed. Nothing herein shall prevent the Parties from agreeing to a lump sum cost.
(A)Changes Ordered By Authority. Authority may at any time issue a written directive ordering additions, deletions, or changes to the Work. Contractor shall proceed with the work in accordance with the directive. To the extent the directive results in extra work or requires additional Contract Time, Contractor shall request a Change Order within seven (7) days of receiving the Work Directive. If any costs are not capable of being determined within seven (7) days, then Contractor shall request a Change Order within seven (7) days of when the costs are capable of being determined.
(B)Changes Requested By Contractor. With respect to any matter that may involve or require an adjustment to the Contract Time or the Contract Price, Contractor shall provide written notice of the underlying facts and circumstances that gave rise to the potential change within seven (7) days or prior to the alteration of conditions, whichever is earlier. Failure to give notice shall constitute a waiver of Contractor’s right to a change order. If any costs are not capable of being determined within seven (7) days, then Contractor shall request a Change Order within seven (7) days of when the costs are capable of being determined.
3.2.2Substitutions/”Or Equal”. Pursuant to Public Contract Code section 3400(b), the Authority may make a finding that designates certain products, things, or services by specific brand or trade name. Unless specifically designated in this Contract, whenever any material, process, or article is indicated or specified by grade, patent, or proprietary name or by name of manufacturer, such Specifications shall be deemed to be used for the purpose of facilitating the description of the material, process or article desired and shall be deemed to be followed by the words “or equal”.

Contractor may, unless otherwise stated, offer for substitution any material, process or article which shall be substantially equal or better in every respect to that so indicated or specified in this Contract. However, the Authority may have adopted certain uniform standards for certain materials, processes, and articles. Contractor shall submit requests, together with substantiating data, for substitution of any “or equal” material, process, or article no later than thirty-five (35) days after award of the Contract. To facilitate the construction schedule and sequencing, some requests may need to be submitted before thirty-five (35) days after award of Contract. Provisions regarding submission of “or equal” requests shall not in any way authorize an extension of time for performance of this Contract. If a proposed “or equal” substitution request is rejected, Contractor shall be responsible for providing the specified material, process, or article. The burden of proof as to the equality of any material, process or article shall rest with Contractor.

The Authority has the complete and sole discretion to determine if a material, process, or article is an “or equal” material, process or article that may be substituted. Data required to substantiate requests for substitutions of an “or equal” material, process or article data shall include a signed affidavit from Contractor stating that, and describing how, the substituted “or equal” material, process or article is equivalent to that specified in every way except as listed on the affidavit. Substantiating data shall include any and all illustrations, specifications, and other relevant data including catalog information which describes the requested substituted “or equal” material, process or article, and substantiates that it is an “or equal” to the material, process or article. The substantiating data must also include information regarding the durability and lifecycle cost of the requested substituted “or equal” material, process, or article. Failure to submit all the required substantiating data, including the signed affidavit, to the Authority in a timely fashion will result in the rejection of the proposed substitution.

Contractor shall bear all of the Authority’s costs associated with the review of substitution requests. Contractor shall be responsible for all costs related to a substituted “or equal” material, process, or article. Contractor is directed to the Special Conditions (if any) to review any findings made pursuant to Public Contract Code section 3400.

3.3 Period of Performance and Liquidated Damages. Contractor shall perform and complete all Work under this Contract within 30 Calendar days, beginning the effective date of the Notice to Proceed (“Contract Time”). Contractor shall perform its Work in strict accordance with any completion schedule, construction schedule or project milestones developed by the Authority. Such schedules or milestones may be included as part of Exhibits “A” or “B” attached hereto or may be provided separately in writing to Contractor. Contractor agrees that if such Work is not completed within the aforementioned Contract Time and/or pursuant to any such completion schedule, construction schedule or project milestones developed pursuant to provisions of the Contract, it is understood, acknowledged and agreed that the Authority will suffer damage. Pursuant to Government Code Section 53069.85, Contractor shall pay to the Authority as fixed and liquidated damages the sum of One Thousand and 00/100 Dollars ($1,000.00) per day for each and every calendar day of delay beyond the Contract Time or beyond any completion schedule, construction schedule, or Project milestones established pursuant to the Contract.

If Contractor is delayed in the performance or progress of the Work by a Force Majeure Event (as defined herein), then the Contractor shall be entitled to a time extension, as provided herein, when the Work stopped is on the critical path and shall not be charged liquidated damages. Such a non-compensable adjustment shall be Contractor’s sole and exclusive remedy for such delays and the Contractor will not receive an adjustment to the Total Contract Price or any other compensation. Contractor must submit a timely request in accordance with the requirements of the Contract.

A Force Majeure Event shall mean an event that materially affects a party’s performance and is one or more of the following: (1) Acts of God or other natural disasters occurring at the project site; (2) terrorism or other acts of a public enemy; (3) orders of governmental authorities (including, without limitation, unreasonable and unforeseeable delay in the issuance of permits or approvals by governmental authorities that are required for the work); (4) pandemics, epidemics or quarantine restrictions; and (5) strikes and other organized labor action occurring at the project site and the effects thereof on the work, only to the extent such strikes and other organized labor action are beyond the control of Contractor and its subcontractors, of every tier, and to the extent the effects thereof cannot be avoided by use of replacement workers. For purposes of this section, “orders of governmental authorities,” includes ordinances, emergency proclamations and orders, rules to protect the public health, welfare and safety, and other actions of the Authority in its capacity as a municipal authority.

3.4Standard of Performance; Performance of Employees. Contractor shall perform all Work under this Contract in a skillful and workmanlike manner, and consistent with the standards generally recognized as being employed by professionals in the same discipline in the State of California. Contractor represents and maintains that it is skilled in the professional calling necessary to perform the Work. Contractor warrants that all employees and subcontractors shall have sufficient skill and experience to perform the Work assigned to them. Finally, Contractor represents that it, its employees, and subcontractors have all licenses, permits, qualifications and approvals of whatever nature that are legally required to perform the Work, including a City Business License, and that such licenses and approvals shall be maintained throughout the term of this Contract. Contractor shall perform, at its own cost and expense and without reimbursement from the Authority, any work necessary to correct errors or omissions which are caused by Contractor’s failure to comply with the standard of care provided for herein. Any employee who is determined by the Authority to be uncooperative, incompetent, a threat to the safety of persons or the Work, or any employee who fails or refuses to perform the Work in a manner acceptable to the Authority, shall be promptly removed from the Project by Contractor and shall not be re‑employed on the Work.
3.5Control and Payment of Subordinates; Contractual Relationship. Authority retains Contractor on an independent contractor basis and Contractor is not an employee of Authority. Any additional personnel performing the work governed by this Contract on behalf of Contractor shall at all times be under Contractor’s exclusive direction and control. Contractor shall pay all wages, salaries, and other amounts due such personnel in connection with their performance under this Contract and as required by law. Contractor shall be responsible for all reports and obligations respecting such additional personnel, including, but not limited to: social security taxes, income tax withholding, unemployment insurance, and workers’ compensation insurance.
3.6Authority’s Basic Obligation. Authority agrees to engage and does hereby engage Contractor to furnish all materials and to perform all Work according to the terms and conditions herein contained for the sum set forth above. Except as otherwise provided in the Contract, the Authority shall pay to Contractor, as full consideration for the satisfactory performance by Contractor of the services and obligations required by this Contract, the below-referenced compensation in accordance with compensation provisions set forth in the Contract.
3.7Compensation and Payment.
3.7.1Amount of Compensation. As consideration for performance of the Work required herein, Authority agrees to pay Contractor the Total Contract Price of [***WRITE OUT DOLLAR AMOUNT***] Dollars ($INSERT NUMERICAL DOLLAR AMOUNT) (“Total Contract Price”) provided that such amount shall be subject to adjustment pursuant to the applicable terms of this Contract or written Change Orders approved and signed in advance by the Authority.
3.7.2Payment of Compensation. If the Work is scheduled for completion in thirty (30) or less calendar days, Authority will arrange for payment of the Total Contract Price upon completion and approval by Authority of the Work. If the Work is scheduled for completion in more than thirty (30) calendar days, Authority will pay Contractor on a monthly basis as provided for herein. On or before the fifth (5th) day of each month, Contractor shall submit to the Authority an itemized application for payment in the format supplied by the Authority indicating the amount of Work completed since commencement of the Work or since the last progress payment. These applications shall be supported by evidence which is required by this Contract and such other documentation as the Authority y may require. The Contractor shall certify that the Work for which payment is requested has been done and that the materials listed are stored where indicated. Contractor may be required to furnish a detailed schedule of values upon request of the Authority and in such detail and form as the Authority shall request, showing the quantities, unit prices, overhead, profit, and all other expenses involved in order to provide a basis for determining the amount of progress payments. Contractor shall submit its final invoice to Authority within thirty (30) days from the last date of the Work or termination in accordance with this Contract and failure by the Contractor to submit a timely invoice shall constitute a waiver of its right to final payment.
3.7.3Prompt Payment. Authority shall review and pay all progress payment requests in accordance with the provisions set forth in Section 20104.50 of the California Public Contract Code. No progress payments will be made for Work not completed in accordance with this Contract. Contractor shall comply with all applicable laws, rules and regulations relating to the proper payment of its employees, subcontractors, suppliers, or others.
3.7.4Contract Retentions. From each approved progress estimate, 5% will be deducted and retained by the Authority, and the remainder will be paid to Contractor. All Contract retention shall be released and paid to Contractor and subcontractors pursuant to California Public Contract Code section 7107.
3.7.5Other Retentions. In addition to Contract retentions, the Authority may deduct from each progress payment an amount necessary to protect Authority from loss because of: (1) liquidated damages which have accrued as of the date of the application for payment; (2) any sums expended by the Authority in performing any of Contractor’s obligations under the Contract which Contractor has failed to perform or has performed inadequately; (3) defective Work not remedied; (4) stop notices as allowed by state law; (5) reasonable doubt that the Work can be completed for the unpaid balance of the Total Contract Price or within the Contract Time; (6) unsatisfactory prosecution of the Work by Contractor; (7) unauthorized deviations from the Contract; (8) failure of Contractor to maintain or submit on a timely basis proper and sufficient documentation as required by the Contract or by Authority during the prosecution of the Work; (9) erroneous or false estimates by Contractor of the value of the Work performed; (10) any sums representing expenses, losses, or damages as determined by the Authority, incurred by the Authority for which Contractor is liable under the Contract; and (11) any other sums which the Authority is entitled to recover from Contractor under the terms of the Contract or pursuant to state law, including Section 1727 of the California Labor Code. The failure by the Authority to deduct any of these sums from a progress payment shall not constitute a waiver of the City’s right to such sums.
3.7.6Substitutions for Contract Retentions. In accordance with California Public Contract Code section 22300, the Authority will permit the substitution of securities for any monies withheld by the Authority to ensure performance under the Contract. At the request and expense of Contractor, securities equivalent to the amount withheld shall be deposited with the Authority, or with a state or federally chartered bank in California as the escrow agent, and thereafter the Authority shall then pay such monies to Contractor as they come due. Upon satisfactory completion of the Contract, the securities shall be returned to Contractor. For purposes of this Section and Section 22300 of the Public Contract Code, the term “satisfactory completion of the contract” shall mean the time the Authority has issued written final acceptance of the Work and filed a Notice of Completion as required by law and provisions of this Contract. Contractor shall be the beneficial owner of any securities substituted for monies withheld and shall receive any interest thereon. The escrow agreement used for the purposes of this Section shall be in the form provided by the City.
3.7.7Payment to Subcontractors. Contractor shall pay all subcontractors for and on account of work performed by such subcontractors in accordance with the terms of their respective subcontracts and as provided for in Section 7108.5 of the California Business and Professions Code. Such payments to subcontractors shall be based on the measurements and estimates made and progress payments provided to Contractor pursuant to this Contract.
3.7.8Title to Work. As security for partial, progress, or other payments, title to Work for which such payments are made shall pass to the Authority at the time of payment. To the extent that title has not previously been vested in the Authority by reason of payments, full title shall pass to the Authority at delivery of the Work at the destination and time specified in this Contract. Such transferred title shall in each case be good, free, and clear from any and all security interests, liens, or other encumbrances. Contractor promises and agrees that it will not pledge, hypothecate, or otherwise encumber the items in any manner that would result in any lien, security interest, charge, or claim upon or against said items. Such transfer of title shall not imply acceptance by the Authority, nor relieve Contractor from the responsibility to strictly comply with the Contract and shall not relieve Contractor of responsibility for any loss of or damage to items.
3.7.9Labor and Material Releases. Contractor shall furnish Authority with labor and material releases from all subcontractors performing work on, or furnishing materials for, the Work governed by this Contract prior to final payment by City.
3.8Labor
3.8.1Prevailing Wages. Contractor is aware of the requirements of California Labor Code Section 1720 et seq., and 1770 et seq., as well as California Code of Regulations, Title 8, Section 16000 et seq., (“Prevailing Wage Laws”), which require the payment of prevailing wage rates and the performance of other requirements on “public works” and “maintenance” projects. Since the Work is being performed as part of an applicable “public works” or “maintenance” project, as defined by the Prevailing Wage Laws, and if the total compensation is $1,000 or more for a public works project or $1,000 or more for a maintenance project, Contractor agrees to fully comply with such Prevailing Wage Laws. Authority shall provide Contractor with a copy of the prevailing rates of per diem wages in effect at the commencement of this Contract. Contractor shall make copies of the prevailing rates of per diem wages for each craft, classification or type of worker needed to execute the Services available to interested parties upon request and shall post copies at Contractor’s principal place of business and at the project site. Contractor shall defend, indemnify, and hold the Authority and their respective officers, agents, employees, volunteers, and representatives free and harmless from any claim or liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws. Contractor and any subcontractor shall forfeit a penalty of up to $200 per calendar day or portion thereof for each worker paid less than the prevailing wage rates.
3.8.2Apprenticeable Crafts. When Contractor employs workmen in an apprenticeable craft or trade, Contractor shall comply with the provisions of Section 1777.5 of the California Labor Code with respect to the employment of properly registered apprentices upon public works. The primary responsibility for compliance with said section for all apprenticeable occupations shall be with Contractor. The Contractor or any subcontractor that is determined by the Labor Commissioner to have knowingly violated Section 1777.5 shall forfeit as a civil penalty an amount not exceeding $100 for each full calendar day of noncompliance, or such greater amount as provided by law.
3.8.3Hours of Work. Contractor is advised that eight (8) hours labor constitutes a legal day’s work. Pursuant to Section 1813 of the California Labor Code, Contractor shall forfeit a penalty of $25.00 per worker for each day that each worker is permitted to work more than eight (8) hours in any one calendar day and forty (40) hours in any one calendar week, except when payment for overtime is made at not less than one and one‑half (1‑1/2) times the basic rate for that worker.
3.8.4Payroll Records. Contractor and each subcontractor shall keep an accurate payroll record, showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by him or her in connection with the public work. The payroll records shall be certified and shall be available for inspection at all reasonable hours at the principal office of Contractor in the manner provided in Labor Code section 1776. In the event of noncompliance with the requirements of this section, Contractor shall have 10 days in which to comply subsequent to receipt of written notice specifying in what respects such Contractor must comply with this section. Should noncompliance still be evident after such 10-day period, Contractor shall, as a penalty to City, forfeit not more than $100.00 for each calendar day or portion thereof, for each worker, until strict compliance is effectuated. The amount of the forfeiture is to be determined by the Labor Commissioner. A contractor who is found to have violated the provisions of law regarding wages on Public Works with the intent to defraud shall be ineligible to bid on Public Works contracts for a period of one to three years as determined by the Labor Commissioner. Upon the request of the Division of Apprenticeship Standards or the Division of Labor Standards Enforcement, such penalties shall be withheld from progress payments then due. The responsibility for compliance with this section is on Contractor. In accordance with Labor Code section 1771.4, the Contractor and each subcontractor shall furnish the certified payroll records directly to the DIR on a weekly basis and in the format prescribed by the DIR, which may include electronic submission. The requirement to submit certified payroll records directly to the Labor Commissioner under Labor Code section 1771.4 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Section 1771.4.
3.8.5Contractor and Subcontractor Registration. Pursuant to Labor Code sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. No bid will be accepted, nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. Contractor is directed to review, fill out and execute the Public Works Contractor Registration Certification attached hereto as Exhibit “E” prior to contract execution. Notwithstanding the foregoing, the contractor registration requirements mandated by Labor Code Sections 1725.5 and 1771.1 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Sections 1725.5 and 1771.1.
3.8.6Labor Compliance; Stop Orders. This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. It shall be the Contractor’s sole responsibility to evaluate and pay the cost of complying with all labor compliance requirements under this Contract and applicable law. Any stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor that affect Contractor’s performance of Work, including any delay, shall be Contractor’s sole responsibility. Any delay arising out of or resulting from such stop orders shall be considered Contractor caused delay subject to any applicable liquidated damages and shall not be compensable by the Authority. Contractor shall defend, indemnify, and hold the Authority and their respective officers, agents, employees, volunteers, and representatives free and harmless from any claim or liability arising out of stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor.
3.9Performance of Work; Jobsite Obligations.
3.9.1Water Quality Management and Compliance.
3.9.1.1Water Quality Management and Compliance. Contractor shall keep itself and all subcontractors, staff, and employees fully informed of and in compliance with all local, state and federal laws, rules and regulations that may impact, or be implicated by the performance of the Work including, without limitation, all applicable provisions of the Federal Water Pollution Control Act (33 U.S.C. §§ 1300); the California Porter-Cologne Water Quality Control Act (Cal Water Code §§ 13000-14950); local ordinances regulating discharges of storm water; and any and all regulations, policies, or permits issued pursuant to any such authority regulating the discharge of pollutants, as that term is used in the Porter-Cologne Water Quality Control Act, to any ground or surface water in the State.
3.9.1.2Compliance with the Statewide Construction General Permit. Contractor shall comply with all conditions of the most recent iteration of the National Pollutant Discharge Elimination System General Permit for Storm Water Discharges Associated with Construction Activity, issued by the California State Water Resources Control Board (“Permit”). It shall be Contractor’s sole responsibility to file a Notice of Intent and procure coverage under the Permit for all construction activity which results in the disturbance of more than one acre of total land area, or which is part of a larger common area of development or sale. Prior to initiating work, Contractor shall be solely responsible for preparing and implementing a Storm Water Pollution Prevention Plan (SWPPP) as required by the Permit. Contractor shall be responsible for procuring, implementing, and complying with the provisions of the Permit and the SWPPP, including the standard provisions, and monitoring and reporting requirements as required by the Permit. The Permit requires the SWPPP to be a “living document” that changes as necessary to meet the conditions and requirements of the job site as it progresses through difference phases of construction and is subject to different weather conditions. It shall be Contractor’s sole responsibility to update the SWPPP as necessary to address conditions at the project site.
3.9.1.3Other Water Quality Rules Regulations and Policies. Contractor shall comply with the lawful requirements of any applicable municipality, drainage Authority, or local agency regarding discharges of storm water to separate storm drain systems or other watercourses under their jurisdiction, including applicable requirements in municipal storm water management programs.
3.9.1.4Cost of Compliance. Storm, surface, nuisance, or other waters may be encountered at various times during construction of the Work. Therefore, the Contractor, hereby acknowledges that it has investigated the risk arising from such waters and assumes any and all risks and liabilities arising therefrom.
3.9.1.5Liability for Non-Compliance. Failure to comply with the Permit is a violation of federal and state law. Pursuant to the indemnification provisions of this Contract, Contractor hereby agrees to defend, indemnify, and hold harmless the Authority and their respective directors, officers, agents, employees, volunteers, and representatives for any alleged violations. In addition, Authority may seek damages from Contractor for any delay in completing the Work in accordance with the Contract, if such delay is caused by or related to Contractor’s failure to comply with the Permit.
3.9.1.6Reservation of Right to Defend. Authority reserves the right to defend any enforcement action brought against the Authority for Contractor’s failure to comply with the Permit or any other relevant water quality law, regulation, or policy. Pursuant to the indemnification provisions of this Contract, Contractor hereby agrees to be bound by, and to reimburse the Authority for the costs (including the City’s attorney’s fees) associated with, any settlement reached between the Authority and the relevant enforcement entity.
3.9.1.7Training. Contractor warrants that all employees and subcontractors shall have sufficient skill and experience to perform the work assigned to them without impacting water quality in violation of the laws, regulations and policies described in paragraph 3.9.1. Contractor further warrants that it, its employees, and subcontractors will receive adequate training, as determined by Authority, regarding the requirements of the laws, regulations and policies described in paragraph 3.9.1 as they may relate to the Work provided under this Contract. Upon request, Authority will provide the Contractor with a list of training programs that meet the requirements of this paragraph.
3.9.2Safety. Contractor shall execute and maintain its work so as to avoid injury or damage to any person or property. Contractor shall comply with the requirements of the specifications relating to safety measures applicable in particular operations or kinds of work. In carrying out its Work, Contractor shall at all times be in compliance with all applicable local, state and federal laws, rules and regulations, and shall exercise all necessary precautions for the safety of employees appropriate to the nature of the Work and the conditions under which the Work is to be performed. Safety precautions as applicable shall include, but shall not be limited to, adequate life protection and lifesaving equipment; adequate illumination for underground and night operations; instructions in accident prevention for all employees, such as machinery guards, safe walkways, scaffolds, ladders, bridges, gang planks, confined space procedures, trenching and shoring, fall protection and other safety devices, equipment and wearing apparel as are necessary or lawfully required to prevent accidents or injuries; and adequate facilities for the proper inspection and maintenance of all safety measures. Furthermore, Contractor shall prominently display the names and telephone numbers of at least two medical doctors practicing in the vicinity of the Project, as well as the telephone number of the local ambulance service, adjacent to all telephones at the Project site.
3.9.3Laws and Regulations. Contractor shall keep itself fully informed of and in compliance with all local, state, and federal laws, rules and regulations in any manner affecting the performance of the Contract or the Work, including all Cal/OSHA requirements, and shall give all notices required by law. Contractor shall be liable for all violations of such laws and regulations in connection with the Work. If Contractor observes that the drawings or specifications are at variance with any law, rule, or regulation, it shall promptly notify the Authority in writing. Any necessary changes shall be made by written Change Order. If Contractor performs any work knowing it to be contrary to such laws, rules, and regulations and without giving written notice to the Authority, Contractor shall be solely responsible for all costs arising therefrom. Authority is a public entity of the State of California subject to certain provisions of the Health & Safety Code, Government Code, Public Contract Code, and Labor Code of the State. It is stipulated and agreed that all provisions of the law applicable to the public contracts of a municipality are a part of this Contract to the same extent as though set forth herein and will be complied with.
3.9.4Permits and Licenses. Contractor shall be responsible for securing City permits and licenses necessary to perform the Work described herein, including, but not limited to, any required business license. While Contractor will not be charged a fee for any City permits, Contractor shall pay the City’s business license fee, if any. Any ineligible contractor or subcontractor pursuant to Labor Code Sections 1777.1 and 1777.7 may not perform work on this Project.
3.9.5Trenching Work. If the Total Contract Price exceeds $25,000 and if the Work governed by this Contract entails excavation of any trench or trenches five (5) feet or more in depth, Contractor shall comply with all applicable provisions of the California Labor Code, including Section 6705. To this end, Contractor shall submit for Authority’s review and approval a detailed plan showing the design of shoring, bracing, sloping, or other provisions to be made for worker protection from the hazard of caving ground during the excavation of such trench or trenches. If such plan varies from the shoring system standards, the plan shall be prepared by a registered civil or structural engineer.
3.9.6Hazardous Materials and Differing Conditions. As required by California Public Contract Code section 7104, if this Contract involves digging trenches or other excavations that extend deeper than four (4) feet below the surface, Contractor shall promptly, and prior to disturbance of any conditions, notify Authority of: (1) any material discovered in excavation that Contractor believes to be a hazardous waste that is required to be removed to a Class I, Class II or Class III disposal site; (2) subsurface or latent physical conditions at the site differing from those indicated by City; and (3) unknown physical conditions of an unusual nature at the site, significantly different from those ordinarily encountered in such contract work. Upon notification, Authority shall promptly investigate the conditions to determine whether a Change Order is appropriate. In the event of a dispute, Contractor shall not be excused from any scheduled completion date and shall proceed with all Work to be performed under the Contract but shall retain all rights provided by the Contract or by law for making protests and resolving the dispute.
3.9.7Underground Utility Facilities. To the extent required by Section 4215 of the California Government Code, Authority shall compensate Contractor for the costs of: (1) locating and repairing damage to underground utility facilities not caused by the failure of Contractor to exercise reasonable care; (2) removing or relocating underground utility facilities not indicated in the construction drawings; and (3) equipment necessarily idled during such work. Contractor shall not be assessed liquidated damages for delay caused by failure of Authority to provide for removal or relocation of such utility facilities.
3.9.8Air Quality. Contractor must fully comply with all applicable laws, rules and regulations in furnishing or using equipment and/or providing services, including, but not limited to, emissions limits and permitting requirements imposed by the California Air Resources Board (CARB). Although CARB limits and requirements are broader, Contractor shall specifically be aware of their application to “portable equipment”, which definition is considered by CARB to include any item of equipment with a fuel-powered engine. Contractor shall indemnify Authority against any fines or penalties imposed by CARB, or any other governmental or regulatory agency for violations of applicable laws, rules and/or regulations by Contractor, its subcontractors, or others for whom Contractor is responsible under its indemnity obligations provided for in this Contract.
3.9.9State Recycling Mandates.Contractor shall comply with State Recycling Mandates. Any recyclable materials/debris collected by the Contractor that can be feasibly diverted via reuse or recycling must be hauled by the appropriate handler for reuse or recycling.
3.9.10Inspection Of Site. Contractor has visited sites where Work is to be performed and has become acquainted with all conditions affecting the Work. Contractor warrants that it has made such examinations as it deems necessary to determine the condition of the Work sites, its accessibility to materials, workmen and equipment, and to determine the Contractor’s ability to protect existing surface and subsurface improvements. No claim for allowances–time or money–will be allowed as to such matters.
3.9.11Field Measurements. Contractor shall make field measurements, verify field conditions, and shall carefully compare such field measurements and conditions and other information known to Contractor with the Contract Documents before commencing activities. Errors, inconsistencies, or omissions discovered shall be reported to the Authority immediately and prior to performing any work or altering the condition.
3.10Completion of Work. When Contractor determines that it has completed the Work required herein, Contractor shall so notify Authority in writing and shall furnish all labor and material releases required by this Contract. Authority shall thereupon inspect the Work. If the Work is not acceptable to the Authority, the Authority shall indicate to Contractor in writing the specific portions or items of Work which are unsatisfactory or incomplete. Once Contractor determines that it has completed the incomplete or unsatisfactory Work, Contractor may request a re-inspection by the Authority. Once the Work is acceptable to Authority, Authority shall pay to Contractor the Total Contract Price remaining to be paid, less any amount which Authority may be authorized or directed by law to retain.
3.11Claims; Government Code Claim Compliance.
3.11.1Except as otherwise provided in this Contract, if any dispute shall arise between the Authority and Contractor regarding performance of the Work, or any alleged change in the Work, Contractor shall timely perform the disputed work and shall give written notice of a claim for additional compensation for the work to the Authority within three (3) days after commencement of the disputed work. Contractor’s failure to give written notice within the three (3)-day period constitutes an agreement by Contractor that it will receive no extra compensation for the disputed work and shall constitute a waiver of the right to further pursue the claim under the Contract or at law.
3.11.1.1Intent. Effective January 1, 1991, Section 20104 et seq., of the California Public Contract Code prescribes a process utilizing informal conferences, non-binding judicial supervised mediation, and judicial arbitration to resolve disputes on construction claims of $375,000 or less. Effective January 1, 2017, Section 9204 of the Public Contract Code prescribes a process for negotiation and mediation to resolve disputes on construction claims. The intent of this Section is to implement Sections 20104 et seq. and Section 9204 of the California Public Contract Code. This Section shall be construed to be consistent with all applicable law, including but not limited to these statutes.
3.11.1.2Claims. For purposes of this Section, “Claim” means a separate demand by the Contractor for:
(A)An adjustment to the time for completion including, without limitation, for relief from damages or penalties for delay assessed by the Authority;
(B)Payment by the Authority of money or damages arising from Work done by or on behalf of the Contractor pursuant to the Contract, payment for which is not otherwise expressly provided or to which the Contractor is not otherwise entitled; or
(C)An amount the payment of which is disputed by the Authority.

A “Claim” does not include any demand for payment for which the Contractor has failed to provide notice, request a Change Order, or otherwise failed to follow any procedures contained in the Contract Documents.

3.11.1.3Filing Claims. Claims governed by this Section may not be filed unless and until the Contractor completes any and all requirements of the Contract Documents pertaining to notices and requests for changes to the Contract Time or Contract Price, and Contractor’s request for a change has been denied in whole or in part. Claims governed by this Section must be filed no later than thirty (30) days after a request for change has been denied in whole or in part or after any other event giving rise to the Claim. The Claim shall be submitted in writing to the Authority and shall include on its first page the following words in 16-point capital font: “THIS IS A CLAIM.” The Claim shall include all the information and documents necessary to substantiate the Claim, including but not limited to those identified below. Nothing in this Section is intended to extend the time limit or supersede notice requirements otherwise provided by Contract Documents. Failure to follow such contractual requirements shall bar any Claims or subsequent proceedings for compensation or payment thereon.
3.11.1.4Supporting Documentation. The Contractor shall submit all claims in the following format:
(A)Summary description of Claim including basis of entitlement, merit and amount of time or money requested, with specific reference to the Contract Document provisions pursuant to which the Claim is made
(B)List of documents relating to claim:
(1)Specifications
(2)Drawings
(3)Clarifications (Requests for Information)
(4)Schedules
(5)Other
(C)Chronology of events and correspondence
(D)Narrative analysis of claim merit
(E)Analysis of Claim cost, including calculations and supporting documents
(F)Time impact analysis in CPM format
3.11.1.5City’s Response. Upon receipt of a Claim pursuant to this Section, the Authority shall conduct a reasonable review of the Claim and, within a period not to exceed 45 days, shall provide the Contractor a written statement identifying what portion of the Claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the Claim will be processed and made within 60 days after the Authority issues its written statement.
(A)If the Authority needs approval from its governing body to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the Claim, and the City’s governing body does not meet within the 45 days or within the mutually agreed to extension of time following receipt of a Claim sent by registered mail or certified mail, return receipt requested, the Authority shall have up to three (3) days following the next duly publicly noticed meeting of the Authority’s governing body after the 45-day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion.
(B)Within 30 days of receipt of a Claim, the Authority may request in writing additional documentation supporting the Claim or relating to defenses or Claims the Authority may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of the Authority and the Contractor. The Authority’s written response to the Claim, as further documented, shall be submitted to the Contractor within 30 days (if the Claim is less than $50,000, within 15 days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.