This is a Construction Waste Management Plan document issued by the City of Palm Desert Building and Safety Division that applies to the California Villas Pool Improvement Project being undertaken by the Palm Desert Housing Authority. The document outlines mandatory waste diversion requirements under California Green Building Code (CALGreen) standards and Palm Desert Ordinance No. 1388, which mandate that construction and demolition projects achieve a minimum 65% diversion rate of non-hazardous debris through recycling, salvage, or reuse, with 100% diversion required for land-clearing debris such as dirt, rock, and landscape materials. The pool improvement project scope includes removal of existing pool and spa plaster, surface preparation and new plaster installation, waterline tile cleaning and restoration, installation of LED pool and spa lights, application of brick clay coping sealer, and repair and repaint of pool and spa deck surfaces. The CWMP must be completed and submitted with the building permit application to the City's Development Services Center, and monthly recycling progress reports must be provided to the District Environmental Coordinator during project execution.
All construction and demolition waste hauling must be conducted exclusively through either direct contractor self-hauling with a Self-Hauling Permit or through Burrtec Waste & Recycling Services, the City's franchised waste hauler. A final diversion report approved by Burrtec must be uploaded to the City's e-TRAKiT portal and submitted to the Building and Safety Division prior to issuance of Certificate of Occupancy, Temporary Certificate of Occupancy, or Final Inspection. The applicant acknowledges understanding that failure to comply with Ordinance No. 1388 constitutes a misdemeanor punishable by up to six months imprisonment or a fine up to $1,000, or both, and may result in job stop orders or delays in final project approval. Free technical assistance and guidance for regulatory compliance is available through the City's District Environmental Coordinator at (760) 674-1026, with additional information available through the City's permit center at (760) 776-6435 or permitcenter@palmdesert.gov.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| California_Villas_Pool_Improvement_Project.pdf | ||
| Short-Form-Construction-Sample.docx | DOCX document | |
| BID_GUARANTEE_(Bid_Bond).docx | DOCX document | |
| Wage_Determination-_California_Villas_Pool_CA20260025.pdf | ||
| CA_Villas_Pool_Area_Site_Map.png | PNG image | |
| Intake_Form_-_Solicitations_(005).pdf | ||
| CDBG_General_Conditions_City_of_Palm_Desert.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Waste Diversion Program City of Palm Desert - Building and Safety Division Phone (760)776-6435 ▪ Email: permitcenter@palmdesert.gov Website: https://www.palmdesert.gov
*PLEASE CONTACT BURRTEC AS OUTLINED BELOW
Construction and Demolition (C&D) waste accounts for 29% of materials going into landfills. The City of Palm Desert is mandated by State law to help reduce the amount of material hauled to landfills through the California Green Building Code (CALGreen). The City has created a process to make compliance easy through the C&D Diversion Program, and it all starts with a Construction Waste Management Plan.
A Construction Waste Management Plan (CWMP) is necessary to demonstrate compliance with State regulations for your C&D project. A CWMP ensures that C&D projects salvage, reuse, or recycle all inert solids (i.e. concrete, drywall, brick, asphalt, glass, plaster, clay, etc.) and divert at least 65% of all other debris generated by your project. This 65% diversion requirement, including 100% diversion of land clearing debris (i.e., dirt, rock, landscape material, etc.), is a mandatory requirement of the CALGreen requirements (See Palm Desert Environmental Programs!!)
The following projects are required to submit a Construction Waste Management Plan and comply with CALGreen:
Residential
1. Newly constructed low- and high-rise residential buildings such as:
• Hotels, motels, and lodging houses.
• Apartments and condominiums.
• One and two-family dwellings and townhouses.
• Dormitories, shelters for homeless people, congregate residences, and employee housing.
• Other types of dwellings containing sleeping accommodations with or without common toilets or cooking facilities.
• Factory-built housing.
• Accessory Dwelling Units (ADU) built in accordance with the California
Building Standards Code.
• Live/Work Units.
• Accessory structures serving residential buildings.
2. Additions or alterations of existing residential buildings where the addition or alteration increases the building’s conditioned area, volume, or size. The CALGreen requirements are only applicable within the specific area of addition or alteration.
Commercial or Non-residential:
1. Newly constructed buildings.
2. Building additions of 1,000 square feet or greater.
3. Building alterations with a permit valuation of $200,000 or above (for occupancies with the California Building Code. Code requirements for additions and alterations shall only apply to the portions of the building being added or altered within the scope of the permitted work.
Note: Minor electrical, plumbing, and mechanical permits are exempt.
mailto:%20permitcenter@palmdesert.gov https://www.palmdesert.gov/ https://www.palmdesert.gov/our-city/departments/public-works/solid-waste-and-recycling-services/organics-and-food-waste/construction-and-demolition-debris-recycling/ https://www.palmdesert.gov/our-city/departments/public-works/solid-waste-and-recycling-services/organics-and-food-waste/construction-and-demolition-debris-recycling/ https://www.calrecycle.ca.gov/LGCentral/Library/CandDModel/
Instructions:
When Applying for a Building Permit: When applying for a building permit, please make sure to include a completed CWMP, which must be provided to the City's Development Services Center. For free assistance and guidance in complying with State regulations, please contact the City of Palm Desert’s District Environmental Coordinator at (760) 674- 1026 from Burrtec."
During Your Project: Provide monthly recycling progress reports to and stay in contact with the District Environmental Coordinator. At the end of the job, both the property owner and/or contractor will be provided a final recycling report showing the overall recycling rate of the project.
Prior to issuance of Certificate of Occupancy or Final Inspection: The project’s final diversion report, to be approved by Burrtec, must be uploaded to your e-TRAKiT account through the City’s portal at:
https://etrakit.palmdesertegov.com/eTRAKiT/
A Certificate of Occupancy, Temporary Certificate of Occupancy, or Final Inspection will not be scheduled or issued without submitting a final approved diversion report from Burrtec to the City.
Self-Hauling
Clean-up companies and other haulers are not permitted to haul waste or recyclables from the City of Palm Desert without a Self-Hauling Permit. If you choose to self-haul any materials, including recyclables or trash:
When Applying for a Building Permit: When applying for a building permit, please make sure to include a completed CWMP, which must be provided to the City's Development Services Center. For free assistance and guidance in complying with State regulations, please contact the City of Palm Desert’s District Environmental Coordinator at (760) 674- 1026 from Burrtec."
A Certificate of Occupancy, Temporary Certificate of Occupancy, or Final Inspection will not be scheduled or issued without submitting a final approved diversion report from Burrtec to the City.
REMINDER: Burrtec Waste & Recycling is the exclusive franchised hauler for the City of Palm Desert.
https://etrakit.palmdesertegov.com/eTRAKiT/
Construction Waste Management Plan City of Palm Desert - Building and Safety Division Phone (760)776-6435 ▪ Email: permitcenter@palmdesert.gov Website: https://www.palmdesert.gov
The City of Palm Desert adopted the 2022 California Green Building Standards Code as part of Ordinance 1388. This Code and Ordinance requires that builders/contractors recycle and/or salvage a minimum of 65% of the non- hazardous construction and demolition debris, or meet a local construction and demolition waste management ordinance, whichever is more stringent.
1. I have read and understand the scope of the City of Palm Desert's Construction Waste Management Program. (Initial)
2. I understand that I am required by Palm Desert Ordinance No.1388 to recycle and/or salvage for reuse a minimum of 65% of the non-hazardous construction and demolition debris or meet a local recycling and waste ordinance, whichever is more stringent. (Initial)
3. I understand that I am required by Palm Desert Ordinance No.1388 to recycle and/or salvage for reuse a minimum of 100% diversion of land-clearing debris (i.e., dirt, rock, landscape material. ___________(Initial)
4. I understand that failure to meet the requirements of Ordinance No.1388 shall constitute a misdemeanor and shall be punishable by imprisonment in the county jail for up to 6 months, or by a fine of up to $1000, or both. In addition, a stop order on the job or a delay of final approval may occur. (Initial)
5. At the completion of this project, or more frequently if required, all receipts or other equivalent documentation from salvage, recycling, and waste facilities will be coordinated with Burrtec. I understand that I may not be issued my final inspection unless all the final diversion report from Burrtec is submitted to the Building and Safety Division. (Initial)
This Construction Waste Management Plan (CWMP) must be completed with a building permit application to obtain a building permit. Separate CWMPs must be completed for demolition if conducted before a building permit is issued. Only one CWMP is necessary if demolition and construction are under the same permit.
Applicant’s Name:
Contact Phone Number:
Check One: Contractor
Email:
Owner/Builder Other:
Project Description:
Permit#
Project Address:
Date of Application:
STEP 1: PROJECT INFORMATION – FILL OUT THE FOLLOWING INFORMATION
mailto:%20permitcenter@palmdesert.gov https://www.palmdesert.gov/
STEP TWO: DETERMINE MATERIALS TO BE PRODUCED AND WHERE THEY WILL BE
REUSED, RECYCLED, OR DISPOSED
Check the materials you anticipate generating and how it will be used or disposed.
MATERIALS
Check
Applicable Items
Reuse Recycle Disposal Facility
Appliances
Asphalt
Cardboard/Paper
Concrete
Drywall
Metals
Roofing (non-asphalt)
Wood/Green Waste
Other:
Other:
Materials can only be hauled by the contractor (No Subcontracting) or by the City’s franchise waste hauler: Burrtec Waste & Recycling Services.
I will be self-hauling materials to a Reuse, Recycling, or Disposal Facility.
I I will be contracting with Burrtec Waste & Recycling Services to haul materials.
The undersigned hereby agrees to comply with the Construction Waste Management Plan as submitted and is the owner or authorized agent of this project.
Applicant Signature: Date:
| Management Program: |
| a local recycling and waste ordinance whichever is more stringent: |
| material: |
| approval may occur: |
| from Burrtec is submitted to the Building and Safety Division: |
| Applicants Name: |
| Contact Phone Number: |
| Email: |
| OwnerBuilder: Off |
| Other: |
| Check the materials you anticipate generating and how it will be used or disposed: |
| Appliances: |
| undefined_3: |
| undefined_4: |
| undefined_5: |
| undefined_6: |
| Asphalt: |
| undefined_7: |
| undefined_8: |
| undefined_9: |
| undefined_10: |
| CardboardPaper: |
| undefined_11: |
| undefined_12: |
| undefined_13: |
| undefined_14: |
| Concrete: |
| undefined_15: |
| undefined_16: |
| undefined_17: |
| undefined_18: |
| Drywall: |
| undefined_19: |
| undefined_20: |
| undefined_21: |
| undefined_22: |
| Metals: |
| undefined_23: |
| undefined_24: |
| undefined_25: |
| undefined_26: |
| Roofing nonasphalt: |
| undefined_27: |
| undefined_28: |
| undefined_29: |
| undefined_30: |
| WoodGreen Waste: |
| undefined_31: |
| undefined_32: |
| undefined_33: |
| undefined_34: |
| Other_2: |
| undefined_35: |
| undefined_36: |
| undefined_37: |
| undefined_38: |
| Other_3: |
| undefined_39: |
| undefined_40: |
| undefined_41: |
| undefined_42: |
| Date: |
| undefined_48: |
| Check Box2: Off |
| Check Box3: Off |
| Check Box4: Off |
| Text1: |
| Text2: |
| Text3: |
File details come from the government source that posted it. Updated .