SECTION 013300 – SUBMITTAL PROCEDURES PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Submittal procedures.
B. Proposed products list.
C. Product Data.
D. Shop Drawings.
E. Samples.
F. Test reports.
G. Certificates.
H. Manufacturer's instructions.
I. Manufacturer's field reports.
J. Erection drawings.
K. Safety procedures manual.
1.2 SUBMITTAL PROCEDURES
A. Deliver submittals to the Contracting Officer’s Representative (COR).
B. Drawings, instruction manuals, and other submittals shall be in the English language.
C. Shop Drawings and manufacturers' information submitted shall be accompanied by completed copies of Submittal Transmittal Form, as provided by the COR. This form may also be available on disk. Reproduce any additional copies required. Submit three copies of Submittal Transmittal Form for initial submittals and re-submittals.
D. Sequentially number the transmittal form. Revise submittals with original number and a sequential alphabetic suffix.
E. Information under “Engineer's/Architect's Action” will be completed by the COR.
F. Schedule submittals to expedite the Project, and deliver to the COR. Coordinate submission of related items.
G. For each submittal for review, allow 15 days excluding delivery time to and from the Contractor.
H. Identify variations from Contract Documents and product or system limitations which may be detrimental to successful performance of the completed Work.
I. Notify the COR in writing, at time of submission, of any deviations in submittals from requirements of Contract Documents. Any such deviations permitted by the COR will require modifications of Contract Documents.
J. Shop drawings shall not be used as media for inquiries for information or for verification of information that must be supplied by others to Contractor. Inquiries or verification of information shall be made by separate Contractor submittal using Request for Information (RFI) process.
K. Begin no fabrication or Work which requires submittals until return of submittals by the COR with Engineer stamp, as either "Reviewed" or Reviewed as Noted."
1.3 PROPOSED PRODUCTS LIST
A. Within 15 days after Contract award, the contractor shall submit a list of major products proposed for use, with name of manufacturer, trade name, and model number of each product.
B. For products specified only by reference standards, give manufacturer, trade name, model or catalog designation, and reference standards.
1.4 PRODUCT DATA
A. Product Data: Submit to the COR for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents. Provide copies and distribute in accordance with article “Submittal Procedures” and for record documents purposes described in Section 01780.
B. Submit the number of copies which the Contractor requires, plus two copies which will be retained by the COR.
C. Mark each copy to identify applicable products, models, options, and other data.
Supplement manufacturers' standard data to provide information specific to this Project.
1.5 SHOP DRAWINGS
A. Submit to the COR for review for the limited purpose of checking for conformance to information given and the design concept expressed in the Contract Documents. Produce copies and distribute in accordance with article “Submittal Procedures” and for record documents purposes described in Section 01780.
B. Sheet size: A3 minimum; A1 maximum.
C. Make submittals to the COR promptly in accordance with approved schedule, and in such sequence as to cause no delay in Work or in work of any other contractor.
D. Number of submittals required:
1. Shop Drawings: Submit three opaque reproductions of each Shop Drawing.
E. Submittals shall contain:
1. Date of submission and dates of any previous submissions.
2. Project title and number.
3. Contract identification.
4. Names of
a. Contractor.
b. Supplier.
c. Manufacturer.
1.6 SAMPLES
A. Submit to the COR for review for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents. Produce duplicates and distribute in accordance with article “Submittal Procedures” and for record documents purposes described in Section 01780.
B. Samples for selection as specified in product sections (where applicable):
1. Submit to the COR for aesthetic, color, or finish selection.
2. Submit samples of finishes from the full range of manufacturers' standard colors, textures, and patterns for the COR selection.
3. After review, produce duplicates and distribute in accordance with article “Submittal Procedures” and for record documents purposes described in Section 01780.
C. Samples will not be used for testing purposes unless specifically stated in the specification section.
1.7 TEST REPORTS
A. Submit test reports for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.
1.8 CERTIFICATES
A. When specified in individual specification sections, submit certification by the manufacturer, installation/application subcontractor, in quantities specified for Product Data.
B. Certificates may be recent or previous test results on material or product, but must be acceptable to the COR.
1.9 ERECTION DRAWINGS
A. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the Contract Documents.
B. Data indicating inappropriate or unacceptable Work may be subject to action by the COR.
1.10 SAFETY PROCEDURES MANUAL
Prepare and submit, as part of the contractor’s proposal, safety procedures manual defining Contractor's safety program for work on site. Manual shall comply with the latest version of the COE standards (EM385-1-1), which can be obtained through the following link: http://www.usace.army.mil/SafetyandOccupationalHealth/SafetyandHealthRequirementsManual.aspx.
This submittal must be reviewed and approved by the technical evaluation panel as part of the proposal evaluation, and part of the contract documents.
A. The safety Program shall include the following as a minimum:
1. Safety responsibilities of Contractor's personnel.
2. Description of Contractor's safety program.
3. Requirements of use of personal protective equipment (PPE).
4. General safety-related rules of conduct.
5. Fire prevention measures.
6. Accident reporting procedures.
7. Procedures for hot work (welding, cutting, etc.), overhead work, and work in enclosed, confined spaces (tank, boiler, etc.).
B. The contractor shall assign a qualified safety inspector, full time on site, to ensure that all work are being conducted in accordance with the approved safety program. A resume of the safety inspector shall be included in the contractor’s proposal as part of his management plan. The COR will have the right to stop the working activities in the event that the contractor is violating the approved safety program, until the violation is rectified. Duration of stopping the work will not be compensated for in the contract schedule.
1.11 COR DUTIES
A. Review required submittals with reasonable promptness and in accordance with schedule, only for general conformance to design concept of Project and compliance with information given in Contract Documents. Review shall not extend to means, methods, sequences, techniques, or procedures of construction or to safety precautions or program incident thereto. Review of a separate item as such will not indicate approval of assembly in which item functions.
B. Affix stamp and initials or signature, and indicate requirements for re-submittal, or review of submittal. The COR's action on submittals is classified as follows:
1. Reviewed: Submittal has been reviewed and appears to be in conformance to design concept of Project and Contract Documents. Contractor may proceed with fabrication of work in submittal.
2. Reviewed As Noted: Submittal has been reviewed and appears to be in conformance to design concept of Project and Contract Documents, except as noted by the COR. Contractor may proceed with fabrication of work in submittal with modifications and corrections as indicated by the COR.
3. Resubmit: Submittal has been reviewed and appears not to be in conformance to design concept of Project or with Contract Documents. Contractor shall not proceed with fabrication of work in submittal, but instead shall make any corrections required by the COR and resubmit for review.
4. Returned without Review: Submittal is being returned without having been reviewed because: 1) not required by Contract Documents; 2) grossly incomplete; 3) indicates no attempt at conformance to Contract Documents; 4) cannot be reproduced; 5) lacks Contractor's completed approval stamp; or 6) lacks design professional's seal when required by law or Contract Documents. If submittal is required by Contract Documents, Contractor shall not proceed with Work as detailed in submittal, but instead shall correct defects and resubmit for review.
5. For Information Only: Submittal has not been reviewed but is being retained for informational purposes only.
C. Return 1 copy of submittals to Contractor. Contractor shall make additional copies as required.
D. The COR's review of submittals shall not relieve Contractor from responsibility for any variation from Contract Documents unless Contractor has, in writing, called the COR's attention to such variation at time of submission, and the COR has given written concurrence pursuant to Contract Documents to specific variation, nor shall any concurrence by the COR relieve Contractor from responsibility for errors or omissions in submittals.
PART 2 - PRODUCTS
(NOT USED) PART 3 - EXECUTION
3.1 CONTRACTOR'S REVIEW
Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to the COR.
3.2 COR'S ACTION
Action Submittals: The COR will review each submittal, make marks to indicate corrections or modifications required, and return it.
Informational Submittals: The COR will review each submittal and will not return it, or will reject and return it if it does not comply with requirements. The COR will forward each submittal to appropriate party.
The contractors shall submit, as part of their bid:
1. Qualification Data: For the contractor to demonstrate their capabilities and experience in similar project in type and scale. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, project costs and scopes summary, and other information specified.
2. Qualification data for the project manager and site engineer.
3. The preliminary project schedule.
4. Special work procedures
5. Quality Control and Assurance program and plan
6. Safety Program and plan.
7. List of all suppliers and sub contractors The contractor shall submit after contract award submittals as included in specification sections
END OF SECTION 013300
SUBMITTAL PROCEDURES