012600_-_CONTRACT_MODIFICATION_PROCEDURES_5-2014.docx

DOCX document 19 KB Posted

Attached to
Construction Services, Electrical Upgrade at the American Embassy Cairo, Egypt
Solicitation number
SGE500-14-R-0059
Issued by

About this file

OBO Specifications

View the file

Other files

File Type Posted
017800-Closeout_Submittal_5-2014.docx DOCX document
Solicitation _SGE500-14-R-0059.pdf PDF
013300__SUBMITTAL_PROCEDURES_5-2014.docx DOCX document
Protective_Devices_Coordination_Study_TechSpecs_JULY_2012.pdf PDF
262700_Wiring_Devices_ _Disconnectors_TechSpecs_JULY_2012.pdf PDF
263623_Automatic_Transfer_Switch_TechSpecs_JULY_2012.pdf PDF
012300_-_ALTERNATES_5-2014.docx DOCX document
014000-QUALITY_REQUIREMENTS_5-2014.docx DOCX document
Payment_ILC.pdf PDF
260500_Basic_Electrical_Materials_and_Methods _July_2012.pdf PDF
092400_Portland_Cement_Plaster_5-2014.docx DOCX document
260526_Earthing_Systems_TechSpecs_JULY_2012.pdf PDF
262413_Low_Voltage_Switchboards_TechSpecs_JULY_2012.pdf PDF
016000-_PRODUCT_REQUIREMENTS_5-2014.docx DOCX document
017000_Execution_Requirements_5-2014.docx DOCX document
013200_-_CONSTRUCTION_PROGRESS_DOCUMENTATION_5-2014.docx DOCX document
261400_RMU_TechSpecs_JULY_2012.pdf PDF
262416_Panel_Boards_TechSpecs_JULY_2012.pdf PDF
Breakdown_of_Proposal_Prices-Maadi_11-11_June_2014.xls XLS spreadsheet
Breakdown_of_Proposal_Prices-Maadi_55-17_June_2014.xls XLS spreadsheet
099123_Paint_5-2014.docx DOCX document
Breakdown_of_Proposal_Prices-FBOZ_June_2014.xls XLS spreadsheet
Performance_Guarantee_ILC.pdf PDF
265000_Lighting_TechSpecs_JULY_2012.pdf PDF
013000-_Administrative_Requirements_5-2014.docx DOCX document
011000_-_SUMMARY_5-2014.doc DOC document
260519_LV_Cables_TechSpecs_JULY_2012.pdf PDF
OCPD_ _Cable_Select_Check_Acc_NEC_JULY_2012.pdf PDF
RFP _signed.pdf PDF
OIG_Employee_Interview_Questionnaire.pdf PDF
260533_Conduit_ _Raceways_TechSpecs_JULY_2012.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

GENERAL

SECTION INCLUDES

This Section specifies administrative and procedural requirements for handling and processing Contract modifications.

MINOR CHANGES IN THE WORK

The Contracting Officer Representative (COR) will supplement instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time.

PROPOSAL REQUESTS

Embassy Initiated Proposal Requests: The Contracting Officer Representative (COR) will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

Proposal Requests issued by the COR are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.

After receipt of Proposal Request, the contractor shall submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change to the Contracting Officer.

Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

CHANGE ORDER PROCEDURES

On the COR’s approval of a Proposal Request, the Contracting Officer will issue a Change Order for signatures of the Contractor.

Where applicable, requirements of contract documents apply to change orders or alteration and amendment works in same manner as for the work under this contract.

END OF SECTION 01250

CONTRACT MODIFICATION PROCEDURES

Housing Compounds Electric Upgrade 5-2014 012600/ 1