013000-_Administrative_Requirements_5-2014.docx

DOCX document 25 KB Posted

Attached to
Construction Services, Electrical Upgrade at the American Embassy Cairo, Egypt
Solicitation number
SGE500-14-R-0059
Issued by

About this file

OBO Specifications

View the file

Other files

File Type Posted
017800-Closeout_Submittal_5-2014.docx DOCX document
Solicitation _SGE500-14-R-0059.pdf PDF
013300__SUBMITTAL_PROCEDURES_5-2014.docx DOCX document
Protective_Devices_Coordination_Study_TechSpecs_JULY_2012.pdf PDF
262700_Wiring_Devices_ _Disconnectors_TechSpecs_JULY_2012.pdf PDF
263623_Automatic_Transfer_Switch_TechSpecs_JULY_2012.pdf PDF
012300_-_ALTERNATES_5-2014.docx DOCX document
014000-QUALITY_REQUIREMENTS_5-2014.docx DOCX document
Payment_ILC.pdf PDF
260500_Basic_Electrical_Materials_and_Methods _July_2012.pdf PDF
092400_Portland_Cement_Plaster_5-2014.docx DOCX document
012600_-_CONTRACT_MODIFICATION_PROCEDURES_5-2014.docx DOCX document
260526_Earthing_Systems_TechSpecs_JULY_2012.pdf PDF
262413_Low_Voltage_Switchboards_TechSpecs_JULY_2012.pdf PDF
016000-_PRODUCT_REQUIREMENTS_5-2014.docx DOCX document
017000_Execution_Requirements_5-2014.docx DOCX document
013200_-_CONSTRUCTION_PROGRESS_DOCUMENTATION_5-2014.docx DOCX document
261400_RMU_TechSpecs_JULY_2012.pdf PDF
262416_Panel_Boards_TechSpecs_JULY_2012.pdf PDF
Breakdown_of_Proposal_Prices-Maadi_11-11_June_2014.xls XLS spreadsheet
Breakdown_of_Proposal_Prices-Maadi_55-17_June_2014.xls XLS spreadsheet
099123_Paint_5-2014.docx DOCX document
Breakdown_of_Proposal_Prices-FBOZ_June_2014.xls XLS spreadsheet
Performance_Guarantee_ILC.pdf PDF
265000_Lighting_TechSpecs_JULY_2012.pdf PDF
011000_-_SUMMARY_5-2014.doc DOC document
260519_LV_Cables_TechSpecs_JULY_2012.pdf PDF
OCPD_ _Cable_Select_Check_Acc_NEC_JULY_2012.pdf PDF
RFP _signed.pdf PDF
OIG_Employee_Interview_Questionnaire.pdf PDF
260533_Conduit_ _Raceways_TechSpecs_JULY_2012.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01300 – ADMINISTRATIVE REQUIREMENTS PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Coordination and project conditions.

B. Project site administration.

C. Field engineering.

D. Site mobilization meeting.

E. Progress meetings.

1.2 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Verify utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment.

C. Coordinate space requirements, supports, and installation of mechanical and electrical Work which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

D. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements in the EMR.

E. Coordinate completion and clean-up of Work of separate sections in preparation for Substantial Completion.

1.3 PROJECT SITE ADMINISTRATION

A. Contractor shall provide competent, suitably qualified personnel to survey and lay out Work and perform construction as required by Contract Documents. Contractor shall at all times maintain good discipline and order at site.

B. Incompetent or incorrigible employees shall be dismissed from Work by Contractor or its representative when requested by the Contracting Officer’s Representative (COR), and such persons shall not again be permitted to return to Work without written consent of the COR.

ADMINISTRATIVE REQUIREMENTS

Housing Compounds Electric Upgrade 5-2014 013000/ 1

C. Workmanship shall be of high industry standards.

1.4 FIELD ENGINEERING

A. Provide field engineering services. Establish elevations, lines, and levels, utilizing recognized engineering survey practices.

1.5 SITE MOBILIZATION MEETING

A. The Embassy will schedule a meeting at the project site prior to Contractor’s occupancy.

B. Attendance required: Embassy, Contractor, Contractor's Superintendent, and major Subcontractors.

C. Agenda:

1. Distribution of Contract Documents.

2. Submission of list of Subcontractors, list of products, schedule of values, and progress schedule.

3. Designation of personnel representing the parties in Contract.

4. Procedures and processing of field decisions, submittals, and substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

5. Use of premises by the Embassy and Contractor.

6. Embassy’s requirements and occupancy.

7. Construction facilities and controls provided by the Embassy.

8. Temporary utilities provided by the Embassy.

9. Security and housekeeping procedures.

10. Schedules.

11. Application for payment procedures.

12. Procedures for maintaining record documents.

13. Inspection and acceptance of equipment put into service during construction period.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to the COR, participants, and those affected by decisions made.

1.6 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at maximum monthly intervals.

B. Make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

C. Attendance Required: Job superintendent, major subcontractors and suppliers, the COR, as appropriate to agenda topics for each meeting.

D. Agenda:

1. Review minutes of previous meetings.

2. Review of Work progress.

3. Field observations, problems, and decisions.

4. Identification of problems which impede planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of off-site fabrication and delivery schedules.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Coordination of projected progress.

11. Maintenance of quality and work standards.

12. Effect of proposed changes on progress schedule and coordination.

13. Other business relating to Work.

E. Record minutes and distribute copies within two days after meeting to participants, with two copies to the COR, participants, and those affected by decisions made.

PART 2 - PRODUCTS

(NOT USED) PART 3 - EXECUTION

(NOT USED)

END OF SECTION 013000