Attachment_7_Transition_Plan.pdf
PDF 202 KB Posted
- Attached to
- Audiovisual Support Services
- Solicitation number
- SFSIAQ17R0005
About this file
Transition Plan
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED//FOR OFFICIAL USE ONLY
Attachment 7 – Transition Plan
RFQ – SFSIAQ17QR0005
AV
Transition Plan
Criteria: The Contractor shall deliver a Transition Plan at proposal submission. The Offeror shall address a Transition in Plan (TIP) and a Transition Out Plan (TOP). The Offeror shall describe the transition methods, budget management, issues, resolutions, and communication plans. Assign an experienced Transition Project Manager(s) (this could be the Key Program Manager) to manage all aspects of the TIP to transfer knowledge, tools, documentation, equipment, processes and methodology from the current Contractors to the new Contractor and their team.
The TIP shall include, but not limited to:
A detailed work break-down structure with intermediate and major milestones
A list of all major milestones and deliverables
A list of costs associated with each major milestone
Processes and standards used to ensure meeting the objective of the Performance
Work Statement (PWS) during the transition
Testing Contractor operational processes for verification of full operational capability
Governance methods, to include regular reporting to FSI
Transition Out Plan (TOP), but not limited to:
Develop and provide a detailed TOP to be conducted at the time of non-renewal or termination of services that shall not exceed 45-calendar days in length. The TOP will be adjusted to align with the follow-on provider TIP. This plan shall identify, track and coordinate resolution of transition-related issues.
A detailed work break-down structure
Deliverables and description of deliverables
A related-staffing plan that shows the staffing requirements by milestone and skill and the status of the staffing plan
Identification of the Contractor’s staffing requirements by skill set and related hours/days
Identification of Contractor-required-transition tools and equipment
All transition-related Contractor personnel as needed to meet the milestones of the Transition Plan
A weekly status report to FSI/EX/AVF on the progress of the TOP, highlighting:
o Milestones Completed per TOP o Milestones missed or forecasted to be missed per TOP o Latest Forecast Completion Date of TOP o Escalated Issues and Up-to-the-Minute Status
Attachment 7 – Transition Plan
RFQ – SFSIAQ17QR0005
AV
Conduct the transition by cooperatively working with the follow-on provider to plan and conduct a coordinated transition-out without disruption or degradation of current service performance.
File details come from the government source that posted it. Updated .