This Scope of Work document outlines Phase IV upgrades to the primary power distribution system at Camp Blanding Joint Training Center, a project under the State of Florida Department of Military Affairs. The work consists of a base bid and seven alternate bid items (ABIs) addressing the 13,200V phase-to-ground and 22,860V phase-to-phase distribution system. The base bid encompasses approximately 109 line poles plus 3 stub poles across 16 project locations, including conductor installations ranging from 0.1 to 0.6 miles per location, with wire sizes specified as either three pulls of 4/0 aluminum ACSR for phase conductors and one pull of 1/0 aluminum ACSR for neutral, or alternatively three pulls of #2 aluminum ACSR for conductors and one pull of #2 aluminum ACSR for neutral. The alternate bid items include additional reframing, pole changeouts, and conductor work across 10 poles to 29 poles per item, with ABI #7 addressing transformer replacements consisting of 20 single-phase 25KVA pole mount units and 12 single-phase 50KVA pole mount units. The solicitation, issued June 25, 2026, carries an estimated construction cost of $1,800,000.00 and requires work to comply with Florida Building Code, State Fire Marshal requirements, and local authority having jurisdiction standards.
The contractor must provide all supervision, labor, materials, tools, equipment, disposal, and construction services necessary for completion. All hardware must be either Hubbell or Chance Hardware manufacturers or approved equivalents, with insulators rated at 27KV, dead-end insulators at 25KV polymer composition, and lightning arrestors at 18KV polymer composition installed no less than every third pole with ground rods achieving no greater than 25 Ohms resistance. The contractor is responsible for field verification of distances, pole locations, and utility effects prior to bidding and job commencement. All copper removed during the project remains the property of Camp Blanding and must be returned; other material designated as trash must be disposed of by the contractor. All outages require CBJTC project manager approval 72 hours in advance with a detailed outage schedule, and material submittals must receive approval before purchasing. The contractor must familiarize itself with Camp Blanding policies and procedures and ensure all installations comply with state, local codes, and applicable FP&L mounting and installation diagrams.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
FOR
PHASE IV
PRIMARY POWER
DISTRIBUTION SYSTEM UPGRADE
PURPOSE
The intent of this scope of work is to define the specifications required in order to perform a PHASE IV upgrade of the primary voltage power distribution system located on Camp Blanding. This project will entail a primary Base Bid plus ( ) Alternate Bid Items.
This Base Bid and Alternates will have their own specific attachment illustrating location by pole number and work to be performed.
The voltage of this distribution system is 13,200V phase-to-ground and 22,860V phase-to-phase.
GENERAL SCOPE
The primary Base Bid of this project will consist of work as outlined in their respective attachments. Attachments are broken down into segments illustrating approximate distance, approximate pole counts, locational references, and relative conductor sizing for those locations. Attachments will illustrate conductor wire sizes per the areas in which to be replaced.
The contractor is to provide all supervision, labor, material, tools, equipment, disposal and construction services necessary to complete but not limited to the work listed below.
Alternates consist of pole replacement counts plus conductor/neutral requirements for specified area.
Insulators, switches, preformed ties, and mounting hardware shall be sized accordingly for system voltage. All hardware will be either Hubbel or Chance Hardware manufacturers (or approved equivalent).
Locations of existing poles, verification of any potentially effected utilities, and distance measurements should be field verified by the contractor prior to bidding and job start.
NOTE: ANY AND ALL COPPER OF ANY SORT REMOVED DURING
THIS PROJECT WILL REMAIN THE PROPERTY OF THE OWENER,
CAMP BLANDING, AND RETURNED TO SUCH. CBJTC HAS THE
MATERIAL. MATERIAL DESIGNATED AS TRASH IS TO BE
DISPOSED OF BY CONTRACTOR.
Bidders will familiarize themselves with Camp Blandings policies and procedures before providing a proposal.
All material installation shall be installed per specification/recommendations. Material and installation are to also be in accordance with all state and local codes or the local authority having jurisdiction.
Contractor shall provide CBJTC project manager material submittals for approval before purchasing.
All outages will need to be approved by CBJTC 72 hours in advance along with an outage schedule.
STATEMENT OF WORK
POLES: 40/3, 35/3 Poles shall be sized and placed according to the corresponding attachments. The contractor shall be responsible for the disposal of any and all existing poles which are removed and replaced new. All poles have butt wrap pole ground #6 copper.
WIRE: Primary conductors and neutral on the Base Bid and alternates will be 4/0 for conductors and 1/0 for neutral or #2 aluminum ACSR as specified per location.
Wire shall have pre-formed ties. All switch jumpers will be #4 stranded copper.
FIELD VERIFICATION OF TOTAL DISTANCE PER DESIGNATED
AREA BY CONTRACTOR IS NECESSARY.
ANCHORING:
diameter shall be 5/16
HARDWARE: All pole insulators shall be rated at 27KV. Dead end insulators will be rated at 25 KV and be of polymer composition. Lightning arrestors shall be of polymer composition and rated at 18 KV. Contractor shall ensure lightning arrestor assemblies are installed no less than every third pole with required ground rod(s) to meet a measured Ohm resistance reading of no greater than 25 Ohms. The remaining hardware (switches, mounting hardware, etc.) shall be sized accordingly ne voltage. Fiber or Steel crossarms will be 8 ft. in length. New gang switches supplied by contractor will match switches on hand by Camp Blanding as follows: Chance; Type: D7; Cat: D7PS2AL. All hardware will be installed in their perspective locations per the corresponding attachments and in accordance with accompanying Florida Power & Light (FP&L) mounting and installation diagrams. HARDWARE LOCATIONS/TYPES SHOULD BE
FIELD VERFIED BY CONTRACTOR PRIOR TO BIDDING AND JOB
COMMENCEMENT.
BASE BID
All wire to be installed in this section and in these locations shall be accomplished with either three pulls of 4/0 aluminum ACSR for phase conductors and one pull of 1/0 aluminum ACSR for the neutral for a total approximate distance of .3 miles (x4) OR three pulls of #2 aluminum ACSR for conductors and one pull of #2 aluminum ACSR for neutral for a total approximate distance of .12 miles (x4). All inclusive poles within this section are to be replaced for a total count of 109 ea.
Line poles plus 3 ea. stub poles ). Following are locations and approximate distances:
1. Yerkes Rd Existing OH Line Replace 18 existing poles and add 4 new poles on Yerkes Rd from Duval Road to Stevens Lake Rd (gate); pull in 2 additional conductors of #2 acsr
2. Stevens Lake Rd (gate) to OP Dickson New OH Line Install 32 new poles with appropriate hardware and lightning arrestors along Treat Rd from Stevens Lake Rd (gate) to OP Dickson compound; pull in 4 conductors of #2 acsr (3 phases, 1 neutral)
3. C
(3) 4/0 Pri. (1) 1/0 N 14 Poles & Wire Distance = .3 Miles Pole # 5702 VD1 Fig 2 (100A Blades) Pole #5711 E3 Fig 1 Pole #5704 E3 Fig 2 Pole #5712 E1 Fig 1 (Single Pole)
Pole #5705 E3 Fig 1 Pole #5713 E1 Fig 1 Pole #5706 E1 Fig 2 Pole #5714 E1 Fig 1 (delete 1 pole) Pole #5707 E1 Fig 1 Pole #5715 E1 Fig 1 Pole #5708 E3 Fig 1 (Reframe Only) Pole #5716 E1 Fig 1 Pole # 5710 E1 Fig 1 Pole #5717 ED1 Fig 3(Reframe Only)
4. L (5720)
(2) #2 Pri. (1) #2 N 2 Poles & Wire Distance = .1 Miles
Pole #5720 E1 Fig 2 Pole #5721 ET2 Fig 3
5. Hillsborough 30 DE Pole 5717 to ASP (5763)
(1) #2 Pri (1) #2 N Re-conduct only #2 ACSR 9 Poles & Wire Distance = .3 Miles Pole #5763 UH1 Fig 1 Pole #5768 E1 Fig 1 Pole #5764 E1 Fig 1 Pole #5774 ET Fig 1 Pole #5765 E1 Fig 2 Pole #5775 ET Fig 1 Pole #5766 E1 Fig 1 Pole #5820 Single Phase Dead End
6. Pole Change out 40/3 & Re-Conduct #2 ACSR .5 Miles
(3) Pri #2 ACSR (1) N
Pole #5767 ET Fig 1
7. Avon Park to Quincy Ave
(3) Pri #2 ACSR (1) N 10 Poles Pole #4980 E1 Fig 1 Pole #4985 E1 Fig 1 Pole #4981 E1 Fig 2 Pole #4986 E1 Fig 1 Pole #4982 E1 Fig 1 Pole #4987 E1 Fig 1 Pole #4983 E1 Fig 1 Pole #5850 ET 2 Fig 2 W/ Anchors
Pole #4984 E3 Fig 1 Pole #5851 Del
8. Plant City to Avon Park
(3) Pri #2 ACSR (1) N 3 Poles Pole #4990 E1 Fig 2 Pole #4991 ET2 Fig 2 Single Phase Pole #4992 ED1 Fig 3 Single Phase
9. Bonifay St to Quincy Ave Pole change out & reframe 40/3 & Re-conduct #2 ACSR Pole
(3) Pri #2 ACSR (1) N 12 Poles= .3 Miles Pole #4743 E1 Fig 2 Pole #4779 E1 Fig 2 Pole #4744 E1 Fig 1 Pole #4780 ED2 Fig 1 Backside 1/0 Pole #4777 E1 Fig 1 Pole #4781 ET2 Fig 2 Backside 1/0 Pole #4778 E2 Fig 4 Pole #4782 ET2 Fig 2 1/0 DE
10. Plant City to Bonifay St
(3) Pri #2 ACSR (1) N Pole #4880 E1 Fig 1 1/0 Pole #4882 ED1 Fig 3 1/0 &Stub 35/3 Pole #4881 E1 Fig 1 1/0 Pole #4883 ET 2 Fig 2 1/0 w/ Trans
11. Bartow & Sarasota Pole change out 40/3 YC
(3) Pri #2 ACSR (1) N 14 Poles = .3 Miles Pole #3801 ET2 Fig 3 Pole #3815 ET2 Fig 1 Pole #3814 ED2 Fig 1 Pole #3819 ET2 Fig 3 Pole #3821 ET2 Fig 1 Pole #3822 E3 Fig 2 Pole #3831 ET2 Fig 1 & Service Stub 35/3 Pole #3832 E1 Fig 1 Pole #3840 ED1 Fig 1 & Service Stub 35/3
12. (To Close Loop, YC) New Built, Pole change out & #2 re-conduct W. Palm Beach
(3) Pri #2 ACSR (1) N Pole #3840 ED1 Fig 3 Pole #3874 E1 Fig 1 Pole #3841 E1 Fig 1 Pole #3875 E1 Fig 1 Pole #3842 E2 Fig 2
13. Pole change out & reframe 40/3 & re-conduct #2 ACSR Wire from Sarasota to Well #3890 4 Poles = .1 Miles
(3) Pri #2 ACSR (1) N Pole #3880 E1 Fig 1 Pole #3890 E1 Fig 2 Pole #3881 ED1 Fig 3 Pole #3891 ET2 Fig 2
14. -conduct #2 ACSR from 2708 to 2715
(3) Pri #2 ACSR (1) N 9 Poles = .2 Miles Pole #2709 ET 1 Fig 1 Pole #2712 ET Fig 1 Pole #2710 E1 Fig 2 Pole #2713 ET1 Fig 1 Pole #2711 ET1 Fig 1 Pole #2714 E1 Fig 2
15. Recreation Department, Pole change out
(3) Pri #2 ACSR (1) N Pole #1530 ET2 Fig 2
16. Conference Center, Pole change out
(3) Pri #2 ACSR (1) N Pole #1515 E1 Fig 1 Pole #1516 ET2 Fig 2
ALTERNATE JOBS
ABI #1
Reframe from Duval to Yerkes (Hardware and Transfer)
(3) Pri #2 ACSR (1) N 10 Poles = .6 Miles
Pole #4909 E1 Fig 1 Pole #6001 E1 Fig 2
Pole #4910 E2 Fig 3 Single Phase take off
Pole #4911 E1 Fig 2 Pole #6002 E1 Fig1
Pole #4920 E1 Fig 1 Pole #6003 E1 Fig1
Pole #4921 E1 Fig 1 Pole #6005 E1 Fig 1
Pole #6000 E1 Fig 1
ABI #2
Yerkes Rd pole change out 40/3
(3) Pri #2 ACSR (1) N 16 Poles = 1.5 Miles
Pole #6500 ED1 Fig 3 Stub 35/3, 2 LAD w/Switch
Pole #6604 E1 Fig 1
Pole #6605 VD1 Fig 2 (100A Blades)
Pole #6607 E1 Fig 2
Pole #6608 ET1 Fig 1
Pole #6612 ET1 Fig 1 (Reframe Only)
Pole #6616 ET1 Fig 1 (Reframe Only)
Pole #6622 ET1 Fig 1 (Reframe Only)
Pole #6624 E1 Fig 2 Pole #6634 E1 Fig 1
Pole #6630 E1 Fig 2 Pole #6635 E1 Fig 1
Pole #6631 E3 Fig 1 Pole #6636 E1 Fig 2
Pole #6633 E1 Fig 2 Pole #6637 ET1 Fig 1
ABI #3
(5750)
(3) #2 Pri (1) #2 N 1 Pole & Wire Distance = 1 Span
Pole #5750 ET2 Fig 3 Re-conduct #2 ACSR & Pole 40/3
ABI #4
#4317-#4321
(3) 4/0 Pri, (1) 1/0 N 5 poles-wire only = .1 Miles
Pole #4317 Pole #4318 Pole #4319 Pole #4320 Pole #4321
ABI #5
(2) 4/0 Pri, (1) 1/0 N 7 Poles-Wire only = .3 Miles
Pole #4234
Pole #4235
Pole #4236
Pole #4237
Pole #4238
Pole #4230
ABI #6
(OR)
within this section are to be replaced for a total count of 29 ea. Plus 1 stub.
Cocoa Street needs upgraded to 4/0 wire pri 1/0 N wire & poles. Wire 4234 to 4239.
29 Poles, 1 Stub = .39 Miles
Pole #04 E3 Fig 1 Pole #3285 E1 Fig 2
Pole #05 E3 Fig 1 Pole #3288 E1 Fig 2
Pole #06 E1 Fig 2 Pole #3289 E1 Fig 1
Pole #07 E1 Fig 1 Pole #4201 E1 Fig 1
Pole #08 ED1 Fig3 Pole #4203 E1 Fig 1
Pole #09 E1 Fig 2 Pole #4206 E1 Fig 1
Pole #11 E3 Fig 1 Pole #4208 E1 Fig 2
Pole #3128 X1 Fig 1 Pole #4210 E1 Fig 1
Pole #3201 E1 Fig 1 Pole #4212 ED1 Fig 3 & Stub 35/3
Pole #3203 ER1 Fig 1 Pole #4240 E1 Fig 2
Pole #3205 E1 Fig 1 Pole #4241 E3 Fig 1
Pole #3207 E1 Fig 3 Pole #4244 UH1 Fig 1
Pole #3209 XD1 Fig 1 Pole #4245 ED1 Fig 1
Pole #3280 ED1 Fig 3
Pole #3281 E1 Fig 2
Pole #3283 E1 Fig 1
ABI #7
Transformer replacements Single Phase Pole Mount 25KVA - Quantity - 20 Single Phase Pole Mount 50KVA - Quantity - 12