- Solicitation number
- ITB-16334
- Issued by
- St. Johns County, Florida
About this file
This Addendum #1 to the Invitation to Bid is issued by the Florida Department of Military Affairs, Construction & Facility Management Office for Project 225164, the Camp Blanding Joint Training Center Power Distribution Upgrade. The addendum modifies the original solicitation issued June 25, 2026, which requested sealed bids from qualified licensed general or electrical contractors for a primary power distribution system upgrade at the facility located at 5629 State Road 16 West, Starke, Florida. The project includes a base bid and seven alternate bid items covering approximately 113 line poles plus 3 stub poles across 16 locations, with scope items encompassing conductor installations using aluminum ACSR wire in sizes ranging from #2 to 4/0, pole reframing, pole replacements, and transformer replacements (20 single-phase 25KVA and 12 single-phase 50KVA pole-mount units). The addendum removes Base Bid Item #2 (Stevens Lake Road to OP Dickson overhead line installation with 32 new poles) from the project scope. The original bid opening date of August 26, 2026 at 2:00 PM in St. Augustine remains unchanged. Potential bidders who attended the mandatory pre-bid/site visit meetings held July 14-15, 2026 may request additional site visits by contacting CBJTC DPW Construction. The addendum includes 42 numbered questions and answers addressing bidder inquiries regarding material specifications, working hours (Monday-Friday, 7:00 AM-4:30 PM), lead times, scope clarifications, payment schedules, security requirements, and compliance obligations.
The estimated construction cost is $1.8 million with performance and labor and material payment bonds equal to 100% of contract sum required. Bidders must include anticipated material cost escalation within bid pricing, as change orders for material price fluctuations will not be permitted; no upfront funding, mobilization payments, or material payments are available, though contractors may request payment upon material delivery to the site. Prequalification is required for bids exceeding $500,000 (Level Five), and contractors must hold current Florida state contractor licensing, maintain an active office within 300 road miles of the project, and secure a letter of intent from a bonding company. Progress payments are made at 95% of completed work with payment issued upon completion of individual jobs based on an estimated monthly draw schedule coinciding with the schedule of values. All work must be performed as energized work without outages unless specifically approved by CBJTC 72 hours in advance. All copper and demolition materials removed during the project remain the property of Camp Blanding Joint Training Center with CBJTC having right of first refusal on all removed materials. Substantial completion is required within 150 calendar days of Notice to Proceed, with liquidated damages assessed at $360 per day. The contractor is responsible for obtaining and paying for all local building permits except State Fire Marshal permits, verifying all measurements and quantities with no additional funds provided for shortages, and furnishing all materials and equipment. Remanufactured or certified refurbished transformers are acceptable if they carry warranty equal to or greater than new transformers.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Army National Guard
Construction & Facility Management Office
ISSUED ADDENDUM
Rev. 11/2018
Date 8/10/2026
ADDENDUM Number 1
Project Number and Name 225164 CBJTC Power Distribution Upgrade
Invitation to Bid Date June 25, 2026
Number of Attachments 3
Bid Opening Date and Time:
No Change
Bid Opening – August 26, 2026 (2 PM – St.
Augustine)
From: Department of Military Affairs, CFMO Contracting Office
Addendum #1 – BIDDERS MUST ACKNOWLEDGE THIS ADDENDUM IN THE
PROPOSAL INCLUDED IN THE INVITATION TO BID.
ADDITIONAL SITE VISITS: ALL potential bidders that attended one or both of the Mandatory Pre-Bid/Site Visit meetings may request to revisit the job site by sending an email to CBJTC DPW Construction ng.fl.flarng.list.cbjtc-dpw-construction@army.mil for CBJTC gate access.
SCOPE CHANGES (See Attached Revised Scope of Work)
1. Base Bid Item #2 has been deleted from the project “Stevens Lake Rd (gate) to OP Dickson. New OH Line Install 32 new poles with appropriate hardware and lightning arrestors along Treat Rd from Stevens Lake Rd (gate) to OP Dickson compound; pull in 4 conductors of #2 acsr (3 phases, 1 neutral)”
REVISED PROPOSAL / LIST OF SUBCONTRACTORS FORM. BIDDERS MUST USE
THIS FORM!!
QUESTIONS FROM BIDDERS:
Q1 - Is there a material sheet and field print that can be provided to bidders.
A1A - We do not have an actual “field print” other than the (figs./images) attachments that were already included with the project’s advertisement
A1B - Attached is a material sheet with some of the material part numbers that are related to the project, but this parts list does not cover all required mailto:ng.fl.flarng.list.cbjtc-dpw-construction@army.mil material. A submittal / data sheet will still be required from all material / equipment used on the project.
Q2 – Please confirm the working hours at CBJTC for this project
A2 – Monday through Friday 7 AM – 4:30 PM. Currently there are no days at this point that the contractor cannot work, there will be portions of this work that will require CBJTC staff to be present and will need to be scheduled and approved by CBJTC PM. CBJTC will make every possible effort to work with the contractors and their schedule with the understanding that the contractor is subjected to Camp Blanding’s normal day to day activities and other requirements the staff has on post. *With this being a military facility, bidders need to be aware that at any given time they could be asked to stop work and leave post, it is unlikely that that will happen but possible.
Q3 -- A bidder mentioned that there is a 52 week lead time on the transformers.
A3 - After contract execution, the contractor will need to identify any long lead items and get those items ordered ahead of their Notice to Proceed if need be, mentioned in both pre-bid meetings to help with lead times, Camp Blanding will accept certified refurbished transformers as long as they carry the same or greater warranty as a new transformer.
Q4 -- Job 2: Please confirm that this job is no longer part of the bid package.
A4 – Confirmed – this Job has been removed Q5 -- Job 5: Please confirm that this job consists of reconductoring only and does not include a pole replacement.
A5 – Reconduct only – no pole replacement
Q6 - ABI 1: Please confirm that this job consists of reframing and transferring only, with no pole replacement or reconductoring A6 – Confirmed - no pole replacement or reconductoring
Q7 -- ABI 2: Please confirm that this job consists of pole replacements and reframing only, with no reconductoring.
A7 – Confirmed – pole replacements and reframing only, no reconductoring
Q8 -- ABI 4: Please confirm that this job consists of reconductoring only, with no pole replacements.
A8 – Confirmed – reconduct only
Q9 -- ABI 5: Please confirm that this job consists of reconductoring only, with no pole replacements.
A9 – Confirmed – reconduct only
Q10 - ABI 6: The last sentence states, "Cocoa Street needs upgraded to 4/0 primary wire, 1/0 neutral wire and poles. Wire 4234 to 4239." The reconductoring of Cocoa Street appears to already be included under ABI 5 – Cocoa Street and D Avenue - 7 Poles, Wire only - Poles 4234, 4235, 4236, 4237, 4238, 4230. Please confirm whether this is additional work or if it is already included under ABI 5.
A10A—Yes, this is already included under ABI 5, with the correction of pole #4239 instead of # 4230
If it is included under ABI 5, should the associated pole replacements for Cocoa Street mentioned in ABI 6 also be included under ABI 5, or are they intended to remain under
ABI 6?
A10B -- All references to Cocoa Street and associated poles are noted in ABI5 and will be removed from ABI 6. ABI 6 (Front Gate to “D”…) will stand alone as ABI 6.
Additionally, please verify the location of poles 04, 05, 06, 07, 08, 09, and 11, as all other pole numbers throughout the bid package appear to use four-digit identifiers. Pole #’s are correct (as 2 digit numbers); See Map below with pole locations highlighted
Please also confirm that, other than the Cocoa Street reconductoring question, ABI 6 consists of pole replacements only and does not include any additional reconductoring.
A10C – ABI 6 consists of upgraded poles and frame only Q11 - Could you please clarify the payment schedule?
Will payment be issued upon completion of each individual job, or only after the entire bid package has been completed?
A11 – The selected contractor will provide an “Estimated Payment Draw Schedule” which will indicate the estimated monthly draw amount, coinciding with the schedule of values and the work completed within the reporting time period.
Q12-- Due to the fluctuation in material pricing, supplier quotations are typically only valid for 15 to 30 days. If material pricing changes after the bid is submitted, will change orders be permitted to account for these increases, or should bidders include anticipated material cost escalation within their bid pricing?
A12- Bidders should include anticipated material cost escalation within their bid pricing
Q13 -- Additionally, please advise whether any upfront funding, mobilization payment, or material payment will be provided to help offset the cost of procuring materials and mobilizing the project prior to completion.
A13 – There is no upfront funding, mobilization payment, or material payment.
The contractor may request payment as soon as materials are delivered to the site.
Q14 -- Will the Owner / Camp Blanding Joint Training Center (CBJTC) provide dedicated security or facility escorts for contractor personnel while working in restricted or secure areas, or is the contractor required to arrange/budget for escort personnel?
A14 – Dedicated security or escort are not required
Q15 -- Is Cybersecurity Maturity Model Certification (CMMC 2.0) compliance or specific DFARS cybersecurity clauses required for contractors or subcontractors performing on this contract?
A15 -- NO
Q16 -- Please confirm whether FAR/DFARS requirements, OCI disclosures, Representations & Certifications, and NIST SP 800-171 / SPRS reporting apply to this solicitation.
A16 – Not Required
Q17 -- Is the Owner utilizing a commercial vehicle contract or specialized procurement mechanism that allows general or electrical contractors to bid directly as a prime vendor?
A17 -- NO
Q18 -- Does the Davis-Bacon Act apply? If federal funds are used, please issue the applicable DOL Wage Determination by addendum.
A18 – Davis Bacon Act does not apply to this project.
Q19 -- Clarify material responsibility and identify any hardware approved for reuse.
A19 – Defined in Scope of Work
Q20 -- Provide the complete copper retention clause from the SOW.
A20 – Any and all copper of any sort removed during this project will remain the property of the Owner (Camp Blanding Joint Training Center) and returned to CBJTC Project Manager. CBJTC has the Right of First Refusal on ALL demolished or removed material. Material designated as trash is to be disposed of by the Contractor.
Q21 -- Provide transformer locations/specifications and confirm whether remanufactured transformers are acceptable.
A21 -- YES if certified and have a warranty equal or greater than a new one. (This is a 2 part question with only one part answered). Locations should have been verified by the contractor during pre-bid.
Q22 -- Provide conductor sizes, route lengths, cable pulls, and wire quantities.
A22 -- Per SOW- Contractor is responsible for verifying all measurement, no additional funds will be provided for shortages
Q23 -- Reconcile Base Bid pole count discrepancy (109 vs approximately 131).
A23 -- Base Bid is 109 poles – Scope Of Work will be updated
Q24 – Confirm Base Bid Item 2 Remains In Scope.
A24 -- Base Bid Item #2 has been removed
Q25 -- Issue corrected SOW pages with complete location names.
A25 -- Updated SOW will be posted in the Addendum
Q26 -- Clarify conductor transfer/new conductor requirements and reusable hardware for
ABI 1.
A26 – The contractor is adding 2 additional conductors to the poles being replaced in the base bid #1
Q27 -- Define 'LAD' and provide BOM for Poles 6500 & 6605.
A27 – LAD stands for lateral---BOM for 6500 & 6605 are shown in SOW beside those pole numbers, reference Fig # drawing.
Q28 -- Verify Pole 4230/4239 and identify missing 7th pole.
A28 -- See Scope of Work 7th pole is a stub pole
Q29 -- Reverify ABI 6 route length.
A29 - Contractor is responsible for verifying all measurement, no additional funds will be provided for shortages
Q30 -- Confirm whether Cocoa Street / Poles 4234–4239 belong to ABI 5 or ABI 6.
A30 - Cocoa Street belongs to ABI #5 – removed from ABI #6
Q31 -- The General Scope states “All outages will need to be approved by CBJTC 72 hours in advance along with an outage schedule.” During the Pre-Bid Site Visit Meeting it was discussed that some of this work may have to be performed as hot or energized work. Please define which work areas that must be performed as hot or energized work without outages.
A31 - For biding purposes expect all areas to be energized work.
Q32 -- The Invitation To Bid states that the Contractor shall obtain and include all costs for required permits necessary for completion of this project from all authorities having jurisdiction. During the Pre-Bid Site Visit Meeting it was discussed that Environmental, Railroad and Utility Locates Permits will be obtained by CBJTC. Please define what other permits and authorities having jurisdiction will be needed for this project’s work.
A32 - None
Q33 -- Is the contractor responsible for furnishing all materials and equipment?
A33 – Yes
Q34 -- Which existing hardware may be reused instead of replaced?
A34 – None
Q35 -- What is the correct Base Bid pole quantity: 109 line poles plus three stubs, or approximately 131 poles shown in the individual sections?
A35 -- Base Bid Pole quantity is 113 poles; SOW has been updated to reflect each pole
Q36 -- Under ABI #1, how many existing conductors are to be transferred A36 -- ALL & Re-sag
Q37 -- How many new conductors are to be installed, and which existing hardware may be reused?
A37 – None
Q38 -- On ABI 2, What does “LAD” mean at pole 6500, and what complete equipment is required at poles 6500 and 6605?
A38-- LAD stands for lateral---BOM for 6500 & 6605 are shown in SOW beside those pole numbers, reference Fig # drawing.
Q39 -- . What are the correct seven pole numbers for ABI #5, and should pole 4230 actually be pole 4239?
A39 - Per Scope of Work
Q40 -- What is the correct ABI #6 route and length, since the SOW states 0.39 mile but our field measurement is approximately 1.12 miles?
A40 - Contractor is responsible for verifying all measurement, no additional funds will be provided for shortages.
Q41 -- Which alternate, ABI #5 or ABI #6, includes the pole and conductor work between poles 4234 and 4239?
A41 -- ABI #5 includes the pole and conductor work – this has been removed from ABI #6 on the updated SOW
Q42 -- What are the exact pole locations and specifications for the 32 replacement transformers, and are approved rebuilt or remanufactured transformers acceptable?
A42 – Yes if certified and has a warranty equal or greater than a new one.
Attachments:
1. Addendum #1
2. Pre-Bid Meeting Agenda Sign In Sheets
3. Revised Scope of Work
4. Revised Proposal and Subcontractor
Procurement Schedule remains unchanged. Bid Opening Remains – August 26, 2026 (2 PM
– St. Augustine)
END OF ADDENDUM #1