RRSFS Solicitation 090220.pdf
PDF 812 KB Posted
- Attached to
- RIDGWAY RESERVOIR SPILLWAY FISH SCREEN
- Solicitation number
- 140R4020R0018
About this file
This solicitation is for a Ridgway Reservoir Spillway Fish Screen project. The Bureau of Reclamation seeks construction services including concrete work, earthwork, riprap installation, and fabrication and installation of a fish screen structure and debris boom. Offerors must submit proposals by October 8, 2020. The period of performance is from December 5, 2020 to December 31, 2021. The total estimated value of the project is between $1,000,000 to $5,000,000. This is a total small business set-aside. The solicitation includes specifications, provisions, and clauses for requirements related to mobilization, payments, subcontracting limitations, safety, cultural resources, and more.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. 140R4020R0018 Ridgway Reservoir Spillway Fish Screen
Ridgway Reservoir Spillway Fish Screen
SOLICITATION NO. 140R4020R0018
UNITED STATES DEPARTMENT OF THE INTERIOR
BUREAU OF RECLAMATION
UPPER COLORADO REGION
SALT LAKE CITY, UTAH
This Solicitation is a Total Small Business Set-Aside.
Solicitation Closing Date: October 08, 2020
Solicitation Closing Time: 14:00 (2:00 PM) Mountain Daylight Time
Printed proposals must be delivered to:
BUREAU OF RECLAMATION
ATTN: Joshua Dunham
Western Colorado Area Office-Grand Junction
445 West Gunnison, Suite 221
Grand Junction, CO 81501
Proposals must be received by the Contracting Officer no later than 14:00 hours (2:00 PM)
MDT on or before October 08, 2020 to be considered for award.
Proposals must be clearly labeled with the following naming scheme:
*Proposal – Company Name 140R4020R0018 – Ridgway Reservoir Spillway Fish Screen*
In addition to hard copy proposals, electronic copy of proposals is required.
Inquiries regarding this Solicitation should be made to:
Dwane D. Esplin, Contract Specialist / Contracting Officer
E-mail: desplin@usbr.gov
All correspondence regarding this Solicitation should reference Ridgway Reservoir Spillway Fish
Screen Solicitation No. 140R4020R0018 in the subject line.
Site Visit: For Site Visit information, please see section L, FAR CLAUSE 52.236-27 A1.
Deadline for Questions: Offerors must submit all technical questions to Dwane D. Esplin at desplin@usbr.gov no later than September 21, 2020 - 12:00 PM (MDT)
ONLY WRITTEN QUESTIONS WILL RECEIVE A RESPONSE. Each question submitted must reference the solicitation number (140R4020R0018) and the specific section, clause, paragraph, or drawing. Reclamation will post an amendment to Beta.SAM.gov to all questions with answers which may affect proposals.
Please read Section M - Provision WBR 1452.215-82 Technical Proposal Instructions – Bureau of
Reclamation thoroughly for evaluation of proposal and award information.
NOTE: Vendors are required to submit printed proposals in three clearly marked volumes as outlined in WBR 1452.215-81 - General Proposal Instructions – Bureau of Reclamation. Failure to submit a three-volume proposal with the appropriate number of copies or format may eliminate the proposal from being reviewed or considered.
mailto:desplin@usbr.gov i
Table of Contents
SECTION A – SF-1442
SECTION B – SUPPLIES OR SERVICES AND PRICES
B.1 SCHEDULE
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
SECTION D – PACKAGING AND MARKING
SECTION E - INSPECTION AND ACCEPTANCE
E.1
E.2
SECTION F - DELIVERIES OR PERFORMANCE
F.1
F.2
F.3
SECTION G - CONTRACT ADMINISTRATION DATA
G.1
G.2
G.3
G.4
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H.1
SECTION I - CONTRACT CLAUSES
I.1
I.2
I.3
I.4
I.5
I.6
I.7
I.8
I.9
I.10
I.11 ii
I.12
I.13
I.14
I.15
I.16
I.17
I.18
I.19
I.20
I.21
I.22
I.23
I.24
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF
OFFERORS
K.1
K.2
K.3
K.4
K.5
K.6
K.7
K.8
K.9
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
L.1
L.2
L.3
L.4
L.5
L.6
L.7 iii
L.8
L.9
L.10
L.11
L.12
L.13
L.14
L.15
L.16
L.17
L.18
L.19
L.20
L.21
SECTION M - EVALUATION FACTORS FOR AWARD
M.1
M.2
(END OF PROVISIONS)
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
Bureau of Reclamation
Upper Colorado Region
Regional Office 125 South State Street, Room 8100
R40
Salt Lake City UT 84138
Dwane Esplin 801-524-3743
1x 09/03/2020
140R4020R0018
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Ridgway Reservoir Spillway Fish Screen
See Final Specifications and Drawings in their entirety.
The estimated magnitude of this project is between $1,000,000 and $5,000,000.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 381 calendar days and complete it within ________________ ________________ calendar days after receiving
10/08/2020
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Bureau of Reclamation Upper Colorado Region
Regional Office 125 South State Street, Room 8100
R40
Salt Lake City UT 84138
Dwane D. Esplin
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 90
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140R4020R0018
Legacy Doc #: BOR
Delivery: 12/31/2021
Delivery Location Code: 0009910014
Bureau of Reclamation-UC-WCAO
445 West Gunnison Ave Suite 221
Grand Junction CO 81501 US
Period of Performance: 12/05/2020 to 12/31/2021
00010 Ridgway Reservoir Spillway Fish Screen
Price Schedule - CLINs 1 through 14
Product/Service Code: Y1PZ
Product/Service Description: CONSTRUCTION OF
OTHER NON-BUILDING FACILITIES
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES
B.1 SCHEDULE
(a) Offers will be considered for award on the following Price Schedule.
(1) Offerors shall complete Price Schedule. Offers for less than a complete Price
Schedule will be considered nonresponsive and will not be evaluated for award.
Please refer to provision 52.204-22 Alternative Line Item Proposal if necessary.
(2) The Government will evaluate offers for award purposes based on the total price of Price Schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) Quantities in the Price Schedule are estimated quantities for comparison of offers only. Except as provided in the contract clause at FAR 52.211-18, Variation in
Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated
Quantity does not apply to lump sum items.
(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and
Preparatory Work, for CLIN 1.
(e) Definitions:
(1) CLIN – Contract Line Item Number.
END OF SCHEDULE
CLIN Section Supplies or Services Quantity Unit Unit Price Amount
1 WBR 1452.232-81 Mobilization and Preparatory Work $0.00
2 01 31 19 Project Management and Coordination $0.00
3 01 71 20 Surveying $0.00
4 02 41 07 Modification of Existing Cable Guardrail $0.00
5 03 33 00 Concrete for Fish Screen 380 cubic yards $0.00 $0.00
6 03 33 00 Lean Concrete Grout for Riprap 245 cubic yards $0.00 $0.00
7 03 64 00 Earthwork for Structure $0.00
8 31 23 11 Excavation of Unsuitable Material 150 cubic yards $0.00 $0.00
9 33 11 15 Compacted Select Backfill 150 cubic yards $0.00 $0.00
10 35 21 94 Chinking for Riprap 185 tons $0.00 $0.00
11 35 22 15 Fish Screen Structure Fabrication $0.00
12 35 22 15 Fish Screen Structure Erection $0.00
13 35 22 80 Debris Boom Fabrication $0.00
14 35 22 80 Debris Boom Installation $0.00
$LINE NO. 00010 - PRICE SCHEDULE TOTAL:
PRICE SCHEDULE
For the lump sum of
For the lump sum of
For the lump sum of
For the lump sum of
For the lump sum of
For the lump sum of
For the lump sum of
For the lump sum of
For the lump sum of
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
SEE ATTACHMENT 1 FOR THE SPECIFICATIONS IN THEIR ENTIRETY.
SECTION D – PACKAGING AND MARKING
THERE ARE NO CLAUSES INCLUDED IN THIS SECTION
SECTION E - INSPECTION AND ACCEPTANCE
E.1 52.246-12 INSPECTION OF CONSTRUCTION AUG 1996
(a) Definition - "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The
Contractor shall maintain complete inspection records and make them available to the
Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not -
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the
Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary.
The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may -
(1) By contract or otherwise, replace or correct the work and charge the cost to the
Contractor; or
(2) Terminate for default the Contractor's right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the
Contractor shall defray the expenses of the examination and of satisfactory reconstruction.
However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the
Government's rights under any warranty or guarantee.
(End of clause)
E.2 52.246-21 WARRANTY OF CONSTRUCTION MAR 1994
(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.
(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.
(c) The Contractor shall remedy at the Contractor's expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor's expense any damage to
Government-owned or controlled real or personal property, when that damage is the result of:
(1) The Contractor's failure to conform to contract requirements; or
(2) Any defect of equipment, material, workmanship, or design furnished.
(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor's warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.
(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.
(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor's expense.
(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall-
(1) Obtain all warranties that would be given in normal commercial practice;
(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and
(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.
(h) In the event the Contractor's warranty under paragraph (b) of this clause has expired, the
Government may bring suit at its expense to enforce a subcontractor's, manufacturer's, or supplier's warranty.
(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government nor for the repair of any damage that results from any defect in
Government-furnished material or design.
(j) This warranty shall not limit the Government's rights under the Inspection and
Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.
SECTION F - DELIVERIES OR PERFORMANCE
F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND
COMPLETION OF WORK
APR 1984
The Contractor shall be required to:
(a) Commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) Prosecute the work diligently, and (c) Complete the entire work ready for use not later than December 31, 2021. The time stated for completion shall include final cleanup of the premises. The completion date is based on the assumption that the successful offeror will receive the notice to proceed by January 30, 2021. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
(End of clause)
F.2 52.211-12 LIQUIDATED DAMAGES -- CONSTRUCTION SEP 2000
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $2,850.00
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of Clause)
F.3 52.211-18 VARIATION IN ESTIMATED QUANTITY APR 1984
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the
Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgment of the Contracting Officer, is justified.
SECTION G - CONTRACT ADMINISTRATION DATA
G.1 1452.201-70 AUTHORITIES AND LIMITATIONS SEP 2011
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction
(written or oral) that the Contractor considers in excess of the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the
COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting
Officer or the COR acting within his or her appointment, shall be at the Contractor’s risk.
G.2 WBR
1452.201-80
CONTRACTING OFFICER’S
REPRESENTATIVE’S AUTHORITIES AND
LIMITATIONS -- BUREAU OF
RECLAMATION
MAY 2018
(a) Performance of the work under this contract shall be subject to the technical direction of the
Reclamation Contracting Officer's Representative (COR). The term “technical direction” is defined to include, without limitation:
(1) Inspecting and accepting or rejecting work performed under the contract.
(2) Representing the Government in technical phases of the work. The COR is responsible for the technical administration of the contract and will provide instructions and interpretations to the
Contractor on all technical matters relating to the contract. The COR will supervise or oversee all
Government technical and administrative personnel assigned to assist the COR.
(3) Reviewing and, where required by the contract, approving submittals of technical data, shop drawings, samples, literature, plans, or other data required to be delivered by the Contractor to the Government.
(b) The Contractor will receive a copy of the written COR designation from the Contracting
Officer. It will specify the extent of the COR's authority to act on behalf of the Contracting
Officer.
(c) Technical direction must be within the scope of work stated in the contract. Only the
Contracting Officer is authorized to determine if a change is within the scope of the contract;
therefore, the COR does not have the authority to, and may not, issue any technical direction that
(1) Constitutes a direction of additional work outside the Contract requirements;
(2) Constitutes a change as defined in the contract clause entitled “Changes;”
(3) In any manner causes an increase or decrease in the total contract cost, or the time required for contract performance;
(4) Changes any of the expressed terms, conditions or specifications of the contract; or
(5) Interferes with the Contractor's right to perform the terms and conditions of the contract.
(d) All technical direction shall be issued in writing by the COR.
(e) The Contractor must proceed promptly with the performance of technical direction duly issued by the COR in the manner prescribed by this clause and within its authority under the provisions of this clause. If, in the opinion of the Contractor, any instruction or direction by the
COR falls within one of the categories defined in (c)(1) through (c)(5) of this clause, the
Contractor must not proceed and must notify the Contracting Officer in writing within five (5) working days after receipt of any such instruction or direction and must request the Contracting
Officer to modify the contract accordingly. Upon receiving the notification from the
Contractor, the Contracting Officer must -
(1) Advise the Contractor in writing after receipt of the Contractor's letter that the technical direction is within the scope of the contract effort and does not constitute a change under the Changes clause of the contract; or
(2) Advise the Contractor that the Government will issue a written change order.
(f) A failure of the Contractor and Contracting Officer either to agree that the technical direction is within the scope of the contract or to agree upon the contract action to be taken with respect to the technical direction will be subject to the provisions of the clause entitled “Disputes.”
G.3 DOI-AAAP
ELECTRONIC INVOICING AND PAYMENT
REQUIREMENTS - INVOICE PROCESSING
PLATFORM (IPP)
APR 2013
Payment requests must be submitted electronically through the U. S. Department of the
Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the
Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
In order for payment, the contractor submits and electronic copy of their business invoice to
Joshua Dunham, the Contracting Officer Representative (COR), by electronic mail at jdunham@usbr.gov to evaluate the submitted invoice and will provide approval by emailing the contractor with an attached signed invoice. The COR may also reject the invoice; in this case, an email will be provided to the contractor with detailed information to revise the invoice as needed for approval. Failure to email the invoice may cause significant delay or possible rejection of your payment request.
https://www.ipp.gov/ mailto:jdunham@usbr.gov
Once the approved invoice is received, the contractor uploads, as an attachment, a copy of the approved invoice with the COR’s signature, PRIOR to clicking “submit” in IPP. Please send a copy to the Contracting Officer, Dwane D. Esplin at desplin@usbr.gov. Please refer to FAR 32.905(b) for proper invoicing information.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of clause)
G.4 WBR
1452.242-80
POST AWARD CONFERENCE BUREAU OF
RECLAMATION
JULY 1993
(a) Prior to the Contractor starting work, a post award conference (as described in FAR Subpart 42.5), will be convened by the contracting activity or contract administration office. The Contractor's Project Manager shall attend the conference. If the contract involves subcontractors, a representative of each major subcontractor is also required to attend.
(b) The conference will be held at location below but may be subject to change:
Reclamation’s office located at 445 West Gunnison Ave., 1st
Floor Conference Room, Grand Junction, CO 81501.
(c) The Contracting Officer and the Contractor will agree to the date and time of the conference after award of the contract. In event of a conflict in schedules, the Contracting Officer shall establish the date for the conference.
The Contractor shall include any associated costs for attendance at the conference in its offer.
(End of clause) mailto:desplin@usbr.gov mailto:ippgroup@bos.frb.org
SECTION H - SPECIAL CONTRACT REQUIREMENTS
H.1 DOI-AAAP
NOTICE TO CONTRACTORS -
CONTRACTOR PERFORMANCE
ASSESSMENT REPORTING SYSTEM
DEC 2015
(a) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance
Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
(b) The past performance evaluation process is a totally paperless process using CPARS.
CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance
Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
(c) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
(d) When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available athttps://www.cpars.gov/.
(e) Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible athttps://www.cpars.gov/.
(1) Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
(2) Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
(3) All information provided should be reviewed for accuracy prior to submission.
(4) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
(5) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, http://www.cpars.gov/ http://www.cpars.gov/ https://www.cpars.gov/ the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
(6) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
(f) The following guidelines apply concerning your use of the past performance evaluation:
(1) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the
CO for instructions.
(2) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
(3) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
(g) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
(h) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
SECTION I - CONTRACT CLAUSES
I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE FEB 1998
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
FAR Clauses - https://www.acquisition.gov/far/
CLAUSE TITLE DATE
52.202-1 Definitions JUN 2020
52.203-3 Gratuities APR 1984
52.203-5 Covenant Against Contingent Fees MAY 2014
52.203-6 Restrictions on Subcontractor Sales to the Government JUN 2020
52.203-7 Anti-Kickback Procedures JUN 2020
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity MAY 2014
52.203-12 Limitation on Payments to Influence Certain Federal
Transactions
JUN 2020
52.203-13 52.203-13 Contractor Code of Business Ethics and Conduct. JUN 2020
52.203-17 Contractor Employee Whistleblower Rights and Requirement
To Inform Employees of Whistleblower Rights
JUN 2020
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements
JAN 2017
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber
Content Paper
MAY 2011
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
JUN 2020
52.204-13 System for Award Management Maintenance OCT 2018
52.204-14 Service Contract Reporting Requirements OCT 2016
52.204-18 Commercial and Government Entity Code Maintenance JUL 2016
52.204-19 Incorporation by Reference of Representations and
Certifications
DEC 2014
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky
Lab and Other Covered Entities
JUL 2018
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment
AUG 2020
52.209-6
Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for
Debarment
JUN 2020
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
OCT 2018
https://www.acquisition.gov/far/
52.209-10 Prohibition on Contracting With Inverted Domestic
Corporations
NOV 2015
52.215-2 Audit and Records – Negotiation JUN 2020
52.215-8 Order of Precedence—Uniform Contract Format OCT 1997
52.215-11 Price Reduction for Defective Certified Cost or Pricing Data--
Modifications.
JUN 2020
52.215-13 Subcontractor Certified Cost or Pricing Data-Modifications JUN 2020
52.215-19 Notification of Ownership Changes OCT 1997
52.215-21 Requirements for Certified Cost or Pricing Data and
Data Other Than Certified Cost or Pricing Data –
Modifications
JUN 2020
52.219-6 Notice of Total Small Business Set-aside MAR 2020
52.219-8 Utilization of Small Business Concerns OCT 2018
52.219-14 Limitations on Subcontracting MAR 2020
52.219-28 Post-Award Small Business Program Representation MAY 2020
52.222-3 Convict Labor JUN 2003
52.222-4 Contract Work Hours and Safety Standards --
Overtime Compensation
MAY 2018
52.222-6 Construction Wage Rate Requirements AUG 2018
52.222-7 Withholding of Funds MAY 2014
52.222-8 Payrolls and Basic Records AUG 2018
52.222-9 Apprentices and Trainees JUL 2005
52.222-10 Compliance with Copeland Act Requirements FEB 1988
52.222-11 Subcontracts (Labor Standards) MAY 2014
52.222-12 Contract Termination-Debarment MAY 2014
52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988
52.222-15 Certification of Eligibility MAY 2014
52.222-21 Prohibition of Segregated Facilities APR 2015
52.222-26 Equal Opportunity SEP 2016
52.222-27 Affirmative Action Compliance Requirements for Construction
APR 2015
52.222-35 Equal Opportunity for Veterans
JUN 2020
52.222-36 Equal Opportunity for Workers with Disabilities
JUN 2020
52.222-37 Employment Reports on Veterans JUN 2020
52.222-40 Notification of Employee Rights Under the National
Labor Relations Act
DEC 2010
52.222-50 Combating Trafficking in Persons JAN 2019
52.222-54 Employment Eligibility Verification OCT 2015
52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015
52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2017
52.223-2 Affirmative Procurement of Biobased Products Under
Service And Construction Contracts
SEP 2013
52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011
52.223-6 Drug-Free Workplace MAY 2001
52.223-17 Affirmative Procurement of EPA-Designated Items in
Service and Construction Contracts
AUG 2018
52.223-18 Encouraging Contractor Policies to Ban text Messaging While Driving
JUN 2020
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008
52.227-1 Authorization and Consent JUN 2020
52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement
JUN 2020
52.227-4 Patent Indemnity-Construction Contracts DEC 2007
52.227-23 Rights to Proposal Data (Technical) JUN 1987
52.227-14 Rights in Data-General MAY 2014
52.228-2 Additional Bond Security OCT 1997
52.228-5 Insurance -- Work on a Government Installation JAN 1997
52.228-11 Pledges of Assets AUG 2018
52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014
52.228-14 Irrevocable Letter of Credit NOV 2014
52.228-15 Performance and Payment Bonds - Construction OCT 2010
52.229-3 Federal, State And Local Taxes FEB 2013
52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014
52.232-16 A1 Progress Payments – Alternate I JUN 2020
52.232-17 Interest MAY 2014
52.232-23 Assignment of Claims MAY 2014
52.232-27 Prompt Payment for Construction Contracts JAN 2017
52.232-33 Payment by Electronic Funds Transfer-- System for
Award Management
OCT 2018
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013
52.232-40 Providing Accelerated Payments to Small
Business Subcontractors
DEC 2013
52.233-1 A1 Disputes - Alternate I (December 1991) MAY 2014
52.233-3 Protest After Award AUG 1996
52.233-4 Applicable Law for Breach of Contract Claim OCT 2004
52.236-3 Site Investigation and Conditions Affecting the Work APR 1984
52.236-5 Material and Workmanship APR 1984
52.236-6 Superintendence by the Contractor APR 1984
52.236-7 Permits and Responsibilities NOV 1991
52.236-8 Other Contracts APR 1984
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984
52.236-11 Use and Possession Prior to Completion APR 1984
52.236-12 Cleaning Up APR 1984
52.236-13 Accident Prevention NOV 1991
52.236-15 Schedules for Construction Contracts APR 1984
52.236-16 Quantity Surveys APR 1984
52.236-17 Layout of Work APR 1984
52.236-21 A1 Specifications and Drawings for Construction -
Alternate I (April 1984)
FEB 1997
52.236-26 Preconstruction Conference FEB 1995
52.242-13 Bankruptcy JUL 1995
52.242-14 Suspension of Work APR 1984
52.243-4 Changes JUN 2007
52.243-6 Change Order Accounting APR 1984
52.244-2 Subcontracts JUN 2020
52.244-6 Subcontracts for Commercial Items JUN 2020
52.248-3 Value Engineering – Construction APR 1984
52.249-2 A1 Termination for Convenience of the Government (Fixed- Price)
- Alternate I (September 1996)
APR 2012
52.249-10 Default (Fixed-Price Construction) APR 1984
52.253-1 Computer Generated Forms JAN 1991
I.2 52.223-3 AI HAZARDOUS MATERIAL
IDENTIFICATION AND MATERIAL
SAFETY DATA-ALTERNATE I (JUL 1995)
JAN 1997
(a) “Hazardous material,” as used in this clause, includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract).
(b) The offeror must list any hazardous material, as defined in paragraph (a) of this clause, to be delivered under this contract. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number.
This information shall also be included on the Material Safety Data Sheet submitted under this contract.
Material
(If none, insert “None”)
Identification No.
(c) This list must be updated during performance of the contract whenever the Contractor determines that any other material to be delivered under this contract is hazardous.
(d) The apparently successful offeror agrees to submit, for each item as required prior to award, a
Material Safety Data Sheet, meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous material identified in paragraph (b) of this clause. Data shall be submitted in accordance with Federal Standard No. 313, whether or not the apparently successful offeror is the actual manufacturer of these items. Failure to submit the Material Safety Data Sheet prior to award may result in the apparently successful offeror being considered non-responsible and ineligible for award.
(e) If, after award, there is a change in the composition of the item(s) or a revision to Federal
Standard No. 313, which renders incomplete or inaccurate the data submitted under paragraph
(d) of this clause, the Contractor shall promptly notify the Contracting Officer and resubmit the data.
(f) Neither the requirements of this clause nor any act or failure to act by the Government shall relieve the Contractor of any responsibility or liability for the safety of Government, Contractor, or subcontractor personnel or property.
(g) Nothing contained in this clause shall relieve the Contractor from complying with applicable
Federal, State, and local laws, codes, ordinances, and regulations (including the obtaining of licenses and permits) in connection with hazardous material.
(h) The Government’s rights in data furnished under this contract with respect to hazardous material are as follows:
(1) To use, duplicate and disclose any data to which this clause is applicable. The purposes of this right are to --
(i) Apprise personnel of the hazards to which they may be exposed in using, handling, packaging, transporting, or disposing of hazardous materials;
(ii) Obtain medical treatment for those affected by the material; and
(iii) Have others use, duplicate, and disclose the data for the Government for these purposes.
(2) To use, duplicate, and disclose data furnished under this clause, in accordance with subparagraph (h)(1) of this clause, in precedence over any other clause of this contract providing for rights in data.
(3) The Government is not precluded from using similar or identical data acquired from other sources.
(i) Except as provided in paragraph (i)(2), the Contractor shall prepare and submit a sufficient number of Material Safety Data Sheets (MSDS’s), meeting the requirements of 29 CFR
1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous materials identified in paragraph (b) of this clause.
(1) For items shipped to consignees, the Contractor shall include a copy of the MSDS’s with the packing list or other suitable shipping document which accompanies each shipment.
Alternatively, the Contractor is permitted to transmit MSDS’s to consignees in advance of receipt of shipments by consignees, if authorized in writing by the Contracting Officer.
(2) For items shipped to consignees identified by mailing address as agency depots, distribution centers or customer supply centers, the Contractor shall provide one copy of the MSDS’s in or on each shipping container. If affixed to the outside of each container, the MSDS’s must be placed in a weather resistant envelope.
I.3 52.223-9 ESTIMATE OF PERCENTAGE OF
RECOVERED MATERIAL CONTENT FOR
EPA DESIGNATED ITEMS
MAY 2008
(a) Definitions. As used in this clause—
“Postconsumer material” means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”
“Recovered material” means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this contract, shall—
(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of postconsumer material content; and
(2) Submit this estimate to the Contracting Officer.
I.4 52.225-9
BUY AMERICAN--CONSTRUCTION
MATERIALS
MAY 2014
(a) Definitions. As used in this clause-
Commercially available off-the-shelf (COTS) item-
(1) Means any item of supply (including construction material) that is-
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material” means an article, material, or supply brought to the construction site by the
Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means-https://www.acquisition.gov/content/2101-definitions#i1125359
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means-
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if-
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
"Foreign construction material” means a construction material other than a domestic construction material.
"United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a…
This is the start of the file's text. The full file is on GovTribe.