REVISED_-_00_42_13_-_PROPOSAL_FORM_-_Addendum_1.pdf
PDF 87 KB Posted
- Solicitation number
- RFP #26063
- Issued by
- Greenville County, South Carolina
About this file
This is a Proposal Form (Addendum 1) issued by Greenville County, South Carolina for construction earthwork at the Twin Chimneys Landfill MSW Unit 4 Cell 5 project. The project encompasses excavation of approximately 160,000 cubic yards of miscellaneous soil, clay, and rock material from a 12.5-acre site, with materials to be stockpiled in designated on-site locations. Major work items include clearing and grubbing (1.3 acres), erosion and sediment control, structural fill placement (7,500 cubic yards), temporary sediment basin decommissioning, access road construction with geotextile (4,750 square yards) and stone (3,100 tons), erosion control matting installation (3,000 square yards), and seeding of 12 acres. The proposal submission deadline is February 9, 2026, at 3:00 PM, with contract award anticipated on February 20, 2026, and a Notice to Proceed targeted for March 16, 2026. The project timeline allows 150 days for substantial completion. Proposals will be evaluated on five equally weighted criteria (20 percent each): responsiveness to the RFP requirements, proposed project schedule, similar project experience (minimum two projects in the last five years), cost, and equipment specifications.
Pricing for this project is structured with both lump sum line items (bonds, insurance, mobilization, construction quality control, survey and control, clearing and grubbing, erosion and sediment control, temporary sediment basin decommissioning) and unit price items (crush and haul rock at estimated 300 cubic yards, miscellaneous soil excavation at 167,000 cubic yards, clay at 10,000 cubic yards, rock at 8,000 cubic yards, structural fill, access road geotextile, access road stone, erosion control matting, and seeding). Proposers are responsible for independent verification of quantities and providing unit prices consistent with industry norms; unit prices that appear inconsistent with typical market rates may result in a non-responsive rating if not satisfactorily justified. A Bid Bond equal to 5 percent of the bid price is required, along with Performance and Payment Bonds equal to the total bid price due within 15 working days of award. Comprehensive insurance requirements include $1,000,000 General Liability per occurrence, $1,000,000 Automobile Liability, statutory Worker's Compensation, $1,000,000 Umbrella/Excess Liability, and $1,000,000 Professional Errors and Omissions, with Greenville County named as an additional insured. Liquidated damages are assessed at approximately $1,000 per day for failure to achieve substantial completion and $500 per day for final completion delays.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HDR Project No. 10404585 Greenville County February 2026 Twin Chimneys MSW Unit 4 Cell 5 Landfill Earthwork Issued For Proposals
PROPOSAL FORM
00 42 13 - 1 Addendum 1
SECTION 00 42 13
PROPOSAL FORM
PROJECT IDENTIFICATION: Twin Chimneys Landfill MSW Unit 4 Cell 5 Earthwork
THIS PROPOSAL IS SUBMITTED TO: Mr. Robert Brewer, Director, Procurement Services Division, Greenville County, hereinafter referred to as OWNER.
1. PROPOSAL PRICE
A. The Base Proposal Schedule in the following section outlines all major components of the Work required to complete the project as specified.
B. The Proposer is directed to the Base Proposal Schedule and Measurement and Basis for Payment for a narrative description of each item in the Base Proposal Schedule.
C. The quantities outlined below represent an approximation as estimated by the Engineer. All quantities depicted in the Base Proposal Schedule, represent in-place, constructed quantities (as constructed in the proposed Work). The Proposer is responsible for verifying quantities for bidding. Engineer’s estimated quantities are provided for informational purposes only and are not to be relied upon as the sole basis for the Proposal.
D. Lump sum line items will constitute the total payment for the Work.
E. Unit price items will be measured and payment will be for the actual quantity.
In the event the Owner desires to modify the quantity (reduce or increase) of work for one or more lump sum Proposal Schedule line items during construction, the general basis for establishing the corresponding change in contract price will be to divide the lump sum bid price by the Engineer’s estimated quantity, thereby yielding a unit price by which to modify the line item total price. Other methods for price adjustment may be considered at the Owner’s and Engineer’s discretion.
2. BASE PROPOSAL SCHEDULE
A. PROPOSER will complete the Work in accordance with the Contract Documents for the following prices:
Item
Description
Estimated
Quantity
Units
Payment
Total Cost
1. Bonds, Insurance, and Mobilization 1 LS LS $_____________
2. Construction Quality Control 1 LS LS $_____________
3. Survey and Control 1 LS LS $_____________
4.
Crush and Haul Existing Surface Rock
300 CY $_________/CY $_____________
5. Clearing and Grubbing 1.3 AC LS $_____________
6.
Erosion and Sediment Control and Maintenance
1 LS LS $_____________
7. Excavation
PROPOSAL FORM
00 42 13 - 2 Addendum 1
Item
Description
Estimated
Quantity
Units
Payment
Total Cost
7a. Miscellaneous Soil 167,000 CY $_________/CY $_____________
7b. Clay 10,000 CY $_________/CY $_____________
7c. Rock 8,000 CY $_________/CY $_____________
8. Structural Fill 7,500 CY $_________/CY $_____________
9.
Temporary Sediment Basin A Decommissioning
1 EA LS $_____________
10. Access Road – Geotextile 4,750 SY $_________/SY $_____________
11. Access Road – Stone 3,100 TON $_________/TON $_____________
12. Erosion Control Matting 3,000 SY $_________/SY $_____________
13. Seeding 12 AC $_________/AC $_____________
TOTAL BASE PROPOSAL PRICE IN NUMBERS $
IN WORDS
3. MEASUREMENT AND BASIS FOR PAYMENT
The line items below provide further description of the Work listed in the Proposal Schedule. Some of the line items include approximate quantities as estimated by the ENGINEER. The CONTRACTOR shall not rely on the quantities given but shall instead estimate all quantities independently as required to complete the Proposal. The price associated with each Lump Sum item shall be the full compensation paid for the Work described, regardless of the ENGINEER’s or CONTRACTOR’s estimated quantity. For Lump Sum items, no claim shall be made by the CONTRACTOR for deviations between the CONTRACTOR's estimated quantity and the actual quantity required to complete the Work described.
A. Base Proposal Schedule:
1. BONDS, INSURANCE, AND MOBILIZATION: This Work shall consist of securing the appropriate bonds and insurance policies for the Project, and performance of preparatory construction operations, including the movement of personnel and equipment to the Project site, safety equipment and other facilities to begin work on a substantial phase of the Contract. Payment for this item will be made on a Lump Sum basis, wherein no measurement will be made. The Lump Sum price proposed shall be full compensation for performing the Work specified and the furnishing of all materials, labor, tools, equipment, and incidentals necessary to mobilize and subsequently demobilize.
2. CONSTRUCTION QUALITY CONTROL: This Work shall consist of testing of the structural fill within Cell 5 and the perimeter berm and testing of the access road stone. The soil stockpiles do not require compaction testing. Payment for this item shall be made on a lump sum basis.
3. SURVEY AND CONTROL: This Work shall consist of all survey and control work required by the Contract Documents. This includes establishment of appropriate local site
PROPOSAL FORM
00 42 13 - 3 Addendum 1 benchmarks, baseline surveys, stakeout of elevation and positional information required to complete the construction, obtaining all survey information required to compile Record (As- Built) survey and the aerial photos as required by the Contract Documents. Payment for this item shall be made on a lump sum basis.
4. CRUSH AND HAUL EXISTING SURFACE ROCK: This Work shall consist of furnishing all labor, materials, equipment, and appurtenances necessary to relocate exposed surface rock piles located west of Cell 5, within the grading limits, to the designated rock stockpile area at the cell tower (14G-01). The rock is not required to be reduced to a specific size;
however, it is assumed that hydraulic hammers will be used as necessary to break the rock into manageable sizes for loading and hauling. Payment shall be made on a unit price basis, based on an agreed-upon truck volume and verified truck counts
5. CLEARING & GRUBBING: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to clear and grub the trees and vegetation in the area indicated on the drawings. Material to be stockpiled in the area shown on the drawings. Payment for this item shall be made on a lump sum basis.
6. EROSION AND SEDIMENT CONTROL AND MAINTENANCE: This Work shall consist of furnishing all labor, materials, equipment, and appurtenances necessary for erosion and sediment control measures not specifically detailed in the Work but required to comply with applicable local and state ordinances, as well as for maintenance of the haul road to Unit 7 for the Contractor’s use. Payment for this item shall be made on a lump sum basis.
7. EXCAVATION: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to excavate, haul, and stockpile material in the locations indicated on the drawings. The quantities for each are for planning purposes and may not reflect the actual quantity.
a. MISCELLANEOUS SOIL: This Work shall consist of furnishing all labor, materials, equipment, and appurtenances necessary to excavate material within Cell 5 that is not classified as clay or rock, haul the material, and stockpile it in Unit 7. The Contractor shall make reasonable efforts to remove rocks larger than approximately 8 inches to 12 inches encountered during excavation prior to hauling material to the Unit 7 stockpile.
The Contractor may use a trommel screen for this purpose at no additional cost to the Owner. Removed rock may be used by the Contractor for construction of the access road to Unit 7. Compaction of the stockpiled material is not required; however, final slopes shall be tracked. All remaining rock not used for the access road shall be hauled to the designated rock stockpile area. Payment shall be made on a unit price basis, with quantities measured by comparison of the stockpile area
b. CLAY: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to excavate clay material from the Cell 5 area, haul, and stockpile the material in the designated area. This item is for in-place clay encountered in the excavation of Cell 5. Compaction is not required however the final slopes shall tracked. Payment will be made on a unit price basis wherein measurement will be made by electronic survey comparison of the stockpile area.
c. ROCK: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to excavate rock encountered from within Cell 5, haul and stockpile the rock in the designated rock stockpile area. Refer to specification 31 23 00 for definition of rock. The unit price shall include equipment (rippers, hammers, etc.)
and blasting that may be necessary. This item is for in-place rock encountered in the excavation of Cell 5. Payment will be made on a unit price basis wherein measurement will be made by electronic survey of the rock before and after excavation.
8. STRUCTURAL FILL: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to place structural fill from the Cell 5 excavation area. Payment will be made on a unit price basis wherein measurement will be made by electronic survey comparison.
PROPOSAL FORM
00 42 13 - 4 Addendum 1
9. TEMPORARY SEDIMENT BASIN A DECOMISSIONING: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to remove and salvage the skimmer and riser followed by removing a portion of the barrel then grouting the barrel with flowable fill. Payment for this item shall be made on a lump sum basis.
10. ACCESS ROAD – GEOTEXTILE: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to install geotextile for the access road along Cell 5. Payment will be made on a unit price basis wherein measurement will be made.
11. ACCESS ROAD – STONE: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to install stone on the access road along Cell 5. Payment will be made on a unit price basis wherein measurement will be made by truck tickets.
12. EROSION CONTROL MATTING: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to install erosion control matting on disturbed slopes (not Soil Stockpiles) that are outside of the Cell 5 footprint, channels and in areas directed by the engineer. Payment will be made on a unit price basis wherein measurement will be made.
13. SEEDING: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to provide permanent seeding on disturbed areas (i.e.
outside of cell 5 and the Miscellaneous Soil Stockpile). The clay stockpile is not seeded.
Payment will be made on a unit price basis wherein measurement will be made.
4. UNIT PRICE DEVIATIONS
The PROPOSER is responsible for providing Unit Prices consistent with typical industry norms for the Work described. Unit Prices which appear inconsistent with typical prices for similar Work shall be justified by the PROPOSER at the request of the ENGINEER. Providing Unit Prices which do not reasonable reflect the Work described, either high or low, which are not justified satisfactorily to the ENGINEER, may deem the PROPOSER non-responsive and invalidate their Proposal.
5. COMPLETION
PROPOSER agrees that the Work will be substantially completed and ready for final payment in accordance with the General Conditions.
PROPOSER accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within the times specified in the Agreement.
6. ATTACHED DOCUMENTS
Required Proposal Security in the form of _______________________.
7. ADDRESS FOR COMMUNICATIONS
Communications concerning this Proposal shall be addressed to:
Contact Name: ____________________________________________
Contact Email address: _________________________________________
Contact Telephone Number: _____________________________________
SUBMITTED on ________________________________________, 20___.
PROPOSAL FORM
00 42 13 - 5 Addendum 1
Date of Qualification / License in South Carolina to do business is _____________________.
If PROPOSER is:
A Corporation
By_____________________________________________________ (SEAL) (Corporation name)
(State of incorporation)
By_____________________________________________________ (SEAL) (Name of person authorized to sign)
(Title)
(Corporate Seal)
Attest ________________________________________________________________________________
(Secretary)
Business address: _____________________________________________
An Individual
By_____________________________________________________ (SEAL) (Individual's name)
Doing business as:
Business address: __________________________________
A Partnership
By_____________________________________________________(SEAL) (Firm name)
(General partner)
Business address: ____________________________
PROPOSAL FORM
00 42 13 - 6 Addendum 1
NOTE: Each joint venture must sign. The manner of signing for each individual, partnership and corporation that is a party to the joint venture should be in the manner indicated above.
8. EVALUATION
Refer to the notification for the evaluation criteria and documents to submit with the proposal.
1. Responsiveness (all information requested in this RFP submitted with proposal)
2. Project Schedule
3. Similar Projects
4. Cost
5. Proposed Equipment
END OF SECTION