About this file
This document is a Request for Proposal (RFP) Change form issued by the City of Carmel, designed to formally document and request modifications to an existing contract. The form provides a structured template for proposing changes to a contract's price, time, or scope, requiring the contractor to submit a detailed proposal within fifteen (15) calendar days. The proposal must include four (4) copies of a comprehensive breakdown showing quantities, material costs, equipment expenses, labor costs, overhead, profit, and any additional time requirements. The document emphasizes that this request does not authorize the contractor to proceed with the proposed work or halt previously scheduled work, and that a formal Contract Change Order and Notice to Proceed will be issued upon approval.
The form requires the contractor to explain the description of the proposed change, the reason for the change, and to specify the potential impact on the project's Substantial Completion and Final Completion dates. The proposal must be submitted by a specific due date, and will require approval from both an Engineer and the Owner's Representative. While this specific form is not directly tied to a specific contract amount or funding source, it serves as a critical administrative tool for managing contract modifications, ensuring transparency, detailed documentation, and formal approval processes for changes to government construction or service contracts.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| 22-ENG-15_Technical_Specifications_Addendum_2_Added.pdf | ||
| 22-ENG-15_Construction_Plans_Addendum_2_Added.pdf | ||
| BID_BOND.pdf | ||
| Clay_Center_Road_Path_Construction_and_Culvert_Replacement_Project_(Addendum_#1_Revision).pdf | ||
| CONTRACT_CHANGE_ORDER.pdf | ||
| CONTRACT_CHANGE_REQUEST.pdf | ||
| MAINTENANCE_BOND.pdf | ||
| MANUFACTURERS_LIST.pdf | ||
| SAMPLE_OF_MOU_FOR_E-VERIFY.pdf | ||
| PERFORMANCE_BOND.pdf | ||
| SAMPLE_AGREEMENT.pdf | ||
| SUBCONTRACTORS_LIST.pdf | ||
| Exhibit_D_E-Verify-1.PDF | ||
| PAYMENT_BOND.pdf | ||
| RIGHT_OF_ENTRY.pdf | ||
| SCREENSHOT_INSTRUCTIONS_-_FOR_BIDS.pdf | ||
| WORK_DIRECTIVE_CHANGE.pdf | ||
| FIELD_ORDER.pdf | ||
| NON_COLLUSION_AFFIDAVIT.pdf | ||
| 6._Comprehensive_Set_of_Technical_Specifications_2021-04-28_(V2.7).docx | DOCX document |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF CARMEL
TO: REQUEST FOR PROPOSAL NO
DATE:
PROJECT NAME:
PROJECT NO.:
Specification Reference:
Drawing Reference: _____________ Drawing Date:____________
Identification of Attachments:
Please submit within fifteen (15) calendar days of this request date a proposal showing increase, decrease or no change in Contract Price and/or Contract Time. Proposal shall be accompanied by four (4) copies of breakdown showing quantities, cost of material, equipment, labor, overhead, profit and basis for the additional time if any.
DESCRIPTION OF PROPOSED CHANGE COVERED BY THIS REQUEST:
REASON FOR CHANGE:
SPECIAL INSTRUCTIONS:
THIS REQUEST DOES NOT AUTHORIZE YOU TO PROCEED WITH THE ABOVE WORK
NOR STOP PREVIOUSLY SCHEDULED WORK. Upon approval a Contract Change Order and a Notice To Proceed will be issued.
Please state in your proposal the effect the acceptance of this Request will have on the Project’s Substantial Completion and Final Completion, if accepted within ___ days of proposal due date.
YOUR PROPOSAL DUE DATE: _____________________________________
By: _____________________________________ _________________ Engineer Date
Approved By: _________________________________ Owners Representative
File details come from the government source that posted it. Updated .