Attachment__2_-_01_74_00_-_Cleaning_and_Waste_Management.pdf

PDF 12 KB Posted

Attached to
SILT PUMPING PLANT MODERNIZATION Federal contract opportunity
Solicitation number
R16PS00121
Issued by
Department of the Interior Bureau of Reclamation

About this file

Attachment 2 - 01 74 00 Cleaning and Waste Managment

View the file

Other files for this federal contract opportunity

Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Silt Pumping Plant Modernization Silt Project - Upper Colorado Region Solicitation No. R16PS00121

Cleaning and Waste Management

01 74 00 - 1

SECTION 01 74 00

CLEANING AND WASTE MANAGEMENT

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the price schedule for other items of work except as specified.

2. Cost of environmental site assessments are Contractor’s responsibility.

1.02 DEFINITIONS

A. Hazardous waste: Defined as hazardous by 40 CFR 261.3; or by other Federal, State, or local laws or regulations.

1.03 REFERENCE STANDARDS

A. Bureau of Reclamation (USBR)

1. RSHS-09 Reclamation Safety and Health Standards, including revisions posted at http://www.usbr.gov/ssle/safety/RSHS/rshs.

html

B. Code of Federal Regulations (CFR)

1. 40 CFR 261.3 Definition of Hazardous Waste

2. 49 CFR 171-179 Transportation - Hazardous Waste Regulations

1.04 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 01 74 00-1, Waste Production and Disposal Plan:

1. For each type of waste, list estimated quantity and planned disposal location.

C. RSN 01 74 00-2, Waste Production and Disposal Records.

1. For each type of waste, list quantity and disposal location.

2. Include certifications that waste was properly disposed.

3. Hazardous wastes manifests.

01 74 00 - 2

D. RSN 01 74 00-3, Environmental Consultant Resume:

1. Describe experience on similar project.

E. RSN 01 74 00-4, Environmental Site Assessment.

1.05 QUALIFICATIONS

A. Environmental consultant: Minimum 2 years experience in conducting environmental site assessments for similar construction.

1.06 REGULATORY REQUIREMENTS

A. Comply with Federal, State, and local laws and regulations.

B. Comply with RSHS.

C. Conform to most stringent requirement in cases of conflict between specifications, regulatory requirements, and RSHS.

D. Comply with local regulations for presuppression, suppression, and prevention of fires when burning wastes.

1.07 PROJECT CONDITIONS

A. Report waste materials discovered at jobsite to COR.

1. Cease work in areas where waste may be hazardous until waste materials are investigated by Government.

2. If waste is hazardous, CO may order delays in time of performance or changes in work, or both.

3. If such delays or changes are ordered, an equitable adjustment will be made in the contract in accordance with applicable clauses of the contract.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.01 PROGRESS CLEANING

A. Keep work and storage areas free from accumulations of waste materials and rubbish.

01 74 00 - 3

3.02 FINAL CLEANUP

A. Remove temporary plant facilities, buildings, concrete footings and slabs, rubbish, unused materials, concrete forms, and other similar materials which are not part of permanent work.

B. Leave premises "broom clean”.

C. Clean equipment and fixtures to a sanitary condition.

D. Replace filters of operating equipment.

3.03 DISPOSAL

A. Nonhazardous waste materials:

1. Reuse at jobsite or reuse or recycle waste materials removed from jobsite whenever possible.

2. Dispose of materials not reused at jobsite by removal from jobsite.

3. Dispose of nonhazardous waste materials that are not reused or recycled at appropriately permitted disposal facilities.

4. Combustible waste materials: Dispose by removal from jobsite.

5. Noncombustible waste: Dispose by removal from jobsite.

6. Disposal by Removal:

a. Reuse or recycle waste materials whenever possible.

b. Dispose of nonhazardous waste materials that are not reused or recycled at appropriately permitted disposal facilities.

7. Do not burn waste materials.

8. Do not bury waste materials.

B. Hazardous Waste Disposal:

1. Dispose by removal from jobsite.

2. Recycle hazardous waste whenever possible.

3. Dispose of hazardous waste materials that are not recycled at appropriately permitted treatment or disposal facilities.

4. Transport hazardous waste in accordance with 49 CFR 171-179.

C. Certification: Certify that wastes are disposed of in accordance with Federal, State, and local regulations.

01 74 00 - 4

3.04 SITE ASSESSMENT

A. Upon completion of work, perform site assessment at following areas for work done under these specifications:

1. Hazardous waste accumulation areas.

2. Petroleum dispensing and storage areas where aggregate storage of petroleum at jobsite was over 110 gallons.

3. Hazardous material storage areas.

B. Employ qualified environmental consultant to perform assessments.

C. Demonstrate and document by appropriate analytical sampling that site contamination is less than State action cleanup levels.

3.05 RECORDS

A. Keep records of types and amounts of waste materials produced.

B. Keep records of waste material disposal.

END OF SECTION