B04 Pre-Proposal Inquiries (11-24) 21R00025.pdf
PDF 181 KB Posted
- Attached to
- PH21PH01H5 PIMC Elevator Modernization Federal contract opportunity
- Solicitation number
- PH21PH01H5
About this file
This document contains pre-proposal inquiries and responses for a solicitation seeking elevator modernization services. The scope of work involves modernizing four elevators at the Phoenix Indian Medical Center located in Phoenix, Arizona. Services include removing and disposing of outdated components, installing new equipment, refurbishing existing parts, and completing electrical and cab interior refurbishment. Offerors must provide preventative maintenance, a one year warranty, and coordinate with the facility's access control and fire alarm vendors. The period of performance is 300 calendar days with a budget between $1,000,000 to $5,000,000. A site visit is scheduled for May 14, 2021 and inquiries are due ten days before proposals. Proposals are due June 7, 2021. The solicitation will be set aside for small businesses with average revenues under $16.5 million. The contract type will be firm fixed price awarded by the Indian Health Service.
View the file
Other files for this federal contract opportunity
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment of Solicitation Amendment A00004 under Solicitation 75H701‐21‐R‐00025 Project PH21PH01H5, Phoenix Indian Medical Center Elevator Modernization
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-21-R-00025
PROJECT:
Phoenix Indian Medical Center Elevator Modernization
LOCATION:
Phoenix Indian Medical Center 4212 North 16th Street Phoenix, AZ, 85016
PROJECT NO: PH21PH01H5
DOCUMENT
OWNER: Kelly Britton PHONE: 602-364-5081 DOCUMENTS:
DATE: 6/4/2021 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference Drawing, Spec, Page COMMENTS POC IHS Approved Response
Amendment A00003 dated 5/25/2021
1. Clauses
This FAR regulation appears in the solicitation: 52.226‐1 Utilization of Indian Organizations and Indian‐Owned Economic Enterprises
Does this apply to the prime offeror? Will preference be given to the prime Indian offeror, under this regulation?
Kelly
FAR 52.226‐1 states that “The Contractor shall use its best efforts to give Indian organizations and Indian‐ owned economic enterprises (25 U.S.C.1544) the maximum practicable opportunity to participate in the subcontracts it awards to the fullest extent consistent with efficient performance of its contract.” The Contractor in this usage is prime offeror.
There is no Indian Owned Preference provided in Section L and M of the solicitation.
2. Drawings
We do not see the drawings posted to the beta.sam.gov website, although there is a note for “Please Request Role”. However, when we click on the “Request Role” button, it leads us to our profile but does not connect to making a request for the subject solicitation. Can you please advise how we should properly request for the drawings for this solicitation?
Kelly All drawings available for this project are included in the solicitations. We do not have any as‐built drawings for this project.
3. SF 1442 Can this bid be extended to June 23rd, 2021? Kelly The proposal due date will be extended from June 7, 2021 to June 17, 2021, 2:00 PM MST. Refer to Amendment A00003.
Project PH21PH01H5, Phoenix Indian Medical Center Elevator Modernization
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-21-R-00025
PROJECT:
Phoenix Indian Medical Center Elevator Modernization
LOCATION:
Phoenix Indian Medical Center 4212 North 16th Street Phoenix, AZ, 85016
PROJECT NO: PH21PH01H5
DOCUMENT
OWNER: Kelly Britton PHONE: 602-364-5081 DOCUMENTS:
DATE: 6/4/2021 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference
4. SF 1442
Will the Notice to Proceed for the project be issued after all critical pre‐construction submittals are approved by the owner, or on award of the contract?
Kelly
The contractor will be provided 30 calendar days to submit and obtain approval by the COR for all critical pre‐construction submittals.
The 30 calendar days will begin after bonds are received but no later than 10 days after award. Refer to SF1442, Block 11
5. SF 1442
Can the total project duration from notice of award to substantial completion be extended to 500 calendar days? Kelly
We believe the 300 day project duration is long enough to complete the project. However, if delays occur during the execution of work from unforeseeable causes beyond the control and without the fault or negligence of the Contractor, the Contract Officer may extend the project duration.
6. SF 1442
The project budget is listed as $500,000 ‐ $1,000,000. Can this be updated to the $1,000,000 ‐ $5,000,000 category? Kelly
SF1442, Block 10, Magnitude of construction was corrected to read “$1,000,000 to 5,000,000.00.” Refer to Amendment A00002.
7.
Spec 14 21 paragraph 3.6
The GC is required to provide a QEI for pretest for the completion of the elevator. Will the owner retain the services of a final inspection company for the Certificate of Use?
Bryan
No, the owner will not retain such services.
This section applies to Pre‐Test and Testing of the elevators. See Bold text at the end of this section, GC to provide “Upon successful completion of inspection and testing, the GC’s QEI will complete, sign, and provide a Certificate of Compliance/Certificate of Use”.
Refer to Amendment A00002 for revisions to Attachment J01, paragraph 3.6.
Project PH21PH01H5, Phoenix Indian Medical Center Elevator Modernization
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-21-R-00025
PROJECT:
Phoenix Indian Medical Center Elevator Modernization
LOCATION:
Phoenix Indian Medical Center 4212 North 16th Street Phoenix, AZ, 85016
PROJECT NO: PH21PH01H5
DOCUMENT
OWNER: Kelly Britton PHONE: 602-364-5081 DOCUMENTS:
DATE: 6/4/2021 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference
8.
Spec 14 21 paragraph
1.5 C
Can any drawings for siesmic loading upgrades for this project? Bryan We do not have information regarding prior seismic design.
9.
RFP Section H.17 Submittals
Will the contractor be required to provide a set of as built drawings, documenting the existing conditions as part of the pre‐construction phase of the project?
Bryan No. Contractor will be required to provide a set of as‐ built drawings, documenting post‐construction equipment/work installed per section H.42.
10.
Spec 14 21 paragraph
3.1 E
Has the electrical system been inspected for sizing of the feeders and verified it is adequate for the new equipment? Can this verification be provided by the owner? Can the existing feeders be re‐used?
Bryan No. Contractor shall determine that existing feeders are code compliant.
Amendment A00004 dated 6/3/2021
11. rfp, Section E E.1 © Can the building's general layout drawings be provided to determine distances of the elevator to panels and other critical building utilities? Bryan Refer to Amendment A00004, Attachment J10, As‐
Builts
Project PH21PH01H5, Phoenix Indian Medical Center Elevator Modernization
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-21-R-00025
PROJECT:
Phoenix Indian Medical Center Elevator Modernization
LOCATION:
Phoenix Indian Medical Center 4212 North 16th Street Phoenix, AZ, 85016
PROJECT NO: PH21PH01H5
DOCUMENT
OWNER: Kelly Britton PHONE: 602-364-5081 DOCUMENTS:
DATE: 6/4/2021 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference
12. General Question
The Invitation to Bid and Specification does not identify the protocol to obtain permits or designation for the Authority Having Jurisdiction (AHJ). Does there need to be design drawings prepared for the Elevator and Electrical to submit for plan review to obtain a permit with inspections to follow?
Bryan
Yes, Contractor shall submit drawings and submittals in accordance with Attachment J01, Section “1.5 Submittals.” All submittals shall be reviewed and approved by the COR.
In accordance with Attachment J01, Section “3.6 Pre‐ Tests and Tests” the Contractor’s QEI will perform inspection and testing of the elevators and related equipment and upon successful completion of the tests will provide a Certificate of Compliance/Certificate of Use signed by the QEI.
Any coordination required by the AHJ will be completed by the COR.
13.
Tech Spec Section 14 21 10 Part 1
– General;
1.1 Description A
The specification says to provide fully functional elevators in compliance with the latest Edition of ASME A17.1. There are significant changes to the 2019 Edition regarding video communication. Please confirm what Edition is to be used.
Bryan
The version of ASME A17.1 to use for this project will be the same one used by the Elevator Safety Section of the Division of Occupational Safety and Health of the Industrial Commission of Arizona. Elevators shall be in compliance with ASME A17.1 – 2007.
SOW has been modified to specify the version of ASME
17.1 from latest edition to 2007. Refer to Amendment A00004 for revisions to Attachment J01, paragraph 1.1. and 1.4
Project PH21PH01H5, Phoenix Indian Medical Center Elevator Modernization
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-21-R-00025
PROJECT:
Phoenix Indian Medical Center Elevator Modernization
LOCATION:
Phoenix Indian Medical Center 4212 North 16th Street Phoenix, AZ, 85016
PROJECT NO: PH21PH01H5
DOCUMENT
OWNER: Kelly Britton PHONE: 602-364-5081 DOCUMENTS:
DATE: 6/4/2021 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference
14.
Tech Spec Section 14 21 10 Part 1
– General;
2.46 Car
Enclosure:
Passenger Elevators And 2.48
2.46 says to provide new passenger and service car doors and 2.48 says to retain existing. Please clarify.
Bryan
Section “2.46 Car Enclosure, Paragraph I. shall be modified to read “Retain existing stainless steel car doors. Doors to be cleaned and refinished to a like new condition.”
Refer to Amendment A00004 for revisions to Attachment J01, paragraph 2.46
15. Electrical There are four existing disconnects that are providing power to the elevator equipment in the Machine Rooms. Can someone confirm there are existing ground wires with the feeders?
Bryan
The main electrical distribution panel in the machine room has an existing ground. Contractor shall replace all electrical conductors from the main electrical distribution panel to each new disconnect switch/shunt trip circuit breaker for each elevator.
16.
Tech Spec 14 21 01 2.7a
1. 1. Paragraph 2.7a states to include regen drive if economically advantaged to government. A regen drive is a very expensive add, and we have no way of telling what the power savings will be, but the payback period could be several years, making it not economically advantaged. We just need to know if customer wants regen drives included in the bid or not included in the bid.
A regen drive is not a requirement of this project.
SOW has been modified to remove the following sentence “Add Regenerative Drive when economically advantageous to the Government.”
Refer to Amendment A00004 for revisions to Attachment J01, paragraph 2.7.A
Project PH21PH01H5, Phoenix Indian Medical Center Elevator Modernization
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-21-R-00025
PROJECT:
Phoenix Indian Medical Center Elevator Modernization
LOCATION:
Phoenix Indian Medical Center 4212 North 16th Street Phoenix, AZ, 85016
PROJECT NO: PH21PH01H5
DOCUMENT
OWNER: Kelly Britton PHONE: 602-364-5081 DOCUMENTS:
DATE: 6/4/2021 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference
17.
Tech Spec 14 21 00 2.8a
1. Specs require separate monitoring for each elevator however specs say each elevator is simplex. The elevators are actually duplex (2 groups of 2 elevator). Since the elevator operation is duplex, this should only require monitoring for each pair of elevators. Please have customer confirm.
SOW has been modified to change Operation from Simplex to Duplex.
Refer to Amendment A00004 for revisions to Attachment J01, paragraph 1.1 Table of Existing Elevators and 2.8. Machine Room Monitor, paragraph A.
18.
The existing fan coil units do not meet the 7’ clearance requirement as required for the servicing and maintenance of the elevator equipment in the machine room. Will new mini split AC units be required as part of this proposal the correct this clearance issue?
Please advise.
It is the Contractor’s responsibility to meet height clearance requirements of ASME A17.1 – 2007.
However, new mini split AC units are NOT a requirement of this project but would be acceptable to correct this clearance issue.
19.
Please identify the specific version (applicable year) for the ASTM‐
17.1 that applies for this project?.
DISCUSSION: The most recent ASMT 17.1 (2019) includes challenging elements for an existing facility to implement. Using this standard adds considerable cost for almost no safety benefit. Recommend using 2016 standard.
I believe you meant ASME A17.1, instead of ASTM‐ 17.1.
Refer to question #13 above.
SOW has been modified to specify the version of ASME A17.1 from latest edition to 2007. Refer to Amendment A00004 for revisions to Attachment J01, paragraph 1.1. and 1.4
20.
Please confirm whether the Pit Ladders are to comply with ASTM 17.1 or are acceptable as is.
DISCUSSION. two of the ladders are not positioned IAW ASTM 17.1.
Pit ladders shall be in compliance with ASME A17.1 – 2007.
Project PH21PH01H5, Phoenix Indian Medical Center Elevator Modernization
INDIAN HEALTH SERVICE
DIVISION OF ENGINEERING
SERVICE
PRE-PROPOSAL INQUIRIES
Solicitation 75H701-21-R-00025
PROJECT:
Phoenix Indian Medical Center Elevator Modernization
LOCATION:
Phoenix Indian Medical Center 4212 North 16th Street Phoenix, AZ, 85016
PROJECT NO: PH21PH01H5
DOCUMENT
OWNER: Kelly Britton PHONE: 602-364-5081 DOCUMENTS:
DATE: 6/4/2021 DEPARTMENT: IHS/PAO/DFE
Item No.
Reference
21.
Please confirm if the existing roof crane is functional, and if so, it's max weight and if we are authorized to use for this project should we provide a qualified crane operator?
Contractor will NOT be allowed to use the existing roof crane.
22. Please provide ICRA guidance applicable to this project?
Refer to Amendment A00004 for revisions to Attachment J01, paragraph 1.1. C. and 1.4.M.
Refer to Attachment J02 ‐ Infection Control Risk Assessment Permit
23. Please confirm Certified Riggers are required to support Crane Operations?
Yes, because this work will take place over an occupied Hospital a Certified Rigger will be required.
All crane work shall comply with 29 CFR 1926 Subpart
CC.
24. Please confirm roof's load bearing capacity?
This building was built in 1968 and the information requested is not available.