Plumbing_and_Fire_Suppression_Division_1_Specifications.pdf
PDF 713 KB Posted
- Attached to
- ALCA Install Plumbing and Fire Sprinkler Qtr Maste Federal contract opportunity
- Solicitation number
- P16PS00600
About this file
Project Specifications
View the file
Other files for this federal contract opportunity
Show all 40
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GOLDEN GATE NATIONAL RECREATION
AREA
ALCATRAZ ISLAND
Quartermaster Warehouse Plumbing and Fire Suppression System
Installation
GOGA PMIS NO. 173969
PROJECT SPECIFICATIONS
NATIONAL PARK SERVICE
February 1, 2016
TABLE OF CONTENTS
Division ............. Section Title .......................................................................................................................... Pages
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00 Contract Modification Procedures
01 11 00 Summary of Work
01 27 00 Definition of Contract Line Items
01 31 00 Project Management & Coordination
01 32 16 Construction Schedule
01 32 33 Photo Documentation for Historic Preservation Projects
01 33 23 Submittal Procedures
01 35 13.22 Archeological Protection
01 35 23 Safety Requirements
01 35 91 Historic Preservation Treatment Procedures
01 40 00 Quality Requirements
01 50 00 Temporary Facilities and Controls
01 73 40 Execution
01 74 19 Construction Waste Management and Disposal
01 77 00 Closeout Procedures
SUPPLEMENTAL REFERENCES AND ATTACHMENTS:
1. AQMW FireSuppressionNarrative_IL_R1
2. AQMW Fire Suppression 0515_2_Specification_FINAL
3. AQMW Fire Suppression 0515_3_Full Set_FINAL
4. DEPARTMENT OF THE INTERIOR Mail - Fire Supply Line Existing
Conditions_Background
5. Original FP Dwgs 2000
6. AQMW Plumbing 160117_Alcatraz_Civil_FINAL
7. AQMW Plumbing Scope Description_FINAL
8. National Park Service, September 15, 2001. Golden Gate National Recreation Area
Standard Operation Procedure 609: Vehicle Use on Alcatraz.
9. Winter 2015-2016 Ferry Schedule
10. AIS Diesel Gas Water Transport and Material Handling Fees
11. Westar Transport and Material Handling Charges
12. General Requirements for Contractors on Alcatraz Island, March 2014 Update
13. Alcatraz Google Calendar Barge and Water Taxi Schedule Entry
Instructions_2015_12_04
SECTION 01 10 00 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation
(FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles (i.e., Superintendent Pickup trucks)
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment
Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor
Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided
Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule,” for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the
Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the
NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work. Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
http://www.nps.gov/dscw/publicforms.htm#ct http://www.nps.gov/dscw/publicforms.htm#ct
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources.
Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment,” in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers, Ownership and Operating Expense
Schedule (use latest edition and applicable region)
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated rental rates shall include the cost of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires
& tracks, routine repairs and maintenance (cost of major overhaul is not included), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above.
If the US Army Corp of Engineers is utilized then their standby rates prevail. If
Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only.
Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit. Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. The following percentages establish the maximum allowable markups (OH&P) for contractor self-performed work:
Overhead………………10%
Profit……………………5%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 01 10 00
SECTION 01 11 00 - SUMMARY OF WORK
PART 4 - GENERAL
4.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work under other contracts.
3. Contractor use of site.
4. Public use of site.
5. Occupancy requirements for buildings.
6. Worker transportation to Alcatraz Island.
7. Materials transport to Alcatraz Island.
8. Work Restrictions.
9. Special Construction Requirements.
10. Supplemental Information and Reports.
4.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: The Alcatraz Quartermaster Warehouse is located on the northeast side of Alcatraz Island in the Golden Gate National Recreation Area.
B. The Work consists of the following:
A. Provide and install sewage and water piping from existing infrastructure in the Water
Tower Staging area to the Quartermaster Warehouse. Work includes provision and installation of a sewage grinder/ pump (macerator).
B. Provide design, materials and installation of a fire suppression system, including fire pump.
C. Provide all code required inspections to commission both plumbing and fire suppression systems.
D. See Section 01 27 00 Definition of Contract Line Items for a description of the base bid work.
E. Project will be constructed under a single prime contract.
4.3 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract.
Coordinate the Work of this Contract with work performed under separate contracts.
B. Preceding Work: None
C. Concurrent Work: Government will award separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.
1. A separate contract with Plant Construction, LLC will be underway, or recently completed, for the renovation of the Quartermaster Warehouse. This contract includes interior plumbing from the macerator location, electrical and fire alarm work. Contractor will need to coordinate with the CO regarding the connections between the work of both contracts.
4.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of
Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to the Guardhouse and the approved staging areas.
B. Storage of Materials: Confine storage of materials to designated staging areas.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the
Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval.
Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times.
Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials.
Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1. All materials arriving at the island must pass through the historic sally port or be crane lifted around the sally port. See the supplemental information for approximate sally port dimensions. Contractor is responsible for taking exact measurements to verify feasibility of moving materials and equipment through the sally port without damaging the structure.
2. Road usage requirements are specified in: National Park Service. September 15, 2001. Golden Gate National Recreation Area Standard Operation Procedure 609:
Vehicle Use on Alcatraz.
3. Roads on the island have multiple hairpin turns that will preclude the use of some construction equipment.
4. Do not block the shuttle route or the main road for any reason during hours of public visitation.
5. All vehicles on the main road must have a spotter on foot to interface with the interpretive staff and public, and to aid in the prevention of accidents. The main road speed limit is 5 miles per hour.
G. Worker Orientation and Identification: All workers must attend an orientation meeting with
Park Staff to review the unique requirements of working on Alcatraz Island, interfacing with the public and safeguarding natural and cultural resources.
1. All workers are required to attend additional natural resource briefings once per month during the bird nesting season. Natural resource briefings will be held in conjunction with the regularly scheduled safety meetings.
2. Provide all workers with photo identification badges listing the worker’s name, employer (if other than the prime contractor) and the prime contractor’s name.
Refer to the worker badge template given in the Supplemental Information.
4.5 WORKER TRANSPORTATION TO ALCATRAZ ISLAND
A. The Contractor is responsible for transportation of the construction crew to and from
Alcatraz Island.
B. Park Concessionaire can transport workers to Alcatraz Island via ferry service designated as "Staff Boats." Coordinate cost of this service and obtain a Schedule of Operating Hours from Park Concessionaire. Only materials that can be hand carried onto and offloaded from the ferry without multiple trips will be allowed on ferries. Park Concessionaire is not required to transport workers to Alcatraz Island except as listed below.
1. Park Concessionaire will transport workers from Alcatraz Island to San Francisco on regularly scheduled passenger ferries.
2. Notify and coordinate with Park Concessionaire when work crew size will vary from an established norm in order to ensure adequate room on passenger ferries.
C. Ferry service outside the service listed above must be arranged and paid for by Contractor and coordinated with Park Concessionaire. Do not interfere with Park Concessionaire's regular ferry schedule.
D. If Contractor provides other ferry service:
1. Coordinate with Park Concessionaire to avoid conflict with scheduled passenger ferries.
2. Coordinate with Park Concessionaire for requirements of use of government facilities managed by Concessionaire.
E. See Supplemental Information for the following documents related to material transportation:
1. Winter 2015-2016 Ferry Schedule
4.6 TRANSPORT OF MATERIALS AND EQUIPMENT TO ALCATRAZ ISLAND
A. Contractor is responsible for arranging transport and delivery of materials and equipment to and from the island.
B. Alcatraz Cruises has the Concession Agreement with the NPS. Use of the finger pier, floating dock and/or fixed wharf, for the purposes of transporting passengers, and/or transportation or storage of equipment or supplies, must be coordinated with the NPS and its concessionaire Alcatraz Cruises.
C. West Star Marine operates a material barge that services the island using a 10 ton crane to off-load and take on material. West Star also operates a water taxi service that is used outside of Alcatraz Cruises operating Hours, or if Alcatraz Cruises cannot supply a vessel.
D. All barge and water taxi arrivals, must be entered into an electronic Google Based
“Alcatraz 1850” calendar to ensure notification of NPS and Parks Conservancy staff, contracted overnight security staff and other contractors doing work on island.
E. Manson Construction, CS Marine or others may be used for heavy lift in cases where heavy equipment is needed on the Island and it will not fit through the Sally Port. This may apply to equipment needed for the Project. Restrictions on this service apply during bird breeding season.
F. The Golden Gate National Parks Conservancy operates a monthly barge to meet the operational needs of both the Conservancy and the NPS. Any barge activities that are arranged by the Contractor shall not interfere or conflict with this monthly barge. The
Conservancy barge schedule is set in October/November of each year for the following calendar year.
1. The Conservancy will allow Contractor limited use of the monthly barge as follows:
a. Availability will be determined by the Conservancy based on availability of space, time and equipment/personnel limitations.
b. Use of Conservancy barge will be subject to "per lift" fees.
c. Coordinate use of Conservancy barge directly with the Golden Gate
National Parks Conservancy a minimum of 1 week prior to barge run.
G. Other arrangements can be made by receiving written permission from the Contracting
Officer for the Concession Agreement or their Representative and filing the proper insurance papers and bonds.
H. Contacts:
1. Alcatraz Island Services: Aaron Warren 415.559.3126
2. West Star Marine Dispatch: 415.495.3191
3. Manson Construction: Charlie Gibson 415.279.2792
4. Golden Gate National Parks Conservancy: Patrick McAllister 415.561.4923
5. NPS Concessions Management Specialist: Maria Banuelos Connell
415.562.4944
I. See Supplemental Information for the following documents related to material transportation:
1. Memo “Stores Delivery Rates and Terms and Conditions,” by Westar Marine
Services.
2. Alcatraz Google Calendar Barge and Water Taxi Schedule Entry
Instructions_2015_12_04. Docx
3. AIS Diesel Gas Water Transport and Material Handling Fees
4.7 PUBLIC USE OF SITE
A. Alcatraz Island will be open to the public during construction. Contractor shall at all times conduct operations to ensure the least inconvenience to the public and to the Government.
The Library roadway will remain open to the public to the greatest extent possible during visiting hours. The Library roadway can be closed periodically and pedestrians redirected, however the Contractor shall conduct operations to ensure uninterrupted SEAT shuttle service through the Sally Port entrance. SEAT is an accessible shuttle that runs twice an hour from the dock to the prison building and twice an hour from the drop off location back to the dock. Service vehicles, including the ambulance, forklift and pickup truck(s) will also need intermittent access up and down the roadway and should be coordinated with Park operations. The SEAT shuttle service schedule is as follows:
1. SEAT Departure Times
a. Departure Times – Dock Level
1) AM: 9:15, 9:40, 10:00, 10:40, 11:10, 11:40
2) PM: 12:10, 12:40, 1:10, 1:40, 2:10, 2:50, 3:20, 4:00, 4:30, 4:50,
5:15, 5:55
3) Night Tours Dock to Cellhouse: 6:30 PM, 7:05 PM
b. Departure Times – Cellhouse Level
1) AM: 9:20, 9:50, 10:30, 11:00, 11:30
2) PM: 12:00, 12:30, 1:00, 1:30, 2:00, 2:40, 3:10, 3:50, 4:20, 4:40,
5:05, 5:45, 6:00
3) Night Tours Cellhouse to Dock: 6:35 PM, 8:25 PM, 9:00 PM
B. Existing Buildings
1. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas under construction.
Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the
CO.
4.8 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:30 a.m. to 4:30 p.m., Monday through Friday, except when otherwise indicated.
No work may occur on the island without a NPS representative on the island.
1. Weekend Hours: No on-site work shall be performed on weekends unless approved in advance by the Contracting Officer. Weekend work is at the discretion of the Contracting Officer and may not be approved.
2. Early Morning Hours: No exterior, on-site work shall be performed before daylight unless approved in advance by the Contracting Officer. Early morning work is at the discretion of the Contracting Officer and may not be approved
3. Hours for Noisy Activity: Noisy work activities, such as, but not limited to:
hammer drilling, chipping and cutting are limited as follows:
a. During Bird Nesting Season, noisy work is not permitted outside before sunrise without installation of approved sound barriers.
4. Holiday work Restrictions: No on-site work shall be performed on national and federal holidays unless approved by the Contracting Officer.
B. Existing Utilities
1. No potable water is available on the island for construction activities. Contractor to arrange with Park Concessionaire for transport of water to the island.
2. Storage and delivery of potable water to the work is extremely limited, Contractor is responsible for providing adequate means for storage and delivery of water
3. Contractor is responsible for collection and disposal of waste water. Contractor to arrange with Park Concessionaire for transport of waste water from the island.
4. Existing Utilities: Electricity on the island is provided by a solar photovoltaic system, with limited capacity and distribution. Coordinate with the Contracting
Officer regarding activities that require site electricity. Contractor is responsible for providing all necessary electricity for the project.
5. The island does not have a telephone land line and limited cellular reception.
Contractor is responsible for providing their own phone and data access.
6. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the
Government.
7. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by
Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
D. Nonsmoking Building: Smoking is not permitted anywhere on the island except the designated smoking area located near the dock.
4.9 SPECIAL CONSTRUCTION REQUIREMENTS
A. Comply with all requirements of the “Alcatraz Island Historic Preservation and Safety
Construction Program”, Final Environmental Impact Statement and the mitigation measures shown.
B. Comply with the reference document, “General Requirements for Contractors on Alcatraz
Island, National Historic Landmark District.”
C. Special environmental requirements are in effect during the bird breeding season of approximately February 15 to August 15.
1. Transport of materials to the island by helicopter is prohibited.
2. Movement of equipment and materials to and from staging areas is restricted to daylight hours to prevent moving lights (i.e., headlights) from disturbing sensitive areas.
3. Reduce night lighting in authorized construction areas to the minimum amount necessary to complete work. Shield lighting and direct downward.
4. Placement, intensity and direction of nighttime lighting are subject to approval of
Contracting Officer.
5. The following activities are not permitted:
a. Approaching birds
b. Disturbing or harassing birds
c. Feeding birds
d. Taking of migratory birds or their nests
D. Bird guano exists in significant quantities at most exterior areas. Take necessary precautions when working in these areas.
E. Alcatraz Island has a severe weather exposure and frequent high winds.
4.10 SUPPLEMENTAL INFORMATION AND REPORTS
A. Supplemental memos, as previously noted in this section, are available to all plan holders.
In addition to information previously noted, the following information is available:
1. A report titled: Alcatraz Island Historic Preservation and Safety Construction
Program Final Environmental Impact Statement, dated October 2001, has been prepared by the National Park Service.
B. If conflicts occur between the supplemental information and drawings or specifications, the drawings and specifications govern.
PART 5 - PRODUCTS (NOT USED)
PART 6 - EXECUTION (NOT USED)
END OF SECTION 01 11 00
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 7 - GENERAL
7.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 8 - PRODUCTS (NOT USED)
PART 9 - EXECUTION
9.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No.1.
1. Install Sewer and Plumbing to Quartermaster Warehouse: This item consists of provision and installation of a design-build sewer and plumbing system based on the following provided documents:
a. AQMW Plumbing Scope Description_FINAL
b. AQMW Plumbing 160117_Alcatraz_Civil_FINAL
2. This item includes all code required inspections for the work.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No.2.
1. Design and Install Fire Suppression System at Quartermaster Warehouse: This item consists of the provision and installation of a design-build fire suppression system based on the following provided documents:
a. AQMW FireSprinklerNarrative_IL_R1
b. AQMW Fire Suppression 0515_2_Specification_FINAL
c. AQMW Fire Suppression 0515_3_Full Set_FINAL
d. DEPARTMENT OF THE INTERIOR Mail - Fire Supply Line Existing
Conditions_Background
e. Original FP Dwgs 2000
2. This item includes all code required inspections for the work.
3. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 10 - GENERAL
10.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Construction Coordination.
2. Coordination Drawings.
3. Requests for Information (RFIs).
4. NPS/DSC SharePoint Project Website.
5. Project meetings.
6. Environmental Coordination.
B. Related Requirements:
1. Section 01 3 200 “Construction Progress Documentation” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 00 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the
Contract.
10.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work.
Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Pre-installation conferences.
7. Project closeout activities.
8. Commissioning activities.
10.3 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify
Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Storm Water Pollution Prevention Plan.
11. Indoor Air Quality (IAQ) Management Plan.
12. Historic Preservation Treatment Plan.
B. All items listed must be provided to the Contracting Officer before the Pre-Construction
Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
10.4 REQUESTS FOR INFORMATION (RFIS)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product
Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select “CMR” in the drop-down of the “Send to” box.
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
10.5 PROJECT WEB SITE
A. Use the NPS/DSC SharePoint Project website for communication throughout the contract period. The NPS/DSC SharePoint Project website will be used for the following functions:
1. Project directory.
2. Project correspondence.
3. Meeting agendas and minutes.
4. Contract modifications forms and logs.
5. RFI form and processing.
6. Task and issue management.
7. Photo documentation.
8. Baseline schedule, schedule updates and calendar management.
9. Submittal form and processing.
10. Payment coordination documentation.
11. Drawing and specification document hosting, viewing, and updating.
12. Online document collaboration.
13. Reminder and tracking functions.
14. Archiving functions.
15. Notification of submittal and RFI statuses and current responsible party.
B. Some documents however are not suitable to be shared using the NPS/DSC SharePoint
Project website. Documents containing Personal Identifying Information (PII) (i.e.
certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.
C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC
SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later
10.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
http://www.nps.gov/dscw/precon_spproj.htm
7. Modifications.
8. Payments to Contractor.
9. Payroll reports.
10. Contract time.
11. Liquidated damages.
12. Contractor Performance Evaluation.
13. Display of Hotline posters.
14. Notice to proceed.
15. Correspondence procedures.
16. NPS/DSC SharePoint Project website.
17. Acceptance/rejection of work.
18. Progress meetings.
19. Submittal procedures.
20. NPS Final Accessibility Inspection.
21. Environmental requirements.
22. As-constructed drawings/operation and maintenance (O&M) manuals.
23. Saturday, Sunday, holiday and night work.
24. Reference materials.
25. Value engineering.
B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the
Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting.
Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications.
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections,
h. Construction Schedule update (provide updated CPM).
i. Status of Project Record Drawings and O&M manuals.
j. Other business relating to work.
C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Sustainable design requirements.
i. Review of mockups.
j. Possible conflicts.
k. Compatibility requirements.
l. Time schedules.
m. Weather limitations.
n. Manufacturer's written instructions.
o. Warranty requirements.
p. Compatibility of materials.
q. Acceptability of substrates.
r. Temporary facilities and controls.
s. Space and access limitations.
t. Regulations of authorities having jurisdiction.
u. Testing and inspecting requirements.
v. Installation procedures.
w. Coordination with other work.
x. Required performance results.
y. Protection of adjacent work.
z. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
10.7 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project;
familiarity with Environmental Management Systems (EMSs) such as ISO
14001; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of the Waste Management Plan (WMP).
c. Implementation of the Indoor Air Quality (IAQ) Management Plan.
d. Implementation of the Storm Water Pollution Prevention Plan (SWPPP).
e. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.
f. Training for Contractor personnel in accordance with their position requirements.
g. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related
Sections, including:
1. Quality Requirements.
2. Regulatory Requirements.
3. Indoor Air Quality (IAQ) Management.
4. Noise & Acoustics Management.
5. Temporary Storm Water Pollution Prevention Environmental Management.
6. Construction Waste Management.
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:
1. Overview of environmental issues related to the building industry.
2. Overview of environmental issues related to the Project.
3. Review of site specific procedures and management plans:
a. Construction Waste Management.
b. Noise & Acoustics Management.
4. Pollution Prevention (P2) practices: Submit evidence of participation in P2 programs.
5. Compliance with environmental regulations: As specified in Regulatory
Requirements. Submit Contractor 40 CFR employee training records upon request of Contracting Officer.
D. Mandatory Bird Sensitivity Training
1. All personnel, including subcontractors, who will be on-site during the period of
February 15 through September 15 are required to attend training.
2. Training is provided by park staff and typically lasts about 1 hour.
3. Training shall be coordinated with Contracting Officer in advance of on-site work during the period of February 15 through September 15.
PART 11 - PRODUCTS (NOT USED)
PART 12 - EXECUTION (NOT USED)
END OF SECTION 01 31 00
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 13 - GENERAL
13.1 SUMMARY
A. This Section consists of Construction Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor.
The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the
Contractor's monthly progress payment.
13.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract
Sum, unless otherwise approved by the Contracting Officer.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships.
Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project…