MATERIALS_TRANSPORATION_AGREEMENT_(REV_1.1.16_OTHER).pdf
PDF 105 KB Posted
- Attached to
- ALCA Install Plumbing and Fire Sprinkler Qtr Maste Federal contract opportunity
- Solicitation number
- P16PS00600
About this file
Materials Transportation Agreement
View the file
Other files for this federal contract opportunity
Show all 40
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MATERIALS TRANSPORTATION AGREEMENT
Pier 33, Alcatraz Landing No.:
San Francisco, CA 94111
415.559.3126 Date: _______________________________
Fax: 415.986.1721 Email: ac_ops@alcatrazcruises.com AIS Representative: ___________________________________________
ALL INFORMATION REGARDING DELIVERIES AND OTHER REQUESTS MUST BE MADE BY EMAIL IN A
TIMELY MANNER.
Contractor Company Name: ______________________________________ Contractor Contact Name: _________________________________________________
Destination of Material: From ________________________________ To _______________________________________ Time of Delivery: ____________________
Transportation costs from Pier 33 San Francisco to Alcatraz Island.
MV Solitary can carry fewer than 6 passengers. Alcatraz Cruises Ferries are rated up to 700 passengers.
Passenger services: Non-scheduled passenger service for hours outside of regular service. This must be scheduled one day in advance. Hand carried items and hand truck items are allowed. *
*After hours services are subject to double time between 2300-0500. Holiday services are subject to double time.
VESSEL PRICE MINIMUM
MV SOLITARY 62’
3 TON CRANE
WATER AND DIESEL SERVICE
$423.50 PER HOUR
$55.00 per crane pick
Water: $.55 per gallon Diesel: $7.15 per gallon Gasoline: $8.25 per gallon
1 Hour
ALCATRAZ CRUISES FERRY
6 PASSENGERS OF MORE
ROLL ON ROLL OFF SERVICES
$533.50 PER HOUR 1 Hour
Forklift picks when on-loading or off-loading at Pier 33 are subject to a rate of $27.50 per pick.
** After two hours of crane operation an additional cost of $55.00 per quarter hour will be charged
Portable Restrooms and Hand Washing Station: $250 a week plus $75 a week for pumping, cleaning, and maintaining of facilities provided by AIS staff.
SERVICE QUANTITY UNIT PRICE TOTAL COST
TOTAL $
Notes: ________________________________________________________________________________________________________________________________
Contractor Signature: ____________________________________________________________ Date: ___________________________________________
FOR MGMT USE ONLY: Approval Signature: ______________________________________________________________
Revised: 1.1.16 Rates Effective: 2.1.2016