SECTION IIIA – SUPPLEMENTAL GENERAL CONDITIONS
SECTION IIIA Page 1 of 6
SECTION IIIA
CITY OF CLEARWATER, FLORIDA
PUBLIC WORKS DEPARTMENT
SUPPLEMENTAL GENERAL CONDITIONS – SUMMARY (SECTION IIIA)
GENERAL
This document summarizes Section IIIA – Supplemental General Conditions for the Osceola Corridor Improvements Project. These provisions modify and supplement the General Conditions and establish coordination-driven requirements for project execution.
1. PHASING AND COORDINATION
Phasing is conceptual and not fixed. The Contractor shall perform the Work in a flexible and adaptive manner to accommodate adjacent developments, including the Ballad Hotel (KAST), Bluffs Apartments (Gotham), and the Osceola Parking Garage (Creative Contractors), as well as City-approved events. Concurrent operations within and adjacent to the corridor shall be considered normal and anticipated conditions of the Work.
2. NO EXCLUSIVE ACCESS
The City retains control of the public right-of-way. The Contractor is not guaranteed exclusive use of the project corridor and shall plan for shared access with developers and other parties. The Contractor shall make a good faith effort to coordinate with adjacent projects, including the Ballad Hotel (KAST), Bluffs Apartments (Gotham), and the Osceola Parking Garage (Creative Contractors); however, such coordination shall not relieve the Contractor of its obligation to maintain progress of the Work in accordance with the Contract Documents. Coordination with all stakeholders is essential to the successful execution of the Work.
3. NO DAMAGES FOR DELAY
The Contractor acknowledges that the Project requires ongoing coordination with adjacent construction activities, utility operations, other contractors, and public events within and adjacent to the Project corridor.
The Contractor further acknowledges that allowances for coordination-related impacts with adjacent property owners and contractors along the corridor are included in the Lump Sum Contract Price and accounted for under the Contract Time (365 days), and that such allowances account for reasonably anticipated impacts associated with adjacent projects, utilities, and City requirements. No coordination-related allowance or contingency work shall proceed without prior written authorization from the Owner.
The Contractor agrees that no monetary compensation shall be due for delays, disruptions, or inefficiencies arising from:
• Activities of adjacent or nearby construction projects
• Operations of other contractors, utility companies, or developers
SECTION IIIA Page 2 of 6
• Coordination requirements imposed by the Owner provided that such impacts are consistent with the Contract Documents, including the Project Coordination Matrix, the Project Schedule, and associated milestones, and coordination requirements documented in project meetings.
For impacts meeting the above conditions, the Contractor’s sole remedy shall be an extension of Contract Time, if justified.
If the Contractor demonstrates that delays or disruptions result from a material deviation from documented coordination, and such impacts could not have been reasonably anticipated and were not caused by the Contractor, the Contractor may be entitled to an equitable adjustment in Contract Time and consideration of additional compensation, subject to proper documentation and notice in accordance with the Contract.
This provision shall not apply in cases of the Owner’s active interference or bad faith actions.
4. COORDINATION MATRIX
Within fourteen (14) days of Notice to Proceed, the Contractor shall submit a Coordination Matrix identifying all stakeholders, including KAST, Moss Construction, Creative Contractors, and City of Clearwater Special Events, and defining associated conflicts, interfaces, and coordination responsibilities.
In addition, the Contractor shall prepare and submit a Project Coordination Plan within the same timeframe. The Coordination Plan shall include, at a minimum:
• Strategies for coordinating with adjacent developments, including sequencing and interface management
• Procedures to avoid and mitigate conflicts with private construction activities
• Methods to maintain access and safety during special events, including concerts, festivals, and public gatherings
• Communication protocols with developers, utility providers, businesses, and City staff
• Procedures for identifying, escalating, and resolving coordination conflicts in a timely manner
The Coordination Matrix and Coordination Plan shall be integrated with the CPM schedule and used together as the primary coordination and documentation tools for the Project.
The Coordination Matrix shall be updated monthly, and the Coordination Plan shall be updated as necessary throughout the duration of the Work.
Acceptance of the Coordination Matrix or Coordination Plan by the Owner does not relieve the Contractor of its obligations under the Contract Documents.
SECTION IIIA Page 3 of 6
5. SCHEDULE AND MILESTONES
The Contractor shall incorporate adjacent project milestones, including those associated with the Ballad Hotel (KAST), Bluffs Apartments (Moss Construction), and the Osceola Parking Garage (Creative Contractors), as well as event readiness requirements and coordination activities, into the CPM schedule.
6. WEEKLY COORDINATION MEETINGS
The Contractor shall attend mandatory weekly coordination meetings and provide a two-week lookahead schedule, updated Coordination Matrix, and identification of potential conflicts, including those associated with adjacent projects such as the Ballad Hotel (KAST), Bluffs Apartments (Moss Construction), and the Osceola Parking Garage (Creative Contractors), and shall proactively coordinate with all stakeholders to mitigate such conflicts.
7. SCHEDULE CONTROL AND FLOAT
The city shall have the sole authority to prohibit or order work stopped. The city reserves the right to cancel scheduled shutdowns if conditions warrant. Delays to the Contractor caused by cancellations will be considered in evaluating requests for a time extension. They will not be considered an entitlement to additional compensation. However, compensation may be considered at city’s sole discretion
8. TRAFFIC AND UTILITY RESPONSIBILITIES
The Contractor shall maintain traffic in accordance with FDOT standards and ensure access at all times. Construction activities shall not interrupt water, wastewater, or reclaimed water service except for shutdowns or services interruptions approved in advance by the City and coordinated in accordance with Section IV, Section 209-2, Maintenance of Operations, and other applicable Contract Documents.
The Contractor shall develop, implement, and maintain a dynamic and adaptive Maintenance of Traffic (MOT) approach that accommodates adjacent construction activities, special events, peak traffic conditions, pedestrian access, and downtown operations.
The Contractor shall adjust MOT operations as necessary and as directed by Public Works, Transportation Division to minimize impacts to the public, businesses, and adjacent developments.
All modifications to MOT shall be performed in accordance with FDOT standards and approved traffic control plans. Pedestrian access to the Clearwater Main Library shall be maintained at all times during the Project. Access to the library parking lot shall also be maintained except where temporary closure is specifically approved by the Owner to facilitate construction activities. The Contractor shall minimize the duration and extent of any parking lot closure to the greatest extent practicable and shall coordinate all closures in advance with the Owner.
Intermittent reopening of eastbound Cleveland Street shall be permitted only when approved in writing by the Owner on a case-by-case basis, for limited durations, and solely as necessary to facilitate traffic detours or maintain traffic operations.
SECTION IIIA Page 4 of 6
Failure to adequately maintain or adapt traffic operations in accordance with this Section may be considered a failure to properly prosecute the Work.
The Contractor shall keep existing utilities in service during all phases of construction and coordinate any system shutdowns with the city sufficiently in advance to provide alternative service. The Contractor shall provide a minimum of 10 days’ notice. The Contractor shall protect the city’s utility system for any spills or overflows during construction. The city’s Project Manager and Dispatch (727-462-6633) shall be notified of any spills or overflows immediately.
9. PERFORMANCE REQUIREMENTS
The Contractor shall prosecute the Work with sufficient forces, equipment, and supervision to ensure completion in accordance with the Contract Documents, including all milestones and schedule requirements.
If, in the opinion of the Owner or Engineer, the Contractor fails to maintain adequate progress, properly staff the Project, or comply with coordination, schedule, or performance requirements, the Owner may, without additional cost to the Owner, require the Contractor to:
• Increase labor, supervision, equipment, or working hours
• Take any other action necessary to restore acceptable progress
If the Contractor fails to take corrective action promptly, the Owner reserves the right to supplement the Work with additional forces or contractors. All costs incurred by the Owner in supplementing the Work shall be the Contractor's responsibility and may be deducted from amounts due under the Contract.
The Contractor shall ensure that all personnel, including key staff and subcontractors, meet the qualification requirements specified in the Contract Documents. The Owner reserves the right to review, approve, and reject personnel or subcontractors that do not meet these requirements or fail to perform satisfactorily.
Failure to comply with this Section may constitute grounds for further contractual remedies, including withholding payment, assessment of damages, or termination in accordance with the Contract Documents.
10. STAKEHOLDER COMMUNICATION REQUIREMENTS
The Contractor shall maintain proactive and continuous communication with all project stakeholders, including adjacent developers, businesses, residents, utility providers, and event coordinators.
The Contractor shall:
• Designate a single point of contact responsible for coordination and communication
• Provide advance notice of construction activities that may impact access, traffic operations, or adjacent development activities
SECTION IIIA Page 5 of 6
• Participate in coordination meetings with stakeholders as required by the Owner
• Respond promptly to coordination issues, conflicts, and public concerns
Failure to maintain effective communication and coordination with stakeholders may be considered a failure to properly prosecute the Work.
11. IMPACT MINIMIZATION REQUIREMENT
The Contractor shall plan and execute the Work in a manner that minimizes disruption to adjacent construction activities, downtown businesses, residents, and special events.
Cleveland Street is permanently closed for traffic, but eastbound Cleveland Street shall be re-opened for short durations, should MOT Phasing require. Advance coordination and prior written approval from the City shall be required.
Construction sequencing, scheduling, and operations shall be developed and adjusted as necessary to maintain access, support adjacent project activities, and reduce impacts to the public and surrounding properties. This may include the temporary opening of eastbound traffic on Cleveland Street to facilitate construction, Advanced coordination and prior written approval from the City shall be required.
The Contractor acknowledges that impact minimization is a material requirement of the Work and shall incorporate such considerations into all planning and execution activities.
12. PRECONSTRUCTION COORDINATION WORKSHOP
Prior to commencement of Work, the Contractor shall participate in a mandatory coordination workshop with the Owner, Engineer, adjacent developers, utility providers, and key stakeholders.
The purpose of the workshop shall be to:
• Review coordination requirements and project constraints
• Establish communication protocols and points of contact
• Identify critical conflicts, interfaces, and access limitations
• Align sequencing, phasing, and milestone expectations
The Contractor shall incorporate outcomes of the workshop into the Project Schedule, Coordination Matrix, and Coordination Plan.
The Contractor shall incorporate the outcomes of the workshop into the Project Schedule, Coordination Matrix, including milestones for project activities that are substantially complete, such as Bluffs, Ballad Hotel, and Osceola Parking Garage, including milestones for project activities that are substantially complete, such as Bluffs, Ballard Hotel, and Osceola Parking Garage, and the Coordination Plan.
SECTION IIIA Page 6 of 6
END OF DOCUMENT
| Osceola Avenue Corridor Improvements |
| 22-0017-EN |
| CONTRACT DOCUMENTS & SPECIFICATIONS |
| Prepared for |
| Final Design |
| JUNE/2026 City of Clearwater, Florida |
| Osceola Avenue Corridor Improvements |
| (22-0017-EN) |
| TABLE OF CONTENTS |
| SECTION I ADVERTISEMENT OF BIDS & NOTICE TO CONTRACTORS |
| SECTION II INSTRUCTIONS TO BIDDERS |
| SECTION IIA SUPPLEMENTAL INSTRUCTIONS TO BIDDERS |
| SECTION III GENERAL CONDITIONS |
| SECTION IIIA SUPPLEMENTAL GENERAL CONDITIONS |
| SECTION IV TECHNICAL SPECIFICATIONS |
| SECTION IVA SUPPLEMENTAL TECHNICAL SPECIFICATIONS |
| SECTION V CONTRACT DOCUMENTS |
| APPENDIX ODP DOCUMENTS AND OTHER PROJECT DOCUMENTATION |
| SectionI - 2025_0709.pdf |
| INVITATION TO BID NOTICE TO CONTRACTORS |
| SectionII - 2025_0709.pdf |
| SECTION II |
| INSTRUCTIONS TO BIDDERS |
| 1. COPIES OF BIDDING DOCUMENTS |
| 2. QUALIFICATION OF BIDDERS |
| 3. EXAMINATION OF CONTRACT DOCUMENTS AND SITE |
| 4. INTERPRETATIONS AND ADDENDA |
| 5. BID SECURITY OR BID BOND |
| 6. CONTRACT TIME |
| 7. LIQUIDATED DAMAGES |
| 8. SUBSTITUTE MATERIAL AND EQUIPMENT |
| 9. SUBCONTRACTORS |
| 10. BID/PROPOSAL FORM |
| 11. SUBMISSION OF BIDS |
| 12. MODIFICATION AND WITHDRAWAL OF BIDS |
| 13. REJECTION OF BIDS |
| 14. DISQUALIFICATION OF BIDDER |
| 15. OPENING OF BIDS |
| 16. LICENSES, PERMITS, ROYALTY FEES AND TAXES |
| 17. IDENTICAL TIE BIDS/VENDOR DRUG FREE WORKPLACE |
| 18. AWARD OF CONTRACT |
| 19. BID PROTEST |
| 20. TRENCH SAFETY ACT |
| 21. CONSTRUCTION SITE EROSION AND SEDIMENT CONTROL MANAGEMENT MEASURES |
| SectionIII - 2025_0709.pdf |
| 1. DEFINITIONS |
| 2. PRELIMINARY MATTERS |
| 2.1. DELIVERY OF BONDS AND CERTIFICATES OF INSURANCE |
| 2.2. COPIES OF DOCUMENTS |
| 2.3. COMMENCEMENT OF CONTRACT TIME/NOTICE TO PROCEED, STARTING THE PROJECT |
| 2.4. BEFORE STARTING CONSTRUCTION |
| 2.5. PRECONSTRUCTION CONFERENCE |
| 2.6. PROGRESS MEETINGS |
| 3. CONTRACT DOCUMENTS, INTENT |
| 3.1. INTENT |
| 3.2. REPORTING AND RESOLVING DISCREPANCIES |
| 4. AVAILABILITY OF LANDS, SUBSURFACE AND PHYSICAL CONDITIONS, REFERENCE POINTS |
| 4.1. AVAILABILITY OF LANDS |
| 4.2. INVESTIGATIONS AND REPORTS |
| 4.3. PHYSICAL CONDITIONS, UNDERGROUND FACILITIES |
| 4.4. REFERENCE POINTS |
| 5. BONDS AND INSURANCE |
| 5.1. PERFORMANCE AND PAYMENT BOND/CONTRACT BOND |
| 5.2. INSURANCE REQUIREMENTS |
| 5.2.1. COMMERCIAL GENERAL LIABILITY INSURANCE |
| 5.2.2. COMMERCIAL AUTOMOBILE LIABILITY INSURANCE |
| 5.2.3. WORKERS’ COMPENSATION AND EMPLOYER’S LIABILITY INSURANCE |
| 5.2.4. PROFESSIONAL LIABILITY/MALPRACTICE/ERRORS OR OMISSIONS INSURANCE |
| 5.2.5. CONTRACTOR’S EQUIPMENT/INLAND MARINE/PROPERTY INSURANCE |
| 5.2.6. BUILDER’S RISK INSURANCE |
| 5.3. OTHER INSURANCE PROVISIONS |
| 5.4. WAIVER OF RIGHTS |
| 6. CONTRACTOR’S RESPONSIBILITIES |
| 6.1. SUPERVISION AND SUPERINTENDENCE |
| 6.2. LABOR, MATERIALS AND EQUIPMENT |
| 6.3. SUBSTITUTES AND "OR EQUAL" ITEMS |
| 6.4. SUBCONTRACTORS, SUPPLIERS AND OTHERS |
| 6.5. USE OF PREMISES |
| 6.5.1. STAGING AREAS |
| 6.5.2. RESTORATION TIME LIMITS |
| 6.6. LICENSE AND PATENT FEES, ROYALTIES AND TAXES |
| 6.7. LAWS AND REGULATIONS |
| 6.7.1. E-VERIFY |
| 6.8. PERMITS |
| 6.9. SAFETY AND PROTECTION |
| 6.10. EMERGENCIES |
| 6.11. DRAWINGS |
| 6.11.1. SHOP DRAWINGS, SAMPLES, RFIs, AND SUBMITTAL REVIEW |
| 6.11.2. AS-BUILT DRAWINGS |
| 6.11.2.1. General |
| 6.11.2.2. Sanitary and Storm Sewer Piping Systems |
| 6.11.2.3. Pressure Pipe construction (Water, Reclaimed Water, Force Main) |
| 6.11.2.4. Electrical and Control Wiring |
| 6.11.2.5. Horizontal and Vertical Control |
| 6.11.2.6. Standards |
| 6.11.2.7. Other |
| 6.11.3. CAD STANDARDS |
| 6.11.3.1. Layer Naming |
| 6.11.3.1.1. Prefixes and Suffixes |
| 6.11.3.1.2. Layer Naming Definitions: |
| 6.11.3.2. Layer Properties |
| 6.11.3.3. Text Styles |
6.11.4. DELIVERABLES
| 6.12. CONTRACTOR'S GENERAL WARRANTY AND GUARANTEE |
| 6.13. CONTINUING THE WORK |
| 6.14. INDEMNIFICATION |
| 6.15. CHANGES IN COMPANY CONTACT INFORMATION |
| 6.16. PUBLIC RECORDS |
| 7. OTHER WORK |
| 7.1. RELATED WORK AT SITE |
| 7.2. COORDINATION |
| 8. OWNER’S RESPONSIBILITY |
| 9. OWNER REPRESENTATIVE’S STATUS DURING CONSTRUCTION |
| 9.1. OWNER’S REPRESENTATIVE |
| 9.2. CLARIFICATIONS AND INTERPRETATIONS |
| 9.3. REJECTING OF DEFECTIVE WORK |
| 9.4. SHOP DRAWINGS, CHANGE ORDERS, AND PAYMENTS |
| 9.5. DECISIONS ON DISPUTES |
| 9.6. LIMITATIONS ON OWNER REPRESENTATIVE'S RESPONSIBILITIES |
| 10. CHANGES IN THE WORK |
| 11. CHANGES IN THE CONTRACT PRICE |
| 11.1. CHANGES IN THE CONTRACT PRICE |
| 11.2. ALLOWANCES AND FINAL CONTRACT PRICE ADJUSTMENT |
| 11.3. UNIT PRICE WORK |
| 12. CHANGES IN CONTRACT TIME |
| 13. TESTS AND INSPECTIONS, CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK |
| 13.1. TESTS AND INSPECTION |
| 13.2. UNCOVERING THE WORK |
| 13.3. OWNER’S REPRESENTATIVE MAY STOP THE WORK |
| 13.4. CORRECTION OR REMOVAL OF DEFECTIVE WORK |
| 13.5. WARRANTY/CORRECTION PERIOD |
| 13.6. ACCEPTANCE OF DEFECTIVE WORK |
| 13.7. OWNER MAY CORRECT DEFECTIVE WORK |
| 14. PAYMENTS TO CONTRACTOR AND COMPLETION |
| 14.1. APPLICATION FOR PROGRESS PAYMENT |
| 14.2. CONTRACTOR'S WARRANTY OF TITLE |
| 14.3. REVIEW OF APPLICATIONS FOR PROGRESS PAYMENTS |
| 14.4. PARTIAL UTILIZATION |
| 14.5. FINAL INSPECTION |
| 14.6. FINAL APPLICATION FOR PAYMENT |
| 14.7. FINAL PAYMENT AND ACCEPTANCE |
| 14.8. WAIVER OF CLAIMS |
| 15. SUSPENSION OF WORK AND TERMINATION |
| 15.1. OWNER MAY SUSPEND THE WORK |
| 15.2. OWNER MAY TERMINATE |
| 15.3. CONTRACTOR MAY STOP WORK OR TERMINATE |
| 16. DISPUTE RESOLUTION |
| 17. MISCELLANEOUS |
| 17.1. SUBMITTAL AND DOCUMENT FORMS |
| 17.2. GIVING NOTICE |
| 17.3. NOTICE OF CLAIM |
| 17.4. PROFESSIONAL FEES AND COURT COSTS INCLUDED |
| 17.5. ASSIGNMENT OF CONTRACT |
| 17.6. RENEWAL OPTION |
| 17.7. ROLL-OFF CONTAINERS AND/OR DUMPSTERS |
| 18. ORDER AND LOCATION OF THE WORK |
| 19. MATERIAL USED |
| 20. CONFLICT BETWEEN PLANS AND SPECIFICATIONS |
| 21. OWNER DIRECT PURCHASE (ODP) |
| 21.1. SALES TAX SAVINGS |
| 21.2. TITLE AND OWNER RISK |
| 21.3. CONTRACTOR’S RECEIPT OF MATERIALS |
| 21.4. ODP RECORDS, WARRANTIES, AND INDEMNIFICATION |
| 22. RESIDENT NOTIFICATION OF START OF CONSTRUCTION |
| 22.1. GENERAL |
| 22.2. EXAMPLE |
| 23. PROJECT INFORMATION SIGNS |
| 23.1. SCOPE AND PURPOSE |
| 23.2. PROJECT SIGN, FIXED OR PORTABLE |
| 23.3. FIXED SIGN |
| 23.4. PORTABLE SIGNS |
| 23.5. SIGN COLORING |
| 23.6. SIGN PLACEMENT |
| 23.7. SIGN MAINTENANCE |
| 23.8. TYPICAL PROJECT SIGN |
| 24. AWARD OF CONTRACT, WORK SCHEDULE AND GUARANTEE |
| 25. SCRUTINIZED COMPANIES AND BUSINESS OPERATIONS WITH CUBA AND SYRIA CERTIFICATION FORM AND ISRAEL CERTIFICATION FORM |
| section-iv_6_11_2026.pdf |
| 100 SERIES: GENERAL |
| 101. SCOPE OF WORK |
| 102. FIELD ENGINEERING |
| 102-1. LINE AND GRADE PERFORMED BY THE CONTRACTOR |
| 102-1.1. GRADES, LINES AND LEVELS |
| 102-1.2. LAYOUT DATA |
102-2. LINE AND GRADE PERFORMED BY THE CITY
| 103. DEFINITION OF TERMS |
| 103-1. REFERENCE STANDARDS |
| 104. STREET CROSSINGS, ETC. |
| 105. AUDIO/VIDEO RECORDING OF WORK AREAS |
| 105-1. CONTRACTOR TO PREPARE AUDIO/VIDEO RECORDING |
| 105-2. SCHEDULING OF AUDIO/VIDEO RECORDING |
| 105-3. PROFESSIONAL VIDEOGRAPHERS |
| 105-4. EQUIPMENT |
| 105-5. RECORDED AUDIO INFORMATION |
| 105-6. RECORDED VIDEO INFORMATION |
| 105-7. VIEWER ORIENTATION |
| 105-8. LIGHTING |
| 105-9. SPEED OF TRAVEL |
| 105-10. VIDEO LOG/INDEX |
| 105-11. AREA OF COVERAGE |
| 105-12. COSTS OF VIDEO SERVICES |
| 106. STREET SIGNS |
| 107. WORK ZONE TRAFFIC CONTROL |
| 107-1. CONTRACTOR RESPONSIBLE FOR WORK ZONE TRAFFIC CONTROL |
| 107-2. WORK ZONE TRAFFIC CONTROL PLAN |
| 107-2.1. WORK ZONE SAFETY |
| 107-3. ROADWAY CLOSURE GUIDELINES |
| 107-3.1. ALL ROADWAYS |
| 107-3.1.1. PUBLIC NOTIFICATION |
| 107-3.2. MAJOR ARTERIALS, MINOR ARTERIALS, LOCAL COLLECTORS |
| 107-3.2.1. PUBLIC NOTIFICATION |
| 107-3.3. MAJOR ARTERIALS, MINOR ARTERIALS |
| 107-3.3.1. PUBLIC NOTIFICATION |
| 107-3.4. MAJOR ARTERIALS |
| 107-3.4.1. PUBLIC NOTIFICATION |
| 107-4. APPROVAL OF WORK ZONE TRAFFIC CONTROL PLAN |
| 107-5. INSPECTION OF WORK ZONE TRAFFIC CONTROL OPERATION |
| 107-6. PAYMENT FOR WORK ZONE TRAFFIC CONTROL |
| 107-7. CERTIFICATION OF WORK ZONE TRAFFIC CONTROL SUPERVISOR |
| 108. OVERHEAD ELECTRIC LINE CLEARANCE |
| 108-1. CLEARANCE OPTIONS |
| 108-2. REQUIRED MINIMUM CLEARANCE DISTANCES |
| 200 SERIES: SITEWORK |
| 201. EXCAVATION FOR UNDERGROUND INFRASTRUCTURE WORK |
| 201-1. EXCAVATION, BACKFILLING, AND COMPACTION FOR UNDERGROUND INFRASTRUCTURE |
| 201-1.1. GENERAL |
| 201-1.2. MATERIALS |
| 201-1.3. CLEARING AND GRUBBING |
| 201-1.3.1. GENERAL |
| 201-1.3.2. CLEARING AND GRUBBING OPERATIONS |
| 201-1.3.3. DISPOSAL OF DEBRIS MATERIAL |
| 201-1.3.4. PRESERVATION OF TREES AND SHRUBBERY |
| 201-1.3.5. PRESERVATION OF DEVELOPED PRIVATE PROPERTY |
| 201-1.3.6. PRESERVATION OF PUBLIC PROPERTY |
| 201-1.4. EXCAVATION PROTECTION |
| 201-1.4.1. SHEETING AND BRACING |
| 201-1.5. EXCAVATING FOR UTILITY STRUCTURES |
| 201-1.6. TRENCH EXCAVATION FOR UTILITY PIPELINES |
| 201-1.6.1. TRENCH EXCAVATION FOR PIPE LAYING - GENERAL |
| 201-1.6.2. LIMITED TRENCH WIDTHS |
| 201-1.6.3. MECHANICAL EXCAVATION |
| 201-1.6.4. PAVEMENT CUTTING |
| 201-1.6.5. ARTIFICIAL FOUNDATIONS IN TRENCHES |
| 201-1.6.6. BELL HOLES |
| 201-1.7. UNDERCUT OF EXCAVATIONS |
| 201-1.8. STABILIZATION OF EXCAVATIONS |
| 201-1.9. BACKFILL AND COMPACTION |
| 201-1.9.1. MATERIALS |
| 201-1.9.2. BACKFILL PLACEMENT AND COMPACTION |
| 201-1.9.3. STRUCTURE FOUNDATION PREPARATION |
| 201-1.10. DRAINAGE FROM EXCAVATIONS |
| 201-1.11. FINAL GRADING |
| 201-1.12. EXCESS EXCAVATED MATERIAL |
| 201-1.13. SETTLEMENT |
| 202. OBSTRUCTIONS |
| 203. DEWATERING |
| 203-1. GENERAL |
| 203-1.1. Definition of Terms for Dewatering System |
| 203-2. OBSERVATION WELLS |
| 203-3. PUMPING AND DRAINAGE - GENERAL |
| 203-3.1. DEWATERING EQUIPMENT |
| 203-3.2. DEWATERING CONSIDERATIONS |
| 203-3.3. DISPOSAL OF PUMPED WATER |
| 203-3.4. GROUNDWATER TREATMENT (IF REQUIRED) |
203-4. PERMIT REQUIREMENTS
| 204. UNSUITABLE MATERIAL REMOVAL |
| 204-1. BASIS OF MEASUREMENT |
| 204-2. BASIS OF PAYMENT |
| 205. UTILITY TIE IN LOCATION MARKING |
| 206. CLEARING AND GRUBBING |
| 206-1. BASIS OF MEASUREMENT |
| 206-2. BASIS OF PAYMENT |
| 207. EROSION AND SEDIMENT CONTROL |
| 207-1. GENERAL |
| 207-2. TRAINING OF PERSONNEL |
| 207-3. STABILIZATION OF DENUDED AREAS |
| 207-4. PROTECTION AND STABILIZATION OF SOIL STOCKPILES |
| 207-5. PROTECTION OF EXISTING STORM SEWER SYSTEMS |
| 207-6. SWALES, DITCHES AND CHANNELS |
| 207-7. UNDERGROUND UTILITY CONSTRUCTION |
| 207-8. MAINTENANCE |
| 207-9. COMPLIANCE |
| 208. CONSTRUCTION AND REPAIR OF SEAWALLS AND OTHER BEACH EROSION CONTROL STRUCTURES |
| 208-1. EXISTING SEAWALLS AND REVETMENTS |
| 208-2. TOP OF CAP ELEVATION |
| 208-3. SEAWALLS AND REVETMENTS LOCATED SEAWARD OF THE CCL |
| 208-4. PLACEMENT OF NEW SEAWALL |
| 208-5. POST CONSTRUCTION SURVEY |
| 208-6. RIP-RAP |
| 208-7. RETAINING WALL IN LIEU OF VERTICAL SEAWALL |
| 209. MAINTENANCE OF OPERATIONS |
| 209-1. GENERAL |
| 209-2. EXECUTION |
| 209-3. BASIS OF MEASUREMENT |
| 210. DETECTION OF FACILITIES |
| 211. RELOCATIONS |
| 211-1. RELOCATION SHOWN ON DRAWINGS |
| 211-2. RELOCATIONS NOT SHOWN ON DRAWINGS |
| 212. RESTORATION PROCEDURES |
| 212-1. INTERIM RESTORATION |
| 212-2. FINAL RESTORATION |
| 300 SERIES: MATERIALS |
| 301. CONCRETE |
| 302. EXCAVATION AND FORMS FOR CONCRETE WORK |
| 302-1. EXCAVATION |
| 302-2. FORMS |
| 303. REINFORCEMENT |
| 303-1. BASIS OF PAYMENT |
| 304. BACKFILL |
| 304-1. MATERIALS AND GENERAL |
| 304-2. TESTING AND INSPECTION |
| 305. RIPRAP |
| 305-1. BASIS OF MEASUREMENT |
| 305-2. BASIS OF PAYMENT |
| 306. FLOWABLE FILL |
| 307. MATERIAL INDEPENDENT TESTING |
| 400 SERIES: SANITARY SEWER |
| 401. SANITARY MANHOLES |
| 401-1. BUILT UP TYPE |
| 401-2. PRECAST TYPE |
| 401-2.1. MANHOLE ADJUSTMENT RINGS (GRADE RINGS) |
| 401-2.2. STAINLESS STEEL MANHOLE STORM WATER INFLOW ABATEMENT INSERTS (DISH/PAN) |
| 401-2.2.1. MATERIALS AND DESIGN |
| 401-2.2.2. MEASUREMENT AND PAYMENT |
| 401-3. DROP MANHOLES |
| 401-4. FRAMES AND COVERS |
| 401-5. MANHOLE COATINGS |
| 401-6. CONNECTIONS TO MANHOLES |
| 401-7. MEASUREMENT AND PAYMENT |
| 402. RAISING OR LOWERING OF SANITARY SEWER STRUCTURES |
| 402-1. BASIS OF PAYMENT |
| 403. SANITARY SEWERS AND FORCE MAINS |
| 403-1. MATERIALS |
| 403-1.1. GRAVITY SEWER PIPE |
| 403-1.2. FORCE MAIN PIPE |
| 403-2. INSTALLATION |
| 403-2.1. GRAVITY SEWER PIPE |
| 403-2.2. FORCE MAIN PIPE |
| 403-3. INSPECTIONS OF LINES AND MANHOLES |
| 403-4. TESTING |
| 403-4.1. TESTING OF GRAVITY SEWERS |
| 403-4.2. TESTING OF FORCE MAINS |
| 403-5. BASIS OF PAYMENT |
| 403-5.1. GRAVITY SEWER PIPE |
| 403-5.2. FORCE MAIN PIPE PAYMENT |
| 404. CURED-IN-PLACE PIPE SANITARY SEWER REHABILITATION |
| 404-1. GENERAL |
| 404-2. MEASUREMENT & PAYMENT |
| 404-3. SUBMITTALS |
| 404-4. CURED-IN-PLACE PIPE (CIPP) FOR GRAVITY SEWER MAINS |
| 404-4.1. LINER MATERIAL |
| 404-4.2. CHEMICAL JOINT, CRACK AND ANNULAR SPACE SEALING MATERIALS FOR ACTIVE LEAKS AND SERVICE LATERAL CONNECTIONS |
| 404-4.3. MANHOLE CONNECTIONS |
| 404-4.4. INSTALLATION AND EXECUTION |
| 404-4.4.1. CLEANING/SURFACE PREPARATION |
| 404-4.4.2. TELEVISION INSPECTION |
| 404-4.4.2.1. IMAGE (PHOTOS) CAPTURE FORMAT AND REQUIREMENTS |
| 404-4.4.2.2. DIGITAL VIDEO FORMAT AND REQUIREMENTS |
| 404-4.4.2.3. SYNCHRONIZATION |
| 404-4.4.3. LINER INSTALLATION |
| 404-4.4.4. LATERAL RECONNECTION |
| 404-4.4.5. TIME OF CONSTRUCTION |
| 404-4.4.6. TESTING AND ACCEPTANCE |
| 404-4.4.7. CLEANUP |
| 404-5. CURED-IN-PLACE PIPE (CIPP) FOR SERVICE LATERALS |
| 404-5.1. LINER MATERIAL |
| 404-5.2. EPOXY RESIN MATERIAL |
| 404-5.3. INSTALLATION AND EXECUTION |
| 404-5.3.1. PRE-LINING INSPECTION |
| 404-5.3.2. LATERAL PREPARATION |
| 404-5.3.3. LINER INSTALLATION |
| 404-5.3.4. TESTING AND ACCEPTANCE |
| 405. SANITARY MANHOLE LINER RESTORATION |
| 405-1. SCOPE AND INTENT |
| 405-2. MEASUREMENT & PAYMENT |
| 405-2.1. MANHOLE LINERS/COATING |
| 405-2.2. REPLACE FRAME & COVER |
| 405-2.3. REBUILD BENCH & CHANNEL/TROUGH |
| 405-2.4. RESET/ADJUST MANHOLE FRAME & COVER |
| 405-2.5. SEAL MANHOLE FRAME TO CORBEL CONNECTION WITH POLYUREA MATERIAL |
| 405-3. CEMENTITIOUS COATING SYSTEM |
| 405-3.1. SUBMITTALS |
| 405-3.2. MATERIALS |
| 405-3.2.1. PATCHING MIX |
| 405-3.2.2. INFILTRATION CONTROL |
| 405-3.2.3. GROUTING MIX |
| 405-3.2.4. COATING MIX |
| 405-3.2.5. WATER |
| 405-3.2.6. OTHER MATERIALS |
| 405-3.3. APPLICATION EQUIPMENT |
| 405-3.4. INSTALLATION AND EXECUTION |
| 405-3.4.1. PREPARATION |
| 405-3.4.2. MIXING |
| 405-3.4.3. SPRAYING |
| 405-3.4.4. PREPARATION OF SAMPLES |
| 405-3.4.5. CURING |
405-3.5. TESTING AND ACCEPTANCE
| 405-4. RAVEN 405 EPOXY COATING SYSTEM |
| 405-4.1. SUBMITTALS |
| 405-4.2. MATERIALS |
| 405-4.2.1. PATCHING MIX |
| 405-4.2.2. INFILTRATION CONTROL |
| 405-4.2.3. GROUTING MIX |
| 405-4.2.4. COATING MATERIAL |
| 405-4.2.5. OTHER MATERIALS |
| 405-4.3. INSTALLATION AND EXECUTION |
| 405-4.3.1. PREPARATION |
| 405-4.3.2. APPLICATION |
405-4.4. TESTING & ACCEPTANCE
| 405-5. SPRAYWALL POLYURETHANE COATING SYSTEM |
| 405-5.1. SUBMITTALS |
| 405-5.2. MATERIALS |
| 405-5.2.1. PATCHING MIX |
| 405-5.2.2. INFILTRATION CONTROL |
| 405-5.2.3. GROUTING MIX |
| 405-5.2.4. COATING MATERIAL |
| 405-5.2.5. OTHER MATERIALS |
| 405-5.3. INSTALLATION AND EXECUTION |
| 405-5.3.1. PREPARATION |
| 405-5.3.2. APPLICATION |
405-5.4. TESTING & ACCEPTANCE
| 405-6. INTERNAL MANHOLE CORBEL SEALING SYSTEM |
| 405-6.1. SUBMITTALS |
| 405-6.2. MATERIALS |
| 405-6.2.1. PATCHING MIX |
| 405-6.2.2. INFILTRATION CONTROL |
| 405-6.2.3. COATING MATERIAL |
| 405-6.3. INSTALLATION AND EXECUTION |
| 405-6.3.1. PREPARATION |
| 405-6.3.2. APPLICATION |
| 405-6.3.3. TESTING & ACCEPTANCE |
| 406. SMOKE AND DYE TESTING |
| 406-1. GENERAL PROTOCOL |
| 406-2. REPORTING |
| 406-3. DYE INVESTIGATION |
| 406-3.1. DYE WATER TRACING |
| 406-3.2. DYE WATER FLOODING |
| 406-4. MEASUREMENT AND PAYMENT |
| 406-5. BASIS OF PAYMENT |
| 500 SERIES: POTABLE AND RECLAIMED WATER MAINS, FIRE LINES AND APPURTENANCES |
| 501. SCOPE |
| 502. MATERIALS |
| 502-1. GENERAL |
| 502-2. PIPE MATERIALS AND FITTINGS |
| 502-2.1. DUCTILE IRON PIPE |
| 502-2.1.1. MANUFACTURED RESTRAINED JOINTS FOR DUCTILE IRON PIPE |
| 502-2.1.2. ALTERNATE MECHANICALLY RESTRAINED JOINTS FOR DI PIPE |
| 502-2.1.2.1. Restraints for Ductile Iron Pipe with Mechanical Joint Fittings |
| 502-2.1.2.2. Restraints for Ductile Iron Pipe with Push-on Joints |
| 502-2.1.3. Ductile Iron Pipe Installed with Steel Casings |
| 502-2.1.4. POLYETHYLENE ENCASEMENT FOR BURIED DUCTILE IRON PIPE |
| 502-2.2. POLYVINYL CHLORIDE (PVC) PIPE |
| 502-2.2.1. RESTRAINED JOINT PVC PIPE (DIRECTIONAL BORE) |
| 502-2.3. HIGH DENSITY POLYETHYLENE (HDPE) PIPE |
| 502-2.3.1. MECHANICAL JOINT ADAPTERS (MJ ADPATERS) |
| 502-2.3.2. BUTT FUSION PROCESS AND INSTALLATION |
| 502-2.4. PIPING IDENTIFICATION SYSTEM |
| 502-2.4.1. EXTERIOR MARKINGS FOR BURIED PIPE |
| 502-2.4.2. LOCATION DETECTION WIRE: |
| 502-2.4.3. WARNING TAPE: |
502-2.5. RESTRAINED JOINT COUPLINGS
| 502-3. GATE VALVES |
| 502-4. VALVE BOXES |
| 502-5. HYDRANTS |
| 502-6. SERVICE SADDLES/ POLYETHYLENE SERVICE LINES |
| 502-7. BACKFLOW PREVENTERS |
| 502-8. TAPPING SLEEVES AND LINESTOPS |
| 502-9. LINE STOPPING ASSEMBLIES |
| 502-10. BLOW OFF HYDRANTS |
| 503. CONSTRUCTION |
| 503-1. MATERIAL HANDLING |
| 503-2. PIPE LAYING |
| 503-2.1. INSPECTION PRIOR TO INSTALLATION |
| 503-2.2. GENERAL INSTALLATION REQUIREMENTS |
| 503-2.3. INSTALLATION OF DUCTILE IRON PIPE |
| 503-2.4. INSTALLATION OF POLYVINYL CHLORIDE (PVC) PIPE |
| 503-2.5. DIRECTIONAL BORING INSTALLATION |
| 503-2.5.1. GENERAL REQUIREMENTS |
| 503-2.5.2. SUBMITTALS |
| 503-2.5.3. QUALITY ASSURANCE AND COORDINATION OF WORK |
| 503-2.5.4. HDD PIPE PRODUCTS |
| 503-2.5.5. GENERAL HDD INSTALLATION CONSIDERATION |
| 503-2.5.6. HDD DRILLING EQUIPMENT AND DRILLING FLUID |
| 503-2.5.7. PREPARATION AND MOBILIZATION FOR HDD OPERATIONS |
| 503-2.5.8. ENVIRONMENTAL REQUIREMENTS |
| 503-2.5.9. DRILLING OPERATIONS |
| 503-2.5.10. HDD INSTALLATION |
| 503-2.5.11. DRILLING MUD AND CUTTINGS |
| 503-2.5.12. REAMING AND PULLBACK |
| 503-2.5.13. PIPELINE PROTECTION |
| 503-2.5.14. PIPELINE CLEANING |
| 503-2.5.15. PIPELINE TESTING |
| 503-2.5.16. DISINFECTION FOR HDD POTABLE WATER PIPELINES |
| 503-2.5.17. CITY ACCEPTANCE |
| 503-2.5.18. REPAIR |
| 503-2.5.19. CLEANUP AND REPAIR |
| 503-3. SETTING OF VALVES, HYDRANTS AND FITTINGS |
| 503-3.1. GENERAL |
| 503-3.2. Fittings |
| 503-3.3. VALVES |
| 503-3.4. FIRE HYDRANTS |
| 503-3.5. ANCHORAGE |
503-4. CONNECTIONS TO EXISTING POTABLE WATER OR RECLAIMED WATER LINES
| 504. PIPELINE CLEANING |
| 504-1. PIPELINE PIGGING |
| 504-2. FINAL PIPELINE FLUSHING |
| 505. TESTS |
| 505-1. HYDROSTATIC PIPELINE TESTING |
| 505-2. NOTICE OF TEST |
| 506. DISINFECTION AND TESTING |
| 506-1. DISINFECTION MATERIALS |
| 506-2. FLUSHING SYSTEM |
| 506-3. FINAL DISINFECTION PROCEDURE FOR POTABLE WATER MAINS |
| 506-4. FLUSHING AND RESIDUAL CHLORINE TESTS |
| 506-5. BACTERIALOGICAL TESTS |
| 507. CORRECTION OF NON-CONFORMING WORK |
| 508. OBTAINING WATER FOR FLUSHING AND TESTING |
| 509. MEASUREMENT AND PAYMENT |
| 509-1. GENERAL |
| 509-2. FURNISH AND INSTALL WATER MAINS |
| 509-2.1. MEASUREMENT |
| 509-2.2. PAYMENT |
| 509-3. FURNISH AND INSTALL FITTINGS |
| 509-3.1. MEASUREMENT |
| 509-3.2. PAYMENT |
| 509-4. FURNISH AND INSTALL GATE VALVES COMPLETE WITH BOXES AND COVERS |
| 509-4.1. MEASUREMENT |
| 509-4.2. PAYMENT |
| 509-5. FURNISH AND INSTALL FIRE HYDRANTS |
| 509-5.1. MEASUREMENT |
| 509-5.2. PAYMENT |
| 600 SERIES: STORMWATER |
| 601. RAISING OR LOWERING OF STORM DRAINAGE STRUCTURES |
| 601-1. BASIS OF PAYMENT |
| 602. UNDERDRAINS |
| 602-1. BASIS OF MEASUREMENT |
| 602-2. BASIS OF PAYMENT |
| 603. STORM SEWERS |
| 603-1. TESTING AND INSPECTION |
| 603-2. BASIS OF PAYMENT |
| 604. STORM MANHOLES, INLETS, CATCH BASINS OR OTHER STORM STRUCTURES |
| 604-1. BUILT UP TYPE STRUCTURES |
| 604-2. PRECAST TYPE |
| 604-3. BASIS OF PAYMENT |
| 605. GABIONS AND MATTRESSES |
| 605-1. MATERIAL |
| 605-1.1. PVC COATED WIRE MESH GABIONS & MATTRESSES |
| 605-1.1.1. GABION & MATTRESS BASKETS |
| 605-1.1.2. PVC (POLYVINYL CHLORIDE) COATING |
| 605-1.1.3. GABION AND MATTRESS FILLER MATERIAL |
| 605-1.1.4. GEOTEXTILE FABRIC |
605-2. PERFORMANCE
| 700 SERIES: STREETS AND SIDEWALKS |
| 701. RESTORATION OR REPLACEMENT OF DRIVEWAYS, CURBS, SIDEWALKS AND STREET PAVEMENT |
| 702. ROADWAY BASE AND SUBGRADE |
| 702-1. BASE |
| 702-1.1. BASIS OF MEASUREMENT FOR BASE AND REWORKED BASE |
| 702-1.2. BASIS OF PAYMENT FOR BASE AND REWORKED BASE |
| 702-2. SUBGRADE |
| 702-2.1. BASIS OF MEASUREMENT |
| 702-2.2. BASIS OF PAYMENT |
| 703. ASPHALTIC CONCRETE MATERIALS |
| 703-1. ASPHALTIC CONCRETE |
| 703-1.1. AGGREGATE |
| 703-1.2. BITUMINOUS MATERIALS |
| 703-2. HOT BITUMINOUS MIXTURES – PLANT, METHODS, EQUIPMENT & QUALITY ASSURANCE |
| 703-3. ASPHALT MIX DESIGNS AND TYPES |
| 703-4. ASPHALT PAVEMENT DESIGNS AND LAYER THICKNESS |
| 703-5. GENERAL CONSTRUCTION REQUIREMENTS |
| 703-6. CRACKS AND POTHOLE PREPARATION |
| 703-6.1. CRACKS |
| 703-6.2. POTHOLES |
| 703-7. ADJUSTMENT OF MANHOLES AND APPURTANENCES |
| 703-8. ADDITIONAL ASPHALT REQUIREMENTS |
| 703-9. BASIS OF MEASUREMENT |
| 703-10. BASIS OF PAYMENT |
| 704. ADJUSTMENT TO THE UNIT BID PRICE FOR ASPHALT |
| 705. ASPHALT DRIVEWAYS |
| 705-1. BASIS OF MEASUREMENT |
| 705-2. BASIS OF PAYMENT |
| 706. CONCRETE CURBS |
| 706-1. BASIS OF MEASUREMENT |
| 706-2. BASIS OF PAYMENT |
| 707. CONCRETE SIDEWALKS AND DRIVEWAYS |
| 707-1. CONCRETE SIDEWALKS |
| 707-2. CONCRETE DRIVEWAYS |
| 707-3. CONCRETE CURB RAMPS |
| 707-4. BASIS OF MEASUREMENT |
| 707-5. BASIS OF PAYMENT |
| 708. MILLING OPERATIONS |
| 708-1. EQUIPMENT, CONSTRUCTION & MILLED SURFACE |
| 708-2. ADDITIONAL MILLING REQUIREMENTS |
| 708-3. SALVAGEABLE MATERIALS |
| 708-4. DISPOSABLE MATERIALS |
| 708-5. ADJUSTMENT AND LOCATION OF UNDERGROUND UTILITIES |
| 708-6. ADJUSTMENT OF UTILITY MANHOLES |
| 708-7. TYPES OF MILLING |
| 708-8. MILLING OF INTERSECTIONS |
| 708-9. BASIS OF MEASUREMENT |
| 708-10. BASIS OF PAYMENT |
| 800 SERIES: TRAFFIC SIGNALS, SIGNS AND MARKINGS |
| 801. TRAFFIC SIGNAL EQUIPMENT AND MATERIALS |
| 801-1. BASIS OF MEASUREMENT AND PAYMENT |
| 802. SIGNING AND MARKING |
| 802-1. BASIS OF MEASUREMENT AND PAYMENT |
| 803. ROADWAY LIGHTING |
| 803-1. BASIS OF MEASUREMENT AND PAYMENT |
| 900 SERIES: LANDSCAPING/RESTORATION |
| 901. WORK IN EASEMENTS OR PARKWAYS |
| 902. GENERAL PLANTING SPECIFICATIONS |
| 902-1. IRRIGATION |
| 902-1.1. DESCRIPTION |
| 902-1.1.1. QUALITY ASSURANCE |
| 902-1.1.2. PROJECT CONDITIONS |
| 902-1.1.3. WARRANTY |
| 902-1.2. PRODUCTS |
| 902-1.2.1. GENERAL |
| 902-1.2.2. PIPING |
| 902-1.2.3. PIPE FITTINGS |
| 902-1.2.4. PVC PIPE CEMENT AND PRIMER |
| 902-1.2.5. THREADED CONNECTIONS |
| 902-1.2.6. GATE VALVES |
| 902-1.2.6.1. MANUAL GATE VALVES TWO INCHES (2”) AND SMALLER |
| 902-1.2.6.2. GATE VALVES TWO AND A HALF INCHES (2½”) AND LARGER |
| 902-1.2.7. SLEEVES |
| 902-1.2.8. REMOTE CONTROL VALVES |
| 902-1.2.9. VALVE BOXES |
| 902-1.2.10. AUTOMATIC CONTROL TIMER |
| 902-1.2.11. FIELD TRANSMITTER |
| 902-1.3. EXECUTION |
| 902-1.3.1. GENERAL INSTALLATION REQUIREMENTS |
| 902-1.3.2. EXCAVATING AND BACKFILLING |
| 902-1.3.2.1. TRENCHING - GENERAL |
| 902-1.3.2.2. BACKFILLING |
| 902-1.3.2.3. ROUTING OF PIPING |
| 902-1.3.3. INSTALLATION |
| 902-1.3.3.1. WATER SUPPLY |
| 902-1.3.3.2. ASSEMBLIES |
| 902-1.3.3.3. SLEEVES: (EXISTING BY CITY OF CLEARWATER) |
| 902-1.3.3.4. PLASTIC PIPE |
| 902-1.3.3.5. CONTROLLERS |
| 902-1.3.3.6. REMOTE CONTROL VALVES |
| 902-1.3.3.7. GATE VALVES |
| 902-2. LANDSCAPE |
| 902-2.1. GENERAL |
| 902-2.1.1. REQUIREMENTS OF REGULATORY AGENCIES |
| 902-2.1.2. SCOPE OF WORK |
| 902-2.1.3. QUALITY ASSURANCE |
| 902-2.1.4. SUBMITTALS |
| 902-2.1.5. ALTERNATES, ADDITIONS, DELETIONS, SUBSTITUTIONS |
| 902-2.1.6. ABBREVIATIONS/DEFINITIONS |
| 902-2.1.7. PRODUCT DELIVERY, STORAGE, AND HANDLING |
| 902-2.1.7.1. PLANT MATERIALS |
| 902-2.1.8. JOB CONDITIONS |
| 902-2.1.8.1. ACCEPTANCE OF JOB CONDITIONS. |
| 902-2.1.8.2. SCHEDULING OF WORK |
| 902-2.1.8.3. UTILITIES |
| 902-2.2. PRODUCTS |
| 902-2.2.1. MATERIALS |
| 902-2.2.1.1. PLANT MATERIALS: NOMENCLATURE |
| 902-2.2.1.2. PLANT MATERIALS: QUALITY ASSURANCE |
| 902-2.2.1.3. GRASSES: SOD OR SEED |
| 902-2.2.1.4. MULCH |
| 902-2.2.1.5. STAKES AND GUYS |
| 902-2.2.1.6. PLANTING SOIL |
| 902-2.2.1.7. TREE PROTECTION |
| 902-2.2.1.8. ROOT BARRIER SYSTEM |
| 902-2.2.1.9. PACKAGED MATERIALS |
| 902-2.2.1.10. PESTICIDES |
| 902-2.3. EXECUTION |
| 902-2.3.1. PREPARATION |
| 902-2.3.1.1. OBSTRUCTIONS BELOW GROUND |
| 902-2.3.1.2. GRADING AND PREPARATION FOR PLANT MATERIALS |
| 902-2.3.1.3. PREPARATION FOR ANNUAL BED PLANTING |
| 902-2.3.1.4. PREPARATION FOR SEEDING AND SOD AREAS |
| 902-2.3.2. INSTALLATION |
| 902-2.3.2.1. BERM CONSTRUCTION (IF SPECIFIED) |
| 902-2.3.2.2. LAYOUT OF PLANT MATERIALS |
| 902-2.3.2.3. PLANTING PROCEDURES |
| 902-2.3.2.4. SODDING |
| 902-2.3.2.5. SEEDING |
| 902-2.3.2.6. TREE GUYING, BRACING AND STAKING |
| 902-2.3.2.7. MULCHING |
| 902-2.3.2.8. CLEAN-UP |
| 902-2.3.2.9. PROTECTION |
| 902-2.3.2.10. REPAIR OF DAMAGES |
| 902-2.3.3. MAINTENANCE |
| 902-2.3.4. INSPECTION, REJECTION, AND ACCEPTANCE |
| 902-2.3.4.1. INSPECTION |
| 902-2.3.4.2. REJECTION AND REPLACEMENT |
| 902-2.3.4.3. ACCEPTANCE |
902-2.3.5. WARRANTY
| 903. SODDING |
| 904. SEEDING |
| 905. LAWN MAINTENANCE SPECIFICATIONS |
| 905-1. SCOPE |
| 905-2. SCHEDULING OF WORK |
| 905-3. WORK METHODS |
| 905-3.1. MAINTENANCE SCHEDULING |
| 905-3.2. DUTIES PER SERVICE VISIT |
| 905-3.2.1. LITTER AND DEBRIS |
| 905-3.2.2. VISUAL CHECK |
| 905-3.2.3. PLANT TRIMMING AND PALM PRUNING |
| 905-3.2.3.1. TRAFFIC CONTROL |
| 905-3.2.3.2. PEDESTRIAN SAFETY |
| 905-3.2.4. WEED REMOVAL IN LANDSCAPED AREA |
| 905-3.2.5. MULCH CONDITION |
| 905-3.2.6. IRRIGATION SERVICE AND REPAIR |
| 905-3.2.7. LAWN AND ORNAMENTAL PEST CONTROL |
| 905-3.2.8. PALM FERTILIZATION |
| 905-3.2.9. FREEZE PROTECTION |
| 906. LEVEL OF SERVICE |
| 907. COMPLETION OF WORK |
| 908. INSPECTION AND APPROVAL |
| 909. SPECIAL CONDITIONS |
| 910. TREE PROTECTION |
| 910-1. TREE BARRICADES |
| 910-2. ROOT PRUNING |
| 910-3. PROPER TREE PRUNING |
| 911. IRRIGATION SYSTEM DESIGN |
| 912. IRRIGATION SYSTEM INSTALLATION |
| SectionV - 2025_0709 6 11 2026.pdf |
| PUBLIC CONSTRUCTION BOND |
| CONTRACT |
| CONSENT OF SURETY TO FINAL PAYMENT |
| PROPOSAL/BID BOND |
| AFFIDAVIT |
| NON-COLLUSION AFFIDAVIT |
| PROPOSAL |
| CITY OF CLEARWATER ADDENDUM SHEET |
| BIDDER’S PROPOSAL |
| SCRUTINIZED COMPANIES AND BUSINESS OPERATIONS WITH CUBA AND SYRIA CERTIFICATION FORM |
| SCRUTINIZED COMPANIES THAT BOYCOTT ISRAEL LIST CERTIFICATION FORM |
| Appendix - 2025_0709.pdf |
| OWNER DIRECT PURCHASE (ODP) DOCUMENTS [if needed] |
| REQUEST TO REQUISITION FORM |
| PROJECT PERMITS |
| GEOTECHNICAL SOIL REPORT |
| UTILITY WORK SCHEDULES |
| PAGES Appendix - 2025_0709 - Copy2.pdf |
| CONTAMINATION SCREENING EVALUATION REPORT |
| Appendix - 2025_0709a.pdf |
| VERIFICATION OF EMPLOYMENT ELIGIBILITY FORM |
| OWNER DIRECT PURCHASE (ODP) DOCUMENTS (Not Applicable) |
| Owner Direct Purchase (ODP) Instructions |
| SectionV - 2025_0709 6 11 2026.pdf |
| PUBLIC CONSTRUCTION BOND |
| CONTRACT |
| CONSENT OF SURETY TO FINAL PAYMENT |
| PROPOSAL/BID BOND |
| AFFIDAVIT |
| NON-COLLUSION AFFIDAVIT |
| PROPOSAL |
| CITY OF CLEARWATER ADDENDUM SHEET |
| BIDDER’S PROPOSAL |
| SCRUTINIZED COMPANIES AND BUSINESS OPERATIONS WITH CUBA AND SYRIA CERTIFICATION FORM |
| SCRUTINIZED COMPANIES THAT BOYCOTT ISRAEL LIST CERTIFICATION FORM |
| section-iv_6_11_2026.pdf |
| 100 SERIES: GENERAL |
| 101. SCOPE OF WORK |
| 102. FIELD ENGINEERING |
| 102-1. LINE AND GRADE PERFORMED BY THE CONTRACTOR |
| 102-1.1. GRADES, LINES AND LEVELS |
| 102-1.2. LAYOUT DATA |
102-2. LINE AND GRADE PERFORMED BY THE CITY
| 103. DEFINITION OF TERMS |
| 103-1. REFERENCE STANDARDS |
| 104. STREET CROSSINGS, ETC. |
| 105. AUDIO/VIDEO RECORDING OF WORK AREAS |
| 105-1. CONTRACTOR TO PREPARE AUDIO/VIDEO RECORDING |
| 105-2. SCHEDULING OF AUDIO/VIDEO RECORDING |
| 105-3. PROFESSIONAL VIDEOGRAPHERS |
| 105-4. EQUIPMENT |
| 105-5. RECORDED AUDIO INFORMATION |
| 105-6. RECORDED VIDEO INFORMATION |
| 105-7. VIEWER ORIENTATION |
| 105-8. LIGHTING |
| 105-9. SPEED OF TRAVEL |
| 105-10. VIDEO LOG/INDEX |
| 105-11. AREA OF COVERAGE |
| 105-12. COSTS OF VIDEO SERVICES |
| 106. STREET SIGNS |
| 107. WORK ZONE TRAFFIC CONTROL |
| 107-1. CONTRACTOR RESPONSIBLE FOR WORK ZONE TRAFFIC CONTROL |
| 107-2. WORK ZONE TRAFFIC CONTROL PLAN |
| 107-2.1. WORK ZONE SAFETY |
| 107-3. ROADWAY CLOSURE GUIDELINES |
| 107-3.1. ALL ROADWAYS |
| 107-3.1.1. PUBLIC NOTIFICATION |
| 107-3.2. MAJOR ARTERIALS, MINOR ARTERIALS, LOCAL COLLECTORS |
| 107-3.2.1. PUBLIC NOTIFICATION |
| 107-3.3. MAJOR ARTERIALS, MINOR ARTERIALS |
| 107-3.3.1. PUBLIC NOTIFICATION |
| 107-3.4. MAJOR ARTERIALS |
| 107-3.4.1. PUBLIC NOTIFICATION |
| 107-4. APPROVAL OF WORK ZONE TRAFFIC CONTROL PLAN |
| 107-5. INSPECTION OF WORK ZONE TRAFFIC CONTROL OPERATION |
| 107-6. PAYMENT FOR WORK ZONE TRAFFIC CONTROL |
| 107-7. CERTIFICATION OF WORK ZONE TRAFFIC CONTROL SUPERVISOR |
| 108. OVERHEAD ELECTRIC LINE CLEARANCE |
| 108-1. CLEARANCE OPTIONS |
| 108-2. REQUIRED MINIMUM CLEARANCE DISTANCES |
| 200 SERIES: SITEWORK |
| 201. EXCAVATION FOR UNDERGROUND INFRASTRUCTURE WORK |
| 201-1. EXCAVATION, BACKFILLING, AND COMPACTION FOR UNDERGROUND INFRASTRUCTURE |
| 201-1.1. GENERAL |
| 201-1.2. MATERIALS |
| 201-1.3. CLEARING AND GRUBBING |
| 201-1.3.1. GENERAL |
| 201-1.3.2. CLEARING AND GRUBBING OPERATIONS |
| 201-1.3.3. DISPOSAL OF DEBRIS MATERIAL |
| 201-1.3.4. PRESERVATION OF TREES AND SHRUBBERY |
| 201-1.3.5. PRESERVATION OF DEVELOPED PRIVATE PROPERTY |
| 201-1.3.6. PRESERVATION OF PUBLIC PROPERTY |
| 201-1.4. EXCAVATION PROTECTION |
| 201-1.4.1. SHEETING AND BRACING |
| 201-1.5. EXCAVATING FOR UTILITY STRUCTURES |
| 201-1.6. TRENCH EXCAVATION FOR UTILITY PIPELINES |
| 201-1.6.1. TRENCH EXCAVATION FOR PIPE LAYING - GENERAL |
| 201-1.6.2. LIMITED TRENCH WIDTHS |
| 201-1.6.3. MECHANICAL EXCAVATION |
| 201-1.6.4. PAVEMENT CUTTING |
| 201-1.6.5. ARTIFICIAL FOUNDATIONS IN TRENCHES |
| 201-1.6.6. BELL HOLES |
| 201-1.7. UNDERCUT OF EXCAVATIONS |
| 201-1.8. STABILIZATION OF EXCAVATIONS |
| 201-1.9. BACKFILL AND COMPACTION |
| 201-1.9.1. MATERIALS |
| 201-1.9.2. BACKFILL PLACEMENT AND COMPACTION |
| 201-1.9.3. STRUCTURE FOUNDATION PREPARATION |
| 201-1.10. DRAINAGE FROM EXCAVATIONS |
| 201-1.11. FINAL GRADING |
| 201-1.12. EXCESS EXCAVATED MATERIAL |
| 201-1.13. SETTLEMENT |
| 202. OBSTRUCTIONS |
| 203. DEWATERING |
| 203-1. GENERAL |
| 203-1.1. Definition of Terms for Dewatering System |
| 203-2. OBSERVATION WELLS |
| 203-3. PUMPING AND DRAINAGE - GENERAL |
| 203-3.1. DEWATERING EQUIPMENT |
| 203-3.2. DEWATERING CONSIDERATIONS |
| 203-3.3. DISPOSAL OF PUMPED WATER |
| 203-3.4. GROUNDWATER TREATMENT (IF REQUIRED) |
203-4. PERMIT REQUIREMENTS
| 204. UNSUITABLE MATERIAL REMOVAL |
| 204-1. BASIS OF MEASUREMENT |
| 204-2. BASIS OF PAYMENT |
| 205. UTILITY TIE IN LOCATION MARKING |
| 206. CLEARING AND GRUBBING |
| 206-1. BASIS OF MEASUREMENT |
| 206-2. BASIS OF PAYMENT |
| 207. EROSION AND SEDIMENT CONTROL |
| 207-1. GENERAL |
| 207-2. TRAINING OF PERSONNEL |
| 207-3. STABILIZATION OF DENUDED AREAS |
| 207-4. PROTECTION AND STABILIZATION OF SOIL STOCKPILES |
| 207-5. PROTECTION OF EXISTING STORM SEWER SYSTEMS |
| 207-6. SWALES, DITCHES AND CHANNELS |
| 207-7. UNDERGROUND UTILITY CONSTRUCTION |
| 207-8. MAINTENANCE |
| 207-9. COMPLIANCE |
| 208. CONSTRUCTION AND REPAIR OF SEAWALLS AND OTHER BEACH EROSION CONTROL STRUCTURES |
| 208-1. EXISTING SEAWALLS AND REVETMENTS |
| 208-2. TOP OF CAP ELEVATION |
| 208-3. SEAWALLS AND REVETMENTS LOCATED SEAWARD OF THE CCL |
| 208-4. PLACEMENT OF NEW SEAWALL |
| 208-5. POST CONSTRUCTION SURVEY |
| 208-6. RIP-RAP |
| 208-7. RETAINING WALL IN LIEU OF VERTICAL SEAWALL |
| 209. MAINTENANCE OF OPERATIONS |
| 209-1. GENERAL |
| 209-2. EXECUTION |
| 209-3. BASIS OF MEASUREMENT |
| 210. DETECTION OF FACILITIES |
| 211. RELOCATIONS |
| 211-1. RELOCATION SHOWN ON DRAWINGS |
| 211-2. RELOCATIONS NOT SHOWN ON DRAWINGS |
| 212. RESTORATION PROCEDURES |
| 212-1. INTERIM RESTORATION |
| 212-2. FINAL RESTORATION |
| 300 SERIES: MATERIALS |
| 301. CONCRETE |
| 302. EXCAVATION AND FORMS FOR CONCRETE WORK |
| 302-1. EXCAVATION |
| 302-2. FORMS |
| 303. REINFORCEMENT |
| 303-1. BASIS OF PAYMENT |
| 304. BACKFILL |
| 304-1. MATERIALS AND GENERAL |
| 304-2. TESTING AND INSPECTION |
| 305. RIPRAP |
| 305-1. BASIS OF MEASUREMENT |
| 305-2. BASIS OF PAYMENT |
| 306. FLOWABLE FILL |
| 307. MATERIAL INDEPENDENT TESTING |
| 400 SERIES: SANITARY SEWER |
| 401. SANITARY MANHOLES |
| 401-1. BUILT UP TYPE |
| 401-2. PRECAST TYPE |
| 401-2.1. MANHOLE ADJUSTMENT RINGS (GRADE RINGS) |
| 401-2.2. STAINLESS STEEL MANHOLE STORM WATER INFLOW ABATEMENT INSERTS (DISH/PAN) |
| 401-2.2.1. MATERIALS AND DESIGN |
| 401-2.2.2. MEASUREMENT AND PAYMENT |
| 401-3. DROP MANHOLES |
| 401-4. FRAMES AND COVERS |
| 401-5. MANHOLE COATINGS |
| 401-6. CONNECTIONS TO MANHOLES |
| 401-7. MEASUREMENT AND PAYMENT |
| 402. RAISING OR LOWERING OF SANITARY SEWER STRUCTURES |
| 402-1. BASIS OF PAYMENT |
| 403. SANITARY SEWERS AND FORCE MAINS |
| 403-1. MATERIALS |
| 403-1.1. GRAVITY SEWER PIPE |
| 403-1.2. FORCE MAIN PIPE |
| 403-2. INSTALLATION |
| 403-2.1. GRAVITY SEWER PIPE |
| 403-2.2. FORCE MAIN PIPE |
| 403-3. INSPECTIONS OF LINES AND MANHOLES |
| 403-4. TESTING |
| 403-4.1. TESTING OF GRAVITY SEWERS |
| 403-4.2. TESTING OF FORCE MAINS |
| 403-5. BASIS OF PAYMENT |
| 403-5.1. GRAVITY SEWER PIPE |
| 403-5.2. FORCE MAIN PIPE PAYMENT |
| 404. CURED-IN-PLACE PIPE SANITARY SEWER REHABILITATION |
| 404-1. GENERAL |
| 404-2. MEASUREMENT & PAYMENT |
| 404-3. SUBMITTALS |
| 404-4. CURED-IN-PLACE PIPE (CIPP) FOR GRAVITY SEWER MAINS |
| 404-4.1. LINER MATERIAL |
| 404-4.2. CHEMICAL JOINT, CRACK AND ANNULAR SPACE SEALING MATERIALS FOR ACTIVE LEAKS AND SERVICE LATERAL CONNECTIONS |
| 404-4.3. MANHOLE CONNECTIONS |
| 404-4.4. INSTALLATION AND EXECUTION |
| 404-4.4.1. CLEANING/SURFACE PREPARATION |
| 404-4.4.2. TELEVISION INSPECTION |
| 404-4.4.2.1. IMAGE (PHOTOS) CAPTURE FORMAT AND REQUIREMENTS |
| 404-4.4.2.2. DIGITAL VIDEO FORMAT AND REQUIREMENTS |
| 404-4.4.2.3. SYNCHRONIZATION |
| 404-4.4.3. LINER INSTALLATION |
| 404-4.4.4. LATERAL RECONNECTION |
| 404-4.4.5. TIME OF CONSTRUCTION |
| 404-4.4.6. TESTING AND ACCEPTANCE |
| 404-4.4.7. CLEANUP |
| 404-5. CURED-IN-PLACE PIPE (CIPP) FOR SERVICE LATERALS |
| 404-5.1. LINER MATERIAL |
| 404-5.2. EPOXY RESIN MATERIAL |
| 404-5.3. INSTALLATION AND EXECUTION |
| 404-5.3.1. PRE-LINING INSPECTION |
| 404-5.3.2. LATERAL PREPARATION |
| 404-5.3.3. LINER INSTALLATION |
| 404-5.3.4. TESTING AND ACCEPTANCE |
| 405. SANITARY MANHOLE LINER RESTORATION |
| 405-1. SCOPE AND INTENT |
| 405-2. MEASUREMENT & PAYMENT |
| 405-2.1. MANHOLE LINERS/COATING |
| 405-2.2. REPLACE FRAME & COVER |
| 405-2.3. REBUILD BENCH & CHANNEL/TROUGH |
| 405-2.4. RESET/ADJUST MANHOLE FRAME & COVER |
| 405-2.5. SEAL MANHOLE FRAME TO CORBEL CONNECTION WITH POLYUREA MATERIAL |
| 405-3. CEMENTITIOUS COATING SYSTEM |
| 405-3.1. SUBMITTALS |
| 405-3.2. MATERIALS |
| 405-3.2.1. PATCHING MIX |
| 405-3.2.2. INFILTRATION CONTROL |
| 405-3.2.3. GROUTING MIX |
| 405-3.2.4. COATING MIX |
| 405-3.2.5. WATER |
| 405-3.2.6. OTHER MATERIALS |
| 405-3.3. APPLICATION EQUIPMENT |
| 405-3.4. INSTALLATION AND EXECUTION |
| 405-3.4.1. PREPARATION |
| 405-3.4.2. MIXING |
| 405-3.4.3. SPRAYING |
| 405-3.4.4. PREPARATION OF SAMPLES |
| 405-3.4.5. CURING |
405-3.5. TESTING AND ACCEPTANCE
| 405-4. RAVEN 405 EPOXY COATING SYSTEM |
| 405-4.1. SUBMITTALS |
| 405-4.2. MATERIALS |
| 405-4.2.1. PATCHING MIX |
| 405-4.2.2. INFILTRATION CONTROL |
| 405-4.2.3. GROUTING MIX |
| 405-4.2.4. COATING MATERIAL |
| 405-4.2.5. OTHER MATERIALS |
| 405-4.3. INSTALLATION AND EXECUTION |
| 405-4.3.1. PREPARATION |
| 405-4.3.2. APPLICATION |
405-4.4. TESTING & ACCEPTANCE
| 405-5. SPRAYWALL POLYURETHANE COATING SYSTEM |
| 405-5.1. SUBMITTALS |
| 405-5.2. MATERIALS |
| 405-5.2.1. PATCHING MIX |
| 405-5.2.2. INFILTRATION CONTROL |
| 405-5.2.3. GROUTING MIX |
| 405-5.2.4. COATING MATERIAL |
| 405-5.2.5. OTHER MATERIALS |
| 405-5.3. INSTALLATION AND EXECUTION |
| 405-5.3.1. PREPARATION |
| 405-5.3.2. APPLICATION |
405-5.4. TESTING & ACCEPTANCE
| 405-6. INTERNAL MANHOLE CORBEL SEALING SYSTEM |
| 405-6.1. SUBMITTALS |
| 405-6.2. MATERIALS |
| 405-6.2.1. PATCHING MIX |
| 405-6.2.2. INFILTRATION CONTROL |
| 405-6.2.3. COATING MATERIAL |
| 405-6.3. INSTALLATION AND EXECUTION |
| 405-6.3.1. PREPARATION |
| 405-6.3.2. APPLICATION |
| 405-6.3.3. TESTING & ACCEPTANCE |
| 406. SMOKE AND DYE TESTING |
| 406-1. GENERAL PROTOCOL |
| 406-2. REPORTING |
| 406-3. DYE INVESTIGATION |
| 406-3.1. DYE WATER TRACING |
| 406-3.2. DYE WATER FLOODING |
| 406-4. MEASUREMENT AND PAYMENT |
| 406-5. BASIS OF PAYMENT |
| 500 SERIES: POTABLE AND RECLAIMED WATER MAINS, FIRE LINES AND APPURTENANCES |
| 501. SCOPE |
| 502. MATERIALS |
| 502-1. GENERAL |
| 502-2. PIPE MATERIALS AND FITTINGS |
| 502-2.1. DUCTILE IRON PIPE |
| 502-2.1.1. MANUFACTURED RESTRAINED JOINTS FOR DUCTILE IRON PIPE |
| 502-2.1.2. ALTERNATE MECHANICALLY RESTRAINED JOINTS FOR DI PIPE |
| 502-2.1.2.1. Restraints for Ductile Iron Pipe with Mechanical Joint Fittings |
| 502-2.1.2.2. Restraints for Ductile Iron Pipe with Push-on Joints |
| 502-2.1.3. Ductile Iron Pipe Installed with Steel Casings |
| 502-2.1.4. POLYETHYLENE ENCASEMENT FOR BURIED DUCTILE IRON PIPE |
| 502-2.2. POLYVINYL CHLORIDE (PVC) PIPE |
| 502-2.2.1. RESTRAINED JOINT PVC PIPE (DIRECTIONAL BORE) |
| 502-2.3. HIGH DENSITY POLYETHYLENE (HDPE) PIPE |
| 502-2.3.1. MECHANICAL JOINT ADAPTERS (MJ ADPATERS) |
| 502-2.3.2. BUTT FUSION PROCESS AND INSTALLATION |
| 502-2.4. PIPING IDENTIFICATION SYSTEM |
| 502-2.4.1. EXTERIOR MARKINGS FOR BURIED PIPE |
| 502-2.4.2. LOCATION DETECTION WIRE: |
| 502-2.4.3. WARNING TAPE: |
502-2.5. RESTRAINED JOINT COUPLINGS
| 502-3. GATE VALVES |
| 502-4. VALVE BOXES |
| 502-5. HYDRANTS |
| 502-6. SERVICE SADDLES/ POLYETHYLENE SERVICE LINES |
| 502-7. BACKFLOW PREVENTERS |
| 502-8. TAPPING SLEEVES AND LINESTOPS |
| 502-9. LINE STOPPING ASSEMBLIES |
| 502-10. BLOW OFF HYDRANTS |
| 503. CONSTRUCTION |
| 503-1. MATERIAL HANDLING |
| 503-2. PIPE LAYING |
| 503-2.1. INSPECTION PRIOR TO INSTALLATION |
| 503-2.2. GENERAL INSTALLATION REQUIREMENTS |
| 503-2.3. INSTALLATION OF DUCTILE IRON PIPE |
| 503-2.4. INSTALLATION OF POLYVINYL CHLORIDE (PVC) PIPE |
| 503-2.5. DIRECTIONAL BORING INSTALLATION |
| 503-2.5.1. GENERAL REQUIREMENTS |
| 503-2.5.2. SUBMITTALS |
| 503-2.5.3. QUALITY ASSURANCE AND COORDINATION OF WORK |
| 503-2.5.4. HDD PIPE PRODUCTS |
| 503-2.5.5. GENERAL HDD INSTALLATION CONSIDERATION |
| 503-2.5.6. HDD DRILLING EQUIPMENT AND DRILLING FLUID |
| 503-2.5.7. PREPARATION AND MOBILIZATION FOR HDD OPERATIONS |
| 503-2.5.8. ENVIRONMENTAL REQUIREMENTS |
| 503-2.5.9. DRILLING OPERATIONS |
| 503-2.5.10. HDD INSTALLATION |
| 503-2.5.11. DRILLING MUD AND CUTTINGS |
| 503-2.5.12. REAMING AND PULLBACK |
| 503-2.5.13. PIPELINE PROTECTION |
| 503-2.5.14. PIPELINE CLEANING |
| 503-2.5.15. PIPELINE TESTING |
| 503-2.5.16. DISINFECTION FOR HDD POTABLE WATER PIPELINES |
| 503-2.5.17. CITY ACCEPTANCE |
| 503-2.5.18. REPAIR |
| 503-2.5.19. CLEANUP AND REPAIR |
| 503-3. SETTING OF VALVES, HYDRANTS AND FITTINGS |
| 503-3.1. GENERAL |
| 503-3.2. Fittings |
| 503-3.3. VALVES |
| 503-3.4. FIRE HYDRANTS |
| 503-3.5. ANCHORAGE |
503-4. CONNECTIONS TO EXISTING POTABLE WATER OR RECLAIMED WATER LINES
| 504. PIPELINE CLEANING |
| 504-1. PIPELINE PIGGING |
| 504-2. FINAL PIPELINE FLUSHING |
| 505. TESTS |
| 505-1. HYDROSTATIC PIPELINE TESTING |
| 505-2. NOTICE OF TEST |
| 506. DISINFECTION AND TESTING |
| 506-1. DISINFECTION MATERIALS |
| 506-2. FLUSHING SYSTEM |
| 506-3. FINAL DISINFECTION PROCEDURE FOR POTABLE WATER MAINS |
| 506-4. FLUSHING AND RESIDUAL CHLORINE TESTS |
| 506-5. BACTERIALOGICAL TESTS |
| 507. CORRECTION OF NON-CONFORMING WORK |
| 508. OBTAINING WATER FOR FLUSHING AND TESTING |
| 509. MEASUREMENT AND PAYMENT |
| 509-1. GENERAL |
| 509-2. FURNISH AND INSTALL WATER MAINS |
| 509-2.1. MEASUREMENT |
| 509-2.2. PAYMENT |
| 509-3. FURNISH AND INSTALL FITTINGS |
| 509-3.1. MEASUREMENT |
| 509-3.2. PAYMENT |
| 509-4. FURNISH AND INSTALL GATE VALVES COMPLETE WITH BOXES AND COVERS |
| 509-4.1. MEASUREMENT |
| 509-4.2. PAYMENT |
| 509-5. FURNISH AND INSTALL FIRE HYDRANTS |
| 509-5.1. MEASUREMENT |
| 509-5.2. PAYMENT |
| 600 SERIES: STORMWATER |
| 601. RAISING OR LOWERING OF STORM DRAINAGE STRUCTURES |
| 601-1. BASIS OF PAYMENT |
| 602. UNDERDRAINS |
| 602-1. BASIS OF MEASUREMENT |
| 602-2. BASIS OF PAYMENT |
| 603. STORM SEWERS |
| 603-1. TESTING AND INSPECTION |
| 603-2. BASIS OF PAYMENT |
| 604. STORM MANHOLES, INLETS, CATCH BASINS OR OTHER STORM STRUCTURES |
| 604-1. BUILT UP TYPE STRUCTURES |
| 604-2. PRECAST TYPE |
| 604-3. BASIS OF PAYMENT |
| 605. GABIONS AND MATTRESSES |
| 605-1. MATERIAL |
| 605-1.1. PVC COATED WIRE MESH GABIONS & MATTRESSES |
| 605-1.1.1. GABION & MATTRESS BASKETS |
| 605-1.1.2. PVC (POLYVINYL CHLORIDE) COATING |
| 605-1.1.3. GABION AND MATTRESS FILLER MATERIAL |
| 605-1.1.4. GEOTEXTILE FABRIC |
605-2. PERFORMANCE
| 700 SERIES: STREETS AND SIDEWALKS |
| 701. RESTORATION OR REPLACEMENT OF DRIVEWAYS, CURBS, SIDEWALKS AND STREET PAVEMENT |
| 702. ROADWAY BASE AND SUBGRADE |
| 702-1. BASE |
| 702-1.1. BASIS OF MEASUREMENT FOR BASE AND REWORKED BASE |
| 702-1.2. BASIS OF PAYMENT FOR BASE AND REWORKED BASE |
| 702-2. SUBGRADE |
| 702-2.1. BASIS OF MEASUREMENT |
| 702-2.2. BASIS OF PAYMENT |
| 703. ASPHALTIC CONCRETE MATERIALS |
| 703-1. ASPHALTIC CONCRETE |
| 703-1.1. AGGREGATE |
| 703-1.2. BITUMINOUS MATERIALS |
| 703-2. HOT BITUMINOUS MIXTURES – PLANT, METHODS, EQUIPMENT & QUALITY ASSURANCE |
| 703-3. ASPHALT MIX DESIGNS AND TYPES |
| 703-4. ASPHALT PAVEMENT DESIGNS AND LAYER THICKNESS |
| 703-5. GENERAL CONSTRUCTION REQUIREMENTS |
| 703-6. CRACKS AND POTHOLE PREPARATION |
| 703-6.1. CRACKS |
| 703-6.2. POTHOLES |
| 703-7. ADJUSTMENT OF MANHOLES AND APPURTANENCES |
| 703-8. ADDITIONAL ASPHALT REQUIREMENTS |
| 703-9. BASIS OF MEASUREMENT |
| 703-10. BASIS OF PAYMENT |
| 704. ADJUSTMENT TO THE UNIT BID PRICE FOR ASPHALT |
| 705. ASPHALT DRIVEWAYS |
| 705-1. BASIS OF MEASUREMENT |
| 705-2. BASIS OF PAYMENT |
| 706. CONCRETE CURBS |
| 706-1. BASIS OF MEASUREMENT |
| 706-2. BASIS OF PAYMENT |
| 707. CONCRETE SIDEWALKS AND DRIVEWAYS |
| 707-1. CONCRETE SIDEWALKS |
| 707-2. CONCRETE DRIVEWAYS |
| 707-3. CONCRETE CURB RAMPS |
| 707-4. BASIS OF MEASUREMENT |
| 707-5. BASIS OF PAYMENT |
| 708. MILLING OPERATIONS |
| 708-1. EQUIPMENT, CONSTRUCTION & MILLED SURFACE |
| 708-2. ADDITIONAL MILLING REQUIREMENTS |
| 708-3. SALVAGEABLE MATERIALS |
| 708-4. DISPOSABLE MATERIALS |
| 708-5. ADJUSTMENT AND LOCATION OF UNDERGROUND UTILITIES |