01320 Const Prog Doc final.doc

DOC document 34 KB Posted

Attached to
Provide and Install Fall Protection Systems at RML
Solicitation number
NIHOF2008057
Issued by

About this file

Construction Progress Documentation

View the file

Other files

File Type Posted
01770 ADG CLOSE OUT PROCEDURES final.doc DOC document
RFP RML Fall Protection Project.doc DOC document
01731 Cutting Patching final.doc DOC document
A0.1.pdf PDF
A3.0.pdf PDF
07725 FALL PROTECTION SYSTEM final.doc DOC document
A3.6.pdf PDF
INDEX Fall Protection.DOC DOC document
01100 Summary final.doc DOC document
01310 Proj Mngmt Coord final.doc DOC document
A3.4.pdf PDF
01600 ADG PROD REQUIREMENTS final.doc DOC document
01330 SUBMTL PROCEDURES final.doc DOC document
SPEC COVER .doc DOC document
01140 Work Restrictions final.doc DOC document
01500 TEMP FACILITIES CONTROL final.doc DOC document
A3.3.pdf PDF
01400 Quality Requirements final.doc DOC document
01420 References final.doc DOC document
A3.2.pdf PDF
sf1449.pdf PDF
A3.1.pdf PDF
A3.5.pdf PDF
01700 Execution Requirements final.doc DOC document
07730 Roof Accessories final.doc DOC document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

07-726

08-811

SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including Sections A through M of the Contract and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's Construction Schedule.

B. Related Sections include the following:

1. Division 1 Section "Project Management and Coordination" for submitting and distributing meeting and conference minutes.

2. Division 1 Section "Submittal Procedures" for submitting schedules and reports.

1.3 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor activity is an activity that must be completed before a given activity can be started.

B. Event: The starting or ending point of an activity.

C. Float: The measure of leeway in starting and completing an activity.

1. Float time belongs to Government.

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the following activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

D. Milestone: A key or critical point in time for reference or measurement.

1.4 SUBMITTALS

A. Preliminary Construction Schedule: Submit two printed copies; one a single sheet of reproducible media, and one a print.

B. Contractor's Construction Schedule: Submit two printed copies of initial schedule, one a reproducible print and one a blue- or black-line print, large enough to show entire schedule for entire construction period.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.

B. Coordinate Contractor's Construction Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. Secure time commitments for performing critical elements of the Work from parties involved.

2. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

C. Auxiliary Services: Cooperate with photographer and provide auxiliary services requested, including access to Project site and use of temporary facilities including temporary lighting.

PART 2 - PRODUCTS

2.1 CONSTRUCTION SCHEDULE

A. Bar-Chart Schedule: Submit preliminary horizontal bar-chart-type construction schedule within seven days of date established for the Notice to Proceed.

B. Preparation: Indicate each significant construction activity separately. Identify first workday of each week with a continuous vertical line. Outline significant construction activities for first 60 days of construction. Include skeleton diagram for the remainder of the Work and a cash requirement prediction based on indicated activities.

PART 3 - EXECUTION (Not Used)

END OF SECTION 01320

FALL PROTECTION ( NIH-NIAID RML ( HAMILTON, MT

CONSTRUCTION PROGRESS DOCUMENTATION 01320 - 1