01140 Work Restrictions final.doc

DOC document 31 KB Posted

Attached to
Provide and Install Fall Protection Systems at RML
Solicitation number
NIHOF2008057
Issued by

About this file

Work Restrictions

View the file

Other files

File Type Posted
01770 ADG CLOSE OUT PROCEDURES final.doc DOC document
A3.2.pdf PDF
sf1449.pdf PDF
A3.1.pdf PDF
01320 Const Prog Doc final.doc DOC document
A3.5.pdf PDF
01700 Execution Requirements final.doc DOC document
07730 Roof Accessories final.doc DOC document
RFP RML Fall Protection Project.doc DOC document
01731 Cutting Patching final.doc DOC document
A0.1.pdf PDF
A3.0.pdf PDF
07725 FALL PROTECTION SYSTEM final.doc DOC document
A3.6.pdf PDF
INDEX Fall Protection.DOC DOC document
01100 Summary final.doc DOC document
01310 Proj Mngmt Coord final.doc DOC document
A3.4.pdf PDF
01600 ADG PROD REQUIREMENTS final.doc DOC document
01330 SUBMTL PROCEDURES final.doc DOC document
SPEC COVER .doc DOC document
01500 TEMP FACILITIES CONTROL final.doc DOC document
A3.3.pdf PDF
01400 Quality Requirements final.doc DOC document
01420 References final.doc DOC document
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

04-436

08-811

SECTION 01140 - WORK RESTRICTIONS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including Sections A through M of the Contract and other Division 1 Specification Sections, apply to this Section.

B. Related Sections:

1. Refer to Section, “Construction Security Requirements” for security procedures.

1.2 USE OF PREMISES

A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to the areas delineated on the “Campus Staging Plan” included on Sheet A0.1.

2. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

c. Keep access to the South and East sides of Building 23 clear at all times.

d. Keep access to the north side of Building 29 clear at all times.

3. The fresh air intakes for the buildings in the Quad are on the east side of the service road between Buildings A and 5; and Buildings 13, 13B and 16. The Contractor is advised that he is required to keep traffic in this area limited to actual ongoing work. Idling of motors for inactive equipment will not be allowed.

B. Hours of work: Refer to Section H of the Contract.

1.3 SECURITY

A. All contractors, suppliers and vendors are subject to search upon entering the Rocky Mountain Laboratories Facility. This includes vehicles, packages, boxes, etc.

1. Two forms of identification will be required for all personnel.

2. A photo identity badge must be worn in plain view while on the RML grounds.

3. Visitors and those without a photo ID Badge will be escorted while on site.

4. Vendors, and suppliers must have paperwork showing what is being delivered and to whom before they will be allowed to enter the facility.

5. All construction delivery trucks must be met at the perimeter gate by an authorized Project Manager, superintendent, etc. and be escorted to their delivery site.

6. All storage units and the inside of these vehicles are subject to inspection.

B. Security measures may be lessened or heightened as National Alert Levels change.

1.4 OCCUPANCY REQUIREMENTS

A. Full Government Occupancy: Government will occupy site and existing building during entire construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's operations.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01140

FALL PROTECTION ( NIH-NIAID RML ( HAMILTON, MT

WORK RESTRICTIONS 01140 - 1